3300005682
SECTION G
CDU-2 & HCU-1 Shell PFI Projects work at MRPL as per tender
Price Bid Format (Schedule of Rates)
To be Quoted in EPS only
A. SCHEDULE OF RATES (SOR) for Civil & Structural works pertaining to SHELL PFI jobs at CDU-II & HCU-I units at
MRPL Plant
Providing and laying at all heights and depths Non shrink flow
cementicious grout it shall be 25mm thick with minimum
compressive strength of 30N/mm2 at 7 days and 40 N/mm2 at
14 C110 28days as per manufacturers recommendations, in all anchor cu.m 2.2
bolt sleeve/pockets under all column baseplates , below static
equipment and skids, under shoe plates etc. 25mm TK for
structural bases & 40mm TK for equipment bases
- Foundation coating 0
Providing and applying two coat of coal tar epoxy paint to ye all
below concrete surfaces in contact with soil of approved make
and shade including staging, scaffolding etc. complete as per
manufacturers specification, the painting material shall conform
the following specifications:
19 E100 volume solids-65% sq.m. 932.8
Catalyzed epoxy content 15%+/-1%
Coal tar content 40%+/-2%
Pigment content 22%+/-1%
DFT per coat 100microns
- Structural steel
Steel painting
Surface preparation:
· Hand tool cleaning to SSC SP 02
Painting
· Primer,p2, one coat of epoxy mastic ,100 microns DFT
· Intermediate, p3, one coat of epoxy high build,
polymidecured, mastic ,100 microns DFT
21 L030 sq.m. 4022.7
· Finish, p5 one coat of acrylic polymurethene aliphatic
isocyanate cured,40 microns DFT
Shall be as per painting sec 00 ES 100 005
Note:
1. Quoted rates shall be inclusive of all supplies, Labour, materials, required PPE’S for the deployed personnel, consumables,
overheads and all other costs, charges, expenses including all applicable taxes/ duties, excluding GST.
2. GST shall be extra at actuals to MRPL A/c.
3. Quantities shown in SOR are indicative only. No minimum Quantity/Value is guaranteed. However Payment shall be released
based on the actual Quantity executed by the contractor.
4. Rates shall be firm and fixed till execution of the contract.
5. MRPL may call for detailed breakup of the quotes, if required later.
6. All expenditure related to the scope of work to be included in the quote.
7. Bidder shall quote the Service Tariff Code (STC) for each of the items.
8. Un-priced ‘Priced bid format’ copy indicating quoted items shall be submitted along with Technical bid.
h) Hydrotesting, Draining, Flushing, Drying, cleaning by compressed air , Card Board Blasting, as
applicable, reinstallation of control valves, safety valves, final box up of the piping system &
making the system ready for pre commissioning.
k) Preparation of final marked up drawings (As Built Drawings).
5.1 Carbon Steel Piping, Thickness <= 10 mm
(i) 1/2" Pipe Meter 7
(ii) 3/4" Pipe Meter 43
(iii) 1" Pipe Meter 24
(iv) 11/2" Pipe Meter 45
(v) 2" Pipe Meter 68
(vi) 3" Pipe Meter 166
(vii) 4" Pipe Meter 7
(viii) 6" Pipe Meter 9
(x) 8" Pipe Meter 96
6 Aboveground GI Piping
Laying of galvanised pipes confirming to IS 1239 & fittings confirming to IS 1239 (Galavnised) including supply of
Teflon tapes, White lead etc. cutting the pipes to required length, making threads, as speefied / Instructed by
Engineer-in-Charge. Installation of all in line fittings/ flanges/spray nozzles/ rupture disc etc as applicable, draining
& flushing and drying by air, including hook up of new lines with existing lines, modifications/ rerouting of existing
lines if required etc. complete as per Drawings, specifications and instructions of Engineer-in-Charge and other
related scope.
Rates to include the followings
a) All required consumables and labour, etc.
b) All work as specified in this document and relevant piping specifications as applicable.
c) Work at all elevations including scaffolding, as required
d) Dismantling of Special Material & instruments before hydrotest & reinstallment of the same
e) Preparation of temporary arrangements/connections required for water flushing.
f) Preparation of final marked up drawings (As Built Drawings).
(i) 1/2" Pipe(Heavy Schedule) Meter 7
(ii) 3/4" Pipe (Heavy Schedule) Meter 13
(iii) 1" Pipe (Heavy Schedule) Meter 102
(iv) 1-1/2" Pipe (Heavy Schedule) Meter 7
(v) 2" Pipe (Heavy Schedule) Meter 149
7 Steam Tracing
Collection and transportation of all materials from OWNER's storage point to work site, cutting, bevelling, grinding,
fabrication, erection of steam tracers, cold bending, providing expansion loops at pipe fittings/valves/change in
directions/flanges (CONTRACTOR to ensure that the loops/bends are not flattened). Supplying, providing,
fastening of SS 304 wire of 18 SWG, fastening of tracers at every 1 mtr. interval including providing and
application of heat resistence cement, Supporting of all tracers (supply and return), etc., Pressure testing of steam
tracers, Insertion of Gaskets, Connecting the tracer systems with Manifold lines, equipment's and instruments etc.
as specified in technical specifications and drawings included in the bidding document and as per instruction's of
Engineer-in-Charge.
11.3 Pad supports for uninsulated pipes fabricated using pipes (Free issue materials). Quoted rates to include
collection of material from OWNER's storage point. MT 1
12.2 Erection of fabricated pipe supports (made using pipes) for trunion supports. MT 1
12.3 Erection and welding of Pad supports (fabricated using pipes) for uninsulated pipes . MT 1
13 Erection of Spring Supports
Installation of Spring Supports/ Hanger Assembley by bolting & fixing/welding, including erection at all elevations,
locking/isolation of all the springs before hydrotesting, unlocking of spring supports during commissioning and
completion the works as per drawings, specifications and instructions of Engineer-in-Charge. MT
1
Rates to include the followings
a) All required consumables and labour, etc.
b) Work at all elevations with scaffolding as required.
14 Surface Preparation & Primer
Surface Preparation of fabricated pipe supports and spring supports by Blast Cleaning (grit/ shot blasting) to
SSPC-SP-6 as per MRPL painting spercification (00-ES-100-005, Rev 7, 12 sheets) & applying Primer, P-2, One
coat of epoxy mastic, 100 microns dft of approved make as per specifications & as directed by the Engineer-in-
Charge.
14.1 Pipe Supports - Rolled Section of Carbon Steel (IS: 2062) Sq.m 300
14.2 Trunion Supports. Sq.m 200
15 Intermediate Coat
Intermediate, P-3, One coat of epoxy high build, polyamide cured, 100 microns dft
15.1 Pipe Supports - Rolled Section of Carbon Steel (IS: 2062) Sq.m 300
15.2 Trunion Supports. Sq.m 200
16 Finish Paint
Finish, P-5, One coat of acrylic polyurethene aliphatic isocyanate cured, 40 microns dft
16.1 Pipe Supports - Rolled Section of Carbon Steel (IS: 2062) Sq.m 300
16.2 Trunion Supports. Sq.m 200
17 Liquid Penetrant Inspection/Dye Penetrant Inspection
Conducting liquid penetrant test of piping weld joints over and above the 10% LPT of total welding joints by each
welder included in the scope of works for Piping, including supply of consumables, labour and supervision as per
specification and direction of Engineer-in-Charge.
Rates to include the followings
a) All required consumables and labour, etc.
b) Work at all elevations.
c) Repeat inspection test due to Contractor’s fault such as weld joints requiring repair etc.
(i) Per inch dia per pass of weld Inch
Dia 396
Inch
(i) Radiography of weld joints in pipes of various sizes 2750
Dia
19 Stress Relieving
Carrying out stress relieving of weld joints on all type of pipings as called for on shop / site fabricated system
including supply of all material, consumables, recording devices, insulating materials etc. proving all normal and
special equipments and gadgets, skilled and unskilled labours, specialists, supervisory staff and completing the
work in all respect as per instructions of Engineer-in-Charge. Repet performance due to defective stress reliving or
any other account shall be on CONTRACTOR's cost (Payment shall be done only after submission and approval
of Chart)
Inch
(i) Stress Relieving of weld joints in pipes of various sizes Dia 440
20 Modification Works
Cutting, bevelling, fitup, welding of different sizes of CS(IBR/NON IBR)/AS /SS piping of all types and thicknessess
in shop, in position, on ground/overhead on rack and at all elevations; transportation of pipes, fittings, flanges etc
from owner's storage point to work site/ work shop,
making necessary scaffoldings, consumables, machinery, tools, tackles, labour and supervision including
attending repairs for completing the work as per the instruction of Engineer-in-charge.
Inch
20.1 Flame Cutting CS Piping IBR/Non IBR 550
Dia
Inch
20.2 Bevelling CS Piping IBR/Non IBR 550
Dia
Inch
20.3 Fitup and Welding CS Piping IBR/Non IBR 550
Dia
Inch
20.4 Cutting Alloy steel P9 Piping 110
Dia
Inch
20.5 Bevelling Alloy steel P9 Piping 110
Dia
Inch
20.6 Fitup and Welding Alloy steel P9 Piping 110
Dia
Inch
20.7 Cutting SS304 Piping 110
Dia
Inch
20.8 Bevelling SS304 Piping 110
Dia
Inch
20.9 Fitup and Welding SS304 Piping 110
Dia
21 Erection of Static Equipment
Transportation of Static Equipments (columns, vessels, tanks, filters, drums, etc.) from OWNER's storage point to
work site, unloading of equipments from trailers, as applicable, necessary alignment in ground as required for
erection of the equipment, assembly of parts, subassemblies, erection at all elevations, aligning, verticality
checking, grouting, tightening of foundation bolts, welding of washer on anchor chairs,erection of wooden pillow for
cold vessels, installation of mixer/agitator, internal cleaning and flushing by water, draining, drying by compressed
air, inertising the equipment with related piping including preparation for startup, providing all tools, tackles,
machinery, consumables, transportation equipment, erection equipment, instruments, labour, ancilliary, etc. to
complete the work in all respects as per drawings, equipment detail, specifications and instructions of the
Engineer-in-Charge.
24.1
Insulation
Insulation Type Pipe Size (In Inches)
thickness (In MM)
25 HOT INSULATION (IH) 0.5 RMT 7
25 HOT INSULATION (IH) 0.75 RMT 23
25 HOT INSULATION (IH) 1 RMT 7
25 HOT INSULATION (IH) 1.5 RMT 7
25 HOT INSULATION (IH) 2 RMT 14
25 HOT INSULATION (IH) 3 RMT 394
25 HOT INSULATION (IH) 4 RMT 1463
25 HOT INSULATION (IH) 6 RMT 30
25 HOT INSULATION (IH) 10 RMT 7
30 HOT INSULATION (IH) 0.5 RMT 7
30 HOT INSULATION (IH) 0.75 RMT 7
30 HOT INSULATION (IH) 1.5 RMT 7
30 HOT INSULATION (IH) 2 RMT 28
30 HOT INSULATION (IH) 3 RMT 7
30 HOT INSULATION (IH) 6 RMT 168
30 HOT INSULATION (IH) 10 RMT 7
30 HOT INSULATION (IH) 12 RMT 11
30 HOT INSULATION (IH) 14 RMT 67
35 HOT INSULATION (IH) 2 RMT 7
40 HOT INSULATION (IH) 0.75 RMT 14
40 HOT INSULATION (IH) 1 RMT 13
40 HOT INSULATION (IH) 1.5 RMT 56
40 HOT INSULATION (IH) 2 RMT 37
40 HOT INSULATION (IH) 3 RMT 7
40 HOT INSULATION (IH) 4 RMT 7
40 HOT INSULATION (IH) 6 RMT 52
40 HOT INSULATION (IH) 8 RMT 7
40 HOT INSULATION (IH) 14 RMT 7
45 HOT INSULATION (IH) 0.5 RMT 7
45 HOT INSULATION (IH) 0.75 RMT 28
45 HOT INSULATION (IH) 1 RMT 37
45 HOT INSULATION (IH) 1.5 RMT 7
45 HOT INSULATION (IH) 2 RMT 17
45 HOT INSULATION (IH) 6 RMT 7
45 HOT INSULATION (IH) 8 RMT 59
50 HOT INSULATION (IH) 0.5 RMT 13
50 HOT INSULATION (IH) 0.75 RMT 24
50 HOT INSULATION (IH) 1 RMT 18
50 HOT INSULATION (IH) 1.5 RMT 7
50 HOT INSULATION (IH) 3 RMT 165
50 HOT INSULATION (IH) 4 RMT 7
55 HOT INSULATION (IH) 0.75 RMT 7
55 HOT INSULATION (IH) 2 RMT 18
60 HOT INSULATION (IH) 0.75 RMT 7
60 HOT INSULATION (IH) 10 RMT 19
60 HOT INSULATION (IH) 26 RMT 7
65 HOT INSULATION (IH) 0.75 RMT 39
65 HOT INSULATION (IH) 1 RMT 15
65 HOT INSULATION (IH) 1.5 RMT 51
65 HOT INSULATION (IH) 2 RMT 31
65 HOT INSULATION (IH) 3 RMT 7
65 HOT INSULATION (IH) 4 RMT 7
65 HOT INSULATION (IH) 6 RMT 7
65 HOT INSULATION (IH) 8 RMT 55
70 HOT INSULATION (IH) 2 RMT 7
70 HOT INSULATION (IH) 3 RMT 7
70 HOT INSULATION (IH) 4 RMT 7
70 HOT INSULATION (IH) 8 RMT 7
70 HOT INSULATION (IH) 10 RMT 11
70 HOT INSULATION (IH) 12 RMT 66
75 HOT INSULATION (IH) 2 RMT 11
75 HOT INSULATION (IH) 3 RMT 13
75 HOT INSULATION (IH) 4 RMT 7
75 HOT INSULATION (IH) 18 RMT 10
80 HOT INSULATION (IH) 18 RMT 11
80 HOT INSULATION (IH) 26 RMT 7
80 HOT INSULATION (IH) 30 RMT 41
90 HOT INSULATION (IH) 3 RMT 7
90 HOT INSULATION (IH) 6 RMT 11
90 HOT INSULATION (IH) 8 RMT 44
90 HOT INSULATION (IH) 10 RMT 7
100 HOT INSULATION (IH) 6 RMT 7
115 HOT INSULATION (IH) 8 RMT 121
125 HOT INSULATION (IH) 12 RMT 35
24.2
Insulation
Insulation Type Pipe Size (In Inches)
thickness (In MM)
25 PERSONAL PROTECTION (IS) 0.75 RMT 94
25 PERSONAL PROTECTION (IS) 1 RMT 14
25 PERSONAL PROTECTION (IS) 1.5 RMT 13
25 PERSONAL PROTECTION (IS) 2 RMT 65
25 PERSONAL PROTECTION (IS) 3 RMT 20
25 PERSONAL PROTECTION (IS) 4 RMT 25
25 PERSONAL PROTECTION (IS) 6 RMT 22
25 PERSONAL PROTECTION (IS) 8 RMT 15
25 PERSONAL PROTECTION (IS) 12 RMT 35
30 PERSONAL PROTECTION (IS) 2 RMT 44
45 PERSONAL PROTECTION (IS) 2 RMT 7
45 PERSONAL PROTECTION (IS) 3 RMT 7
45 PERSONAL PROTECTION (IS) 6 RMT 7
24.3
Insulation
Insulation Type Pipe Size (In Inches)
thickness (In MM)
30 TRACED HOT INSULATION (IT) 1 RMT 7
45 TRACED HOT INSULATION (IT) 0.75 RMT 7
50 TRACED HOT INSULATION (IT) 0.75 RMT 7
50 TRACED HOT INSULATION (IT) 1 RMT 7
65 TRACED HOT INSULATION (IT) 1 RMT 7
65 TRACED HOT INSULATION (IT) 1.5 RMT 7
65 TRACED HOT INSULATION (IT) 4 RMT 7
65 TRACED HOT INSULATION (IT) 6 RMT 106
75 TRACED HOT INSULATION (IT) 4 RMT 7
90 TRACED HOT INSULATION (IT) 8 RMT 10
90 TRACED HOT INSULATION (IT) 10 RMT 7
100 TRACED HOT INSULATION (IT) 6 RMT 124
115 TRACED HOT INSULATION (IT) 8 RMT 19
115 TRACED HOT INSULATION (IT) 10 RMT 7
125 TRACED HOT INSULATION (IT) 10 RMT 7
125 TRACED HOT INSULATION (IT) 12 RMT 7
24.4 Aluminium Foil:
Supply and instalation of aluminium foil of 0.1 mm (42 SWG) thick as per ASTM B 209 alloy 3003 H16 or IS 737
Sq M 165
deignation 31000 condition H3 for flat sheets, as specified in specification ((EIL specification no 6-44-0002 Rev 2,
53 pages) for insulation of SS surfaces and as per instructions from Engineer-In-Charge
25 Painting of Piping
Providing and supplying all required materials supported with necessary test certificates, carrying out grit/ shot
blasting to SSPC-SP-6 & painting of piping systems as per MRPL Painting specification (00-ES-100-005, Rev 7,
12 sheets) including supply of all consumables, tools, tackles, & providing covered shed etc. Completing the work
in all respect as per specifications, drawings & instructions of Engineer-in-Charge.
25.2 Primer
(i) Primer, P-2, One coat of epoxy mastic, 100 microns dft Sq.m 231
25.3 Intermediate Coat
(i) Intermediate, P-3, One coat of epoxy high build, polyamide cured, 100 microns dft Sq.m 231
25.4 Finish Paint / Coat
(i) Finish, P-5, One coat of acrylic polyurethene aliphatic isocyanate cured, 40 microns dft Sq.m 231
25.5 Finish Paint / Coat
(i) 3 coats of Epoxy Phenolic coating (P-12 @ 80 microns dft/coat Sq.m 1242
(ii) 3 coats of heat resistant Silicone Aluminium paint suitable upto 500 deg C, P-8, 20 microns dft per coat Sq.m 481
26 Painting of Equipments
Providing and supplying all required materials supported with necessary test certificates, carrying out hand tool
cleaning to SSPC-SP-2 and painting of equipments as per MRPL Painting specification (00-ES-100-005, Rev 7, 12
sheets) including supply of all consumables, tools, tackles, and providing covered shed etc. Completing the work
in all respect as per specifications, drawings and instructions of Engineer-in-Charge.
of testing as specified, draining, drying by compressed air, performing Positive Material Identification(PMI) using
alloy analysers, stacking of servicable/unservicable materials and disposal of the unservicable material including
return of all unused / scarp pipes to OWNER's storage point, completing all such works in all respects as per the
specifications, drawings and instructions of Engineer-in-Charge.
Rates to include the followings:
a) All required consumables and labour, etc.
b) All work as specified in this document and relevant piping specifications as applicable.
c) Work at all elevations including scaffolding, as required
d) Dismantling of Special Material & instruments before hydrotest & reinstallment of the same
after hydrotest
e) Fabrication & installation of Reinforcement pads as per branch table included in enquiry.
f) Preparation of temporary arrangements/connections required for water flushing.
g) Hydrotesting, Draining, Flushing, Drying, cleaning by compressed air , Card Board Blasting, as
applicable, reinstallation of control valves, safety valves, final box up of the piping system,
preparation of flange history sheet, depressurising the system, inertising the system by inert
gas if required & making the system ready for pre commissioning.
h) Positive Material Identification (PMI) of all pieces of pipes, all weld joints and all the fittings with
recorder.
j) Preparation of final marked up drawings (As Built Drawings).
27.1 Alloy Steel Piping, Thickness <= 10 mm, Material: ASTM A 335, GR. P9 B36.10 Seamless
(i) 3/4" Pipe Meter 7
(ii) 1-1/2" Pipe Meter 7
(iii) 8" Pipe Meter 14
(iv) 10" Pipe Meter 7
Note:
1. Quoted rates shall be inclusive of all supplies, Labour, materials, required PPE ’S for the deployed personnel, consumables, overheads and all other costs,
charges, expenses including all applicable taxes/ duties, excluding GST.
2. GST shall be extra at actuals to MRPL A/c.
3. Quantities shown in SOR are indicative only. No minimum Quantity/Value is guaranteed. However Payment shall be released based on the actual Quantity
executed by the contractor.
4. Rates shall be firm and fixed till execution of the contract.
5. MRPL may call for detailed breakup of the quotes, if required later.
6. All expenditure related to the scope of work to be included in the quote.
7. Bidder shall quote the Service Tariff Code (STC) for each of the items.
8. Un-priced ‘Priced bid format’ copy indicating quoted items shall be submitted along with Technical bid.