UNIVERSITY OF THE EAST – MANILA

2219 Recto Ave, Sampaloc, Manila, 1008 Metro Manila


BS Civil Engineering On-the-Job Training
ON-THE-JOB TRAINING / PRACTICUM WEEKLY REPORT

Name of Student Trainee: JOSHUA U. TESORO Student Number: 20150114742


Name of Company: VISION PROPERTIES DEVELOPMENT

DAILY WORK ACTIVIES (WEEK1)


No. Of
Day Date Daily Accomplishment working
Hours
Orientation
 About the works that the interns will do
Monday April 29,2019 during their OJT. 8 Hrs.
 about the do’s and don’ts by safety officer
Site Visit
 Familiarized the locations
Tuesday April 30, 2019 8 Hrs.
Studying the Plans of the building

Wednesday May 01, 2019

Lecture
 About the cutting diagram
 About the Rebar works
Thursday May 02, 2019 8 Hrs.
Site Visit
 Application of Rebar works

Lecture
 About the Formworks
Friday May 03, 2019 Site Visit 8 Hrs.
 Knowledge about actual formworks
Inspection

Saturday May 04, 2019

TOTAL NUMBER OF HOURS: 32 HOURS

CERTIFIED BY:

ENGR. CIRILO R. BELAMIDE


PROJECT SUPERINTENDENT
UNIVERSITY OF THE EAST – MANILA
2219 Recto Ave, Sampaloc, Manila, 1008 Metro Manila
BS Civil Engineering On-the-Job Training
ON-THE-JOB TRAINING / PRACTICUM WEEKLY REPORT

Name of Student Trainee: JOSHUA U. TESORO Student Number: 20150114742


Name of Company: VISION PROPERTIES DEVELOPMENT

DAILY WORK ACTIVIES (WEEK2)


No. Of
Day Date Daily Accomplishment working
Hours
 Lecture on how to make Inspection and
Work Request (IWR)
Monday May 06, 2019 8 Hrs.
 Signing the IWR to the Engineers and
Sub Contractors.
Site Visit
Tuesday May 07, 2019  Pouring of Concrete (Podium of Tower 5) 8 Hrs.
 Measure the alignment of Formworks
For Final Inspection
 Tower 4, Zone 1, 11th-12th Floor
(Form Enclosure / Column)
Wednesday May 08, 2019  Tower 4, Zone 3 & 4, 8th – 9th Floor 12 Hrs.
(Concrete Pouring / Column, Corewall and
Shearwall)
Lecture about Cutting Diagram in Podium
For Final Inspection
 Tower 4, Zone 2, 9th-10th Floor
(Concrete Pouring/ Column)
Thursday May 09, 2019  Tower 4, Zone 3, 9th Floor 12 Hrs.
(Concrete Pouring / Slab with beams)
Meeting with the Leadman/Foreman, Project
Engineers, and Project Manager
Lecture about the Productivity
Collecting the Productivity and input in the excel
Site Visit
Friday May 10, 2019  Tower 4 9th-11th Floor
11 Hrs.
 Foundation
 Steel Fabrication
Paper works
 Inspection and Work Request (IWR)
Site Visit
Saturday May 11, 2019 Final Inspection 9 Hrs.
 Tower 4, Zone 3 and 4
 Foundation, Zone 43 and 44

TOTAL NUMBER OF HOURS: 60 HOURS


CERTIFIED BY:

ENGR. CIRILO R. BELAMIDE


PROJECT SUPERINTENDENT
UNIVERSITY OF THE EAST – MANILA
2219 Recto Ave, Sampaloc, Manila, 1008 Metro Manila
BS Civil Engineering On-the-Job Training
ON-THE-JOB TRAINING / PRACTICUM WEEKLY REPORT

Name of Student Trainee: JOSHUA U. TESORO Student Number: 20150114742


Name of Company: VISION PROPERTIES DEVELOPMENT

DAILY WORK ACTIVIES (WEEK3)


No. Of
Day Date Daily Accomplishment working
Hours

Monday May 13, 2019 SPECIAL NON-WORKING HOLIDAY

Site Visit
 Tower 4, 9th-11th Floor
 Podium
Tuesday May 14, 2019 10 Hrs.
 Foundation
Final Inspection
 Podium, Zone 44 and 23
Site Visit
 Tower 4, and Tower 3
Wednesday May 15, 2019 12 Hrs.
Paper works
 Inspection and Work Request (IWR)
Site Visit
 Tower 4
Paper works
Thursday May 16, 2019  Inspection and Work Request (IWR) 12 Hrs.
Final Inspection
 Tower 4, Zone 4, 9th Floor
Daily Accomplishment
Toolbox
Final Inspection
 Tower 4, Zone 4, 9th Floor
Friday May 17, 2019 12 Hrs.
 Podium, Zone 19
Concrete Pouring
Daily Accomplishment
Toolbox
Site Visit
 Tower 4, 11th Floor
Saturday May 18, 2019  Podium, Zone 19 12 Hrs.
Paper Works
 Inspection and Work Request (IWR)
Daily Accomplishment

TOTAL NUMBER OF HOURS: 58 HOURS


CERTIFIED BY:

ENGR. CIRILO R. BELAMIDE


PROJECT SUPERINTENDENT
UNIVERSITY OF THE EAST – MANILA
2219 Recto Ave, Sampaloc, Manila, 1008 Metro Manila
BS Civil Engineering On-the-Job Training
ON-THE-JOB TRAINING / PRACTICUM WEEKLY REPORT

Name of Student Trainee: JOSHUA U. TESORO Student Number: 20150114742


Name of Company: VISION PROPERTIES DEVELOPMENT

DAILY WORK ACTIVIES (WEEK4)


No. Of
Day Date Daily Accomplishment working
Hours

Monday May 20, 2019 General Assembly (OJT)

Final Inspection
 Tower 4, Zone 1, 12th Floor
 Tower 4, Zone 2, 10th Floor
Tuesday May 21, 2019 Site Visit 10 Hrs.
 Tower 3 (Architectural)
 Tower 4, Zone 1 and 2
Paper Works
 Inspection and Work Request (IWR)
Site Visit
 Tower 3 (Architectural)
 Tower 4, Zone3 and 4
Wednesday May 22, 2019 Paper Works 10 Hrs.
 Inspection and Work Request (IWR)
Meeting with Project Engineers, Project Architects
and Project Manager
Site Visit
 Tower 4, Zone 3, 10th Floor
Thursday May 23, 2019 Paper Works 10 Hrs.
 Inspection and Work Request (IWR)
Daily Accomplishment
Site Visit
 Tower 4, Zone 3 (Concrete Pouring)
Paper Works
Friday May 24, 2019 10 Hrs.
 Inspection and Work Request (IWR)
Daily Accomplishment
AutoCAD (Formworks)

Site Visit
Saturday May 25, 2019  Tower 4 and Tower 3 10 Hrs.
Daily Accomplishment

TOTAL NUMBER OF HOURS: 50 HOURS


CERTIFIED BY:

ENGR. CIRILO R. BELAMIDE


PROJECT SUPERINTENDENT