Beruflich Dokumente
Kultur Dokumente
DH3E-L-A3-
C 05-Aug-16 A. Benoni S. Suresh R. Prakash R. Subramaniam SC-E-160802-
0324
Revised as
DH3E-L-A3-
B 20-Jun-16 A. Benoni S. Suresh R. Prakash R. Subramaniam
SC-E-160609-
0174
OWNER:
POWER GENERATION CORPORATION 1
THERMAL POWER PROJECT MANAGEMENT BOARD 3
CONSULTANT:
POWER ENGINEERING CONSULTING JOINT STOCK
COMPANY 2
CONTRACTOR:
SUMITOMO CORPORATION
SUB-CONTRACTOR:
JURONG ENGINEERING LIMITTED (JEL)
Ref.:
CONTRACT
DUYEN HAI 3 EXTENTION THERMAL POWER No.:
PROJECT:
PLANT PROJECT DH3EXT-
25112014
Document Title:
Table of contents:
NO. DESCRIPTIONS PAGE
COVER PAGE
TABLE OF CONTENT 1
1 GENERAL 2
1.1. PURPOSE 3
1.2. SCOPE OF WORK 3
1.3. MAN POWER LIST 3
1.4. SITE ORGANIZATION CHART 4
1.3. REFERENCE DOCUMENTS 5
2 INSTALLATION SEQUENCE – FLOW CHART 6
3 INSTALLATION PROCEDURE 8
3.1. PREPARATION 9
3.2. TOOLS AND EQUIPMENT 9
3.3. TRANSPORTATION, LOADING/UNLOADING, PRESERVATION 10
3.4. INSTALLATION DETAIL 11
4 QUALITY INSPECTION 19
5 SAFETY PLAN 21
5.1. PLAN TOOLS AND EQUIPMENT SAFETY 22
5.2. STORAGE SAFETY 22
5.3. CRANE AND RIGGING 23
5.4. PERSONAL SAFETY 25
5.5. HOUSE KEEPING 26
5.6. WASTE INDUSTRIAL MATERIAL 27
5.7. GENERAL HOUSE KEEPING 27
5.8. CONFINED SPACE WORK 27
5.9. EMERGENCY PROCEDURE AND EMERGENCY FLOW CHART 28
5.10. TEMPLETE PERMIT TO WORK 29
6 JOB SAFETY ANALYSIS AND RISK ASSESSMENT 30-37
1
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
1. INTRODUCTION
1.GENERAL
1.GENERAL.
2
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
1.1 Introduction
This document contains the above mentioned installation works Method of Statement
for the GCB and Generator Accessory at the Duyen Hai 3 Extension Thermal power
plan project, Vietnam.
The purpose of procedure is to describe all the activities to be performed for the GCB
and Generator Accessory installation. The general sequencing of activities are intended
to ensure that all the works are properly planned and executed in accordance with the
contract document. Rev C
1.2. Scope of Work
This procedure covers the general process, methods, equipment, tools materials
preparation for GCB and Generator Accessory installation.
No. of
Man power person
1 Electrical Engineer 1
2 Electrical Supervisor 1
3 Foreman 1
4 Welder 1
5 Electrical Fitter 15
6 Crane operator 1
7 Signal man 1
8 Helper 2
3
1.4. Site Organization Chart
HEAD OFFICE
SITE
Ramanathan Subramanian E
Site Project Manager Ngo van Son L
+84-169-591-9534 Site Secretary
+84-972-540-353
Ramachandran Prakash E
Site Manager
+84-164-862-4839
Sivaprakasam
Bueza Dennis Silvestre Nguyen Thi Oanh L Le Thi Mong Thu L Lucio Medallo Louie Rosales E Benoni B Arricivita E Mangasi Lumbanbatu E Thiru Moorthy E
E Muruganandam E
HSE Manager Admin Co-ordinator Sr.Accountant Material Controller QA/QC Sr. Engineer Mech Chief Engineer Electrical Engineer Project Controller
+84-165-548-7705 +84-904-542-630 +84-943-222-308 +84-1689-087-911 +84-169-585-9626 +84-121-226-2298 +84-163-513-0019 +84-122-694-0344
Peter Tamondong E Tran Thi Huyen Tran L Phan Thị Ngọc Qúi L Chandrakanth Ravuth E Murugesh Rathinam E Sookragsa Eknarin E Tran Minh Loc L P. Ganesh E
Safety Coordinator Admin Asst(HR) Accountant Deputy Material Controller QA/QC Sr. Engineer CW Piping Engineer (MIS) Planning Engineer
+84-120-569-4386 +84-165-274-0848 +84-168-317-1757 +84-1699 609 592 +84-169-585-9626 +84-165-429-2793 +84-163-839-9260 +84-166-667-7535
Le Minh Trung L Ramasamy Sakthivel E Iilayaraja E Document Controler Muniyandi Subbu E Dinesh Babu E
Safety officer Camp Controller Material Asst-1 Mohan Vignesh E Steel Strcutre Engineer Planning Engineer
+84-937-046-349 +84-164-520-6864 +84-1693-713-96 +84-1673-20-448 +84-169-222-3541 +84-165-548-7705
Tran Minh Tien L Nguyen Thi Ngoc Dung L Truong Thi Oanh L Trinh Phuong Dung L
Admin Asst(Safety) Material Clerk +84-976-364-700 +84-1203-576-566
+84-968-063-009 +84-964-009-646
Lifting Supervisor -1
Lifting Supervisor -2
Lifting Supervisor -3
Huynh Ngoc Long To Dac Kien Dang Van Hai Dong Thanh Tinh
HSE Manager Construction Manager QA/QC Manager Construction Manager Nguyễn Văn Quân Nguyen Thi Thu Ngan
01649.770.244 01656.535.253 0963.823.724 0904.406.254 Material & Machinery Accountance Manager
0984 594 325 01655 385 622
Date 06-Apr-16
Page 4
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
Rev C
1.5. Reference Documents
Drawing:
- DH3E-MKA-E-TSB-0001 : Single line of steam turbine generator main circuit
- DH3E-BAC-E-B&V-0006 : Generator Circuit Breaker schematic drawing.
- DH3E-BAC-E-B&V-9001 : Generator Circuit Breaker Outline drawing.
- DH3E-BAA-E-B&V-9001 : IPB General Arrangement – Plan view.
- DH3E-BAA-E-B&V-9002 : IPB General Arrangement – Section view.
- DH3E-BAA-E-B&V-9003 : IPB General Layout.
- Erection Manual of GCB’s Manufacturer, VT cubicle and generator NGR
- Technical Specification of GCB, VT cubicle and generator NGR.
- VT cubicle & generator NGR outline and detail drawing
…
Standards:
- IEEE C37.013 : AC High-Voltage Generator Circuit Breakers
Rated on a Symmetrical Current Basis.
- IEC 60298 Ed. 3.0 A.C. : Metal-enclosed switchgear and control gear for
rated voltages above 1 kV and up to and including 52 kV.
5
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
6
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
Preparation Works
(Include platform / Scaffolding Installation if
necessary)
Centreline/Marking
Lift up and Install NGR Lift up and Install GCB Install VT cubicle, Excitation
XFMR on the right position
Official Inspection
Final Sealing
7
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
3. INSTALLATION PROCEDURE
8
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
3. Installation
3.1. Preparation
Before installing, consult all drawings.
Arrange, analyze drawings and typical documents clearly before the site
execution.
Receiving floor plan drawings for each installation from vendor.
Ensure the affected areas are well coordinated with all other related party.
Install barricade and caution board around working area.
Confirm elevation as per drawing.
Cleaning of installation area and mark adjustment according to layout
drawing.
Ensure tools and equipment are well maintained. Usage of handmade
strictly prohibited.
Installation scaffolding:
- Concentrate scaffold and accessories to site.
- Verify scaffold to ensure nothing damage.
- Ensure wearing full PPE properly and prepare tools be fastened by
lanyards.
- Execute erecting scaffold and tag yellow card during erection.
- Ensure scaffold after erecting steady enough and supply proper
handrails, toe planks.
- Remove obstructions and tag green card prior to use.
- Scaffold can only be verified and certified tagged by a suitably qualified
scaffolds inspector
3.2. Tools and equipment (with illustration)
1. Portable hand tools for the work ( Angle grinder, hacksaw, hammer)
9
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
10
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
11
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
Civil hand over report with full signature to be taken over prior start work.
Make the basic centerline marking according to the foundation drawing.
The position of supporting steel structure shall be longitudinally located
according to the allowable tolerance.
Install each supporting structure, following the type of support given at the
drawing.
Check alignment and level of each element.
Fixing bolt of supporting structures.
12
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
13
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
14
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
Connect to GCB:
15
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
For illustration
3.4.2 NGR installation to the supporting structures.
16
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
17
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
18
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
4. QUALITY INSPECTION
19
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
4. QUALITY INSPECTION
Upon approval of Inspection Test Plan and Inspection forms, these documents
will be included later:
Title: “Site Inspection and Test of GCB and Generator Accessory System
ITP ref No: “DH3E-BAA-E-JEL-0125”
Those applicable test plan & forms will be implemented during inspection and
erection, and keep records for final documentation in which to be submitted later to
TPMB3/PECC2. SC/JEL will do internal check before submit request for official
inspection.
20
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
21
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
All gas and oxygen regulators shall be fitted whit flashback arrestors, being
flashback arrestors valves designed to prevent an explosive mix developing in
either cylinder such that explosive mixes can occur due to loose connections,
leaking hoses, etc.
Prior to use, all equipment shall be thoroughly checked to ensure:
a) All connection is tight
b) All fitting such as gauges, flashback arrestors, etc., are functioning
correctly
c) Hoses are in good condition and free from sign of cracking or perish in
d) Checking for leaks shall be by means of soapy liquid to each joint.
UNDER NO CIRCUMSTANCE SHALL A NAKED FLAME BE APPLIED TO
ANY PART OF THE CYLINDER OR HOSE ARRANGEMENT TO DETECT
LEAKS
The cutting and welding of certain metals or metal coatings such as zinc
galvanized surfaces give off harmful fumes, and such works must, where possible
be carried out in a well-ventilated area. When working at height, do not place
cylinders directly beneath the work area, as molten metal may fall onto hoses,
causing leaks, and possibly igniting the gases.
and responsibilities will include the preparation of rigger training course and
safe rigging and lifting of the load at the location.
Crane and lifting equipment must be inspected and carry a valid test certificate
issued by as accredited testing agency, designated by the government of the
country, monthly color coding and inspection (by DH3E Project HSE).
Crane hooks are to be fitted with properly functioning safety clips to prevent
the displacement of the sling from the hooks during the lifting.
Loads must always be slung with the center of gravity directly beneath the
crane hooks, to prevent uneven tensions being applied to the sling legs.
The angle between sling legs shall not, under any circumstances exceed 120
degree, as this doubles the tension on each leg, thereby reducing the lifting
capacity of the sling 50%.
For wheeled cranes, outriggers shall be used for each lift, regardless of the size,
and shall always be fully extended. One person only, shall give instruction to the
crane operator (signalman).
A’ trial’ lift shall be carried out, raising the load a short distance above its pick-
up points, to check the stability of the crane, and efficiency of the brakes.
The loads shall, at all times be kept as close to the ground as possible.
Whenever possible, and after lifting the load from its pick-up point, the radius
of the lift should be shortened to increase the crane’s lifting capacity and stability.
Wire sling and the chains under direct tension during the lift shall not be
extended artificially, nor be knotted.
Wire sling which show signs of excessive wear, kinking, or broken wires shall
be discarded and not used further.
At no time while the load is suspended shall personnel perform any works
directly beneath.
Particular consideration to the presence of low-level structures such as pipe
bridges shall be given, where crane is to move about the site.
Consideration shall be given to prevailing weather conditions, and where a
greater than normal risk exists, the lift shall be postponed until more favorable
conditions developed.
Retain a fire extinguisher at the location of fabrication or welding works at all
time. All the works carrying out at a height greater than 2 meters above the
24
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
- Hand Protection
Gloves shall be used by personnel involved in works for possibility of the
following hazards:
+ Risk of abrasion
+ Risk of cutting
+ Risk of tearing
+ Risk of chemical, or other, burn
+ Risk of infection
The wearing of gloves should be avoided if possible, when works are being
carried out on, immediately next to rotating or moving equipment.
- Foot Protection
Suitable safety footwear shall be worn by personnel, considering the nature of
works and such hazards as:
+ Risk of crushing by heavy objects.
+ Penetration by sharp objects
+ Penetration by chemical or harmful liquids.
+ Weld spatter
- Hearing Protection:
Hearing protection shall be worn by personnel involved in works in areas of
high noise levels (>100dBA), or when working with equipment that generate high
noise levels.
Hearing protection is available in 2 basic types, being an external Cup type
defender which fits over the outside of the ear, and an internal plug-type, usually
made of compressible foam, which fits inside the ear.
Selection of the correct type shall depend upon:
+ The nature and source of the noise
+ The assumed, or known, level of the noise
25
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
28
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
29
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessory
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
30
JURONG ENGINEERING LTD.
Work Plan Procedure for GCB and Generator Accessories Installation
REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
ASPECT
IMPACT
ENVIRONMENT
Prob x Cons = RR
Prob x Cons = RR
CODE
CODE
JOB STEPS /
RERSONNEL
REPUTATION
RISK AS
ASSET
cause effect
31
JURONG ENGINEERING LTD.
Work Plan Procedure for GCB and Generator Accessories Installation
REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
32
JURONG ENGINEERING LTD.
Work Plan Procedure For Emergency Diesel Generator Installation
REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
33
JURONG ENGINEERING LTD.
Work Plan Procedure for GCB and Generator Accessories Installation
REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
Scor 1 2 3 4 5
e
Probability Most Unlikely Unlikel Likel Most Inevitab
y y Likely le
Consequence First Aid treatment Medical treatment Lost Time Injury Serious Injury / Hospital Fatalit
Treatment y
1–5= 6 – 14 = 15 – 25 –
LOW MEDIUM HIGH
Awareness education is required by Further control measures will be Full mitigation required to
Risk Rating means of required reduce residual risk to
(RR) Prob x TBT Impacts on: Localized low.
Cons = RR . Country Impacts on:
Impacts on: International
Worksite
Aspect Code: Impact Codes:
1. Waste Generation A. Impacts on flora
2. Waste water Discharge B. Impacts on fauna
3. Storm water Discharge C. Impacts on biological
diversity
4. Point Source Air Emission D. Impacts on habitat
5. Fugitive Air Emission E. Impacts on landscape and
natural beauty
6. Automobile Exhaust Emission F. Impacts on agricultural lands
7. Chemical Use Operations G. Impacts on water supplies
8. Water Use Operations H. Impacts on minerals
9. Energy Use Operations I. Impacts on marine resources
10. Use of Natural Resources J. Impacts on Air
11. Product disposal K. Impacts on water
33
JURONG ENGINEERING LTD.
Work Plan Procedure for GCB and Generator Accessories Installation
REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
34
JURONG ENGINEERING LTD.
Work Plan Procedure for GCB and Generator Accessories Installation
REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
This JSA / RA (Job Safety Analysis / Risk Assessment) is a formal written safety assessment for every job method statement or worki ng plan.
It contains the Job Steps, Hazards and Risk Assessed, identifies impact to Personnel, Asset, Environment and Reputation, t he Initial Risk, the
Mitigating controls with assessment of Residual controls, and Impact assessment to Environment. Training will be introduced t o all personnel
managing this safety document.
NOTE 2:
Explanation of low risk, medium risk, and high risk.
1-5 LOW RISK Acceptable. Job may proceed assuming that competent personnel are performing it.
However, review to see if the risk can be reduced further.
6 - 14 MEDIUM RISK Job should only proceed with appropriate supervisory authorization. Check to see if the job
could be modified or if more controls can be added to reduce the risk.
15 - 25 HIGH RISK Job must not proceed. It should be redefined or further control measures put in place to reduce
risk. The controls should be re-assessed for adequacy prior to restarting the job. The job may
not proceed until proper managerial approval is given.
NOTE 3:
Explanation of investigation and reporting level:
1-5 INVESTIGATE INCIDENT at the site manager level, incident notification report
15 - 25 SMC/EVN Representative
INVESTIGATE INCIDENT with local authorities, TPMB3 Representatives and SMC Management.
Risk – The probability for a hazard to cause an accident and has a measure of the potential severity. Severity x Probability = Risk
Risk Assessment – is a careful examination of what, in your work, could cause harm to people, property or th e environment.
It allows appropriate measures to be developed.
35
JURONG ENGINEERING LIMITTED.
Work Plan Procedure for GCB and Generator Accessories
Installation REV : C
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
NOTE 4:
Table 1 – Definitions of Likelihood (for environmental)
Major & Difficult to Rectify Environmental Damage, effect lasting for many years –
5 Certain & Substantial Criminal & Civil penalties.
36