Sie sind auf Seite 1von 7

Construction of Slabs on Ground -Design

Considerations Based on ACI and ASTM


Home/ Structural Engineering / Slab Design / Construction of Slabs on Ground -Design Considerations Based on
ACI and ASTM

Construction of Slab on Ground- Design


Elements
The construction of slab on ground requires certain basic design elements. These design
elements must be enlisted and added in the contract documents by the designer in charge
before asking for a bidding.

The design elements required for slabs on ground are:


1. The Materials required for base and the sub – base preparation. The vapor retarder can be provided
if necessary.

2. The thickness of the concrete slab intended to construct

3. The Strength values of concrete – Both compressive and flexural strength

4. The Concrete Mix proportions for the desired concrete slab

5. The details of joints and their locations.

6. The type of reinforcement if necessary. The type, size, detailing and locations have to be specified.

7. The surface treatment and surface finish requirements

8. The extent of tolerances for the base, sub-base, the slab thickness and the surface

9. The curing of the concrete

10. The Filling material used to fill the joint and their installation details

11. The details of special embedment

12. The details of pre – construction meetings, the details of overall quality assurance and quality
control.
Soil – Support System for Slab on Ground
The construction of a concrete slab on the soil demands the soil to behave like a standard
supporting system. Hence the performance of a slab that is constructed on the ground is
dependent on the integrity of the slab and the soil – support system. This requires high
preparation of the site as per the desired requirement of loads.

Fig.1: A Concrete Slab Supported over the Soil Bed


Mostly the soils undergo proof rolling. The method of proof rolling well help us to know
whether the full layer of soil is able to behave as a supporting system i.e. whether they
are uniformly stable and have adequate bearing capacity so that they perform well after
the whole construction of slab.
It is recommended to have this procedure just after the rough grading and before the
placement of the slab.

To control the thickness of the concrete and to have a reduction in the friction between
the base material and a slab, a thin layer of fine grading material is used. This fine
grading material can be graded, granular and a compatible material. The details of the
materials used is explained in ACI 360R.
Protection of Slab on Ground Against
Moisture Penetration
The slab constructed above the ground is highly subjected to moisture penetration if no
proper treatment is carried out. The moisture protection is provided for the floor over the
slab by means of flooring materials like wood, carpet, linoleum, vinyl, impermeable floor
coatings, adhesives, rubber – backed carpet tile.

These are moisture sensitive flooring materials. This is mainly applied for floors that are
installed in a moisture sensitive environment or refrigerator rooms where it is humidity
controlled.

Fig.2: Use of Vapor Retarders for Slab Construction


To minimize the transmission of moisture content from the below to the floor
surface, vapor retarders can be used. The ASTM E 1745 provides the performance
requirements of a plastic vapor retarder that must be used in practical applications.
Generally, a permeance value that is less than 0.3perms must be gained by the vapor
retarder employed as per ASTM E 96.

The selection of the vapor retarder or the barrier material depends on the:
o The extend of protection requirements

o The moisture related sensitivity of the floor material


The materials used for this protection must comply with the specification given in ASTM
E 1745 and the minimum thickness is 0.25mm. If an increased thickness is provided, the
moisture penetration and hence the durability is increased after the complete installation.

A true vapor retarder is as specified by ASTM E 96 that have a permeance equal to 0.00
perms. Many designers have been employing and referring wrong materials as vapor
retarders. The lap that is employed in the installation of vapor retarders must be 150mm
as per ASTM E 1643.

This can also be based on the measurement recommended by the manufacturer. The
joints and the penetration after the installation must be sealed properly by the sealants, or
by pressure-sensitive tapes or as it is instructed by the manufacturer.

Installation of Vapor Retarders for Moisture


Resistance
The decision on where to place the vapor retarder will vary from site to site. The vapor
retarders can be placed either in contact with the slab or it can be placed in contact with
the granular fill.

In the case of a moisture sensitive environment, the concrete can be placed directly in
contact with the vapor retarder material or the barrier that is used for moisture
penetration. This method will help in the penetration of moisture and water from the
potential sources like rain, curing, cleaning or saw-cutting. The saturated fill, when
placed above the vapor retarder, will consume time for the slab to dry up.

As mentioned in above method, the placing of concrete in direct contact with the vapor
retarder will demand high quality considerations. Only proper installation can help in
avoiding slab related issues during the performance period.

It has been observed that the placement of concrete directly over the vapor retarder when
compared to other slab installation methods are subjected to length change, drying
shrinkage and other related effects from the environment. Settlement is also observed.

The design detailing of the concrete must incorporate these considerations so that the
restraints are reduced. The standards recommend to follow each site to perform this
construction must be separately evaluated for the sensitivity towards moisture of the
floors, the project conditions and the effects due to slab curling, cracking and crusting.

All the benefits and risks that are anticipated must be discussed with the appropriate
parties before the commencing of the construction.
The figure-3 below shows a flow chart that will help in assisting the evaluation and
construction.

Fig.3. A decision flow chart to assist the decision of vapor retarder or the barrier.
From the figure-2, the FIG.2 is employed if the granular material is subjected to future
moisture infiltration. The decision of FIG.2 will ask for a concrete mix design that is of
low shrinkage, reduction for joint spacing and all other properties that would minimize
the curling of the slab.

Causes of Cracks over Reinforcement in


Slabs on ground
Inadequate consolidation of the concrete, use of bars of large diameters, inadequate
concrete cover provided for the reinforcement, higher temperature of the employed
reinforcing bars, higher slump value than desired, inappropriate curing or the
combination of the above-mentioned factors are the main reasons behind the formation of
cracks near to the reinforcement installed in slab constructed on ground.

Crack – Width Control in Slabs on Ground


The use of reinforcement in a non-structural member is performed to control the width of
the cracks that will occur in the concrete slabs. The reinforcement mainly used will be
steel bars deformed, welded wire reinforcing, post tensioning tendons or the steel fibers.
These reinforcements can also be used in combination.

Mainly, the non-structural concrete slab mainly employs a small amount of reinforcement
that they do not have any role in the restraining movement caused from the volume
changes.

The slab on ground that are not reinforced will experience temperature and shrinkage
cracks. These are observed wider at the surface of the concrete slab and will narrow
throughout the depth.

The reinforcing steel or the post-tensioned steel or the deformed steel have to be
supported and tied together while installing in concrete. This is to ensure that their
movement during the concrete placing is avoided.

The required support can be given by pre-cast concrete bars. The precast concrete bar
employed for this purpose must have a thickness of 100mm in minimum value and have a
compressive strength equal to the concrete used in the slab.

When using welded wire reinforcement, it is essential that the contractor provides
sufficient support so that placing of the concrete does not affect the reinforcement
drastically. Proper support at adequate locations must be provided so that pulling out of
the wire reinforcement is avoided during foot traffic.

Steel Fibers in Slabs on Ground


The use of steel fibers won’t bring a reduction in the amount of cracks formed in the
concrete slab constructed in the ground. The steel fibers used near to the contraction
joints helps in the reduction of joint openings. This helps in the reduction of chances of
cracking between the joints. The crack width must remain narrow.

Synthetic Fibers in Slabs on Ground


The concrete slab casting will sometimes welcome plastic shrinkage and their cracks
during the first few hours of curing. This can be reduced to some extend by the use
synthetic fibers of polyethylene, nylon, polypropylene and other types.
These fibers also help in the reduction of segregation of concrete in the plastic state. The
modulus of elasticity will get increase when the concrete gets hardened.

Post- Tensioning Reinforcement for Slabs on


ground
A relatively high compressive stress is induced within the concrete, using high strength
steel tendons. This is used instead of conventional mild steel reinforcement and the steel
fibers.

This post tensioned slab will have compressive stress that can balance all other
undesirable stress caused after the placement of concrete and when the load is applied.
This hence reduces the crack formation on the slabs.

It is recommended that the construction loads on the concrete slab have to be fully
minimized until the slabs are fully stressed. This type of work must be done only by
experienced contractors and engineers.

Read More:

Das könnte Ihnen auch gefallen