Daily Drilling Fluid Report API No: AQBC88RGH0NVFH8G Report No: 025

Date 05-21-2019 11:59:00 PM Well Name ZB-387 Spud Date 04-27-2019


Operator ENI DGS - 002,ZUBAIR Country Iraq Depth (MD / TVD) 3,270.00 / 3,270.00 m
Operator Rep Khuram Khuram,Anil Anil State Al Basrah Rig Name KCADT-601
Contractor KCA DEUTAG DRILLING GMBH County Rig Activity Drilling 8.5" section
Contractor Rep Imad Duraid,Moustafa Ahmed Field or Block Zubair Field Unit System WSE API(Copy)
Bit Information Drill String (in) / (m) in Casing m Pumps 1 2 3
Bit Size 8.500 in OD ID Length T OD Set MD Model BOMCO F1600 BOMCO F1600 BOMCO F1600
Make/Type HYCALOG / DS70F+GDrill Pipe 5.000 4.276 3,010.85 C 24.500 @ 57.00 Bore Strokes in 6.000 12.000 6.000 12.000 6.000 12.000
Jets 6x14 Drill Pipe 5.000 3.000 86.36 C 18.625 @ 704.00 Eff (%) 97 97 97
TFA 0.902 in2 Drill Collar 5.000 3.000 18.65 C 13.375 @ 1,865.00 liter/strk 16.2 16.2 16.2
Jets Velocity 206.2 ft/s Drill Collar 6.250 111.36 C 9.625 @ 2,985.00 SPM 68 68
2.750
Jet Impact Force 698.5 lb C 9.625 @ 2,985.00 L/min | L/min 1,100.23 1,100.23 1,100.23 1,100.23
Other 6.750 5.18
Bit HHSI 2.56 hhp/in2 Drill Collar Circulation/Hydraulics Data
6.250 1.500 26.32
Bit Depth MD 3,270.00 m Motor 6.750 10.97 Surf to Bit Time 12.7 Total L/min 2,200.46 Pressure Drop (psi)
Bit Depth TVD 3,270.00 m BU Time min 35.0 AV, Riser Surface 230
Riser Open Hole Total Circ Time 106.8 AV min DP 90.76 Drill Pipe 2,443
RPM Bit rpm Open Hole 8.500 285.00 Surf to Bit Strk 1,733 AV max DC 130.85 Motor+Other
RPM Surface rpm BU Strokes 4,764 AV max Csg Annulus 351
Torque ft-lbf Total Strokes 14,531 ECD@Shoe 1.42 Bit 427
WOB ton (long) Circ Press psi 2,560 ECD@Bit 1.43 Tot Pres Loss 3,451
Properties 1 2 3 Hyd 4 Targets Program Fluid Treatments
Fluid Set Enhanced LSND K Enhanced LSND K Enhanced LSND K Enhanced LSND K Fluid Type Enhanced LSND KCL / GEM Polymer Mud
Source Flow Line Flow Line Flow Line Flow Line * Water well analysis: Salinity Cl- : 39,000 mg/l
Time 6:00 12:00 19:00 23:59 , Ca++: 600 mg/l, Mg++: 389, Total Hardness:
Depth (MD/TVD) m 3,056.00/3,056. 3,080.00/3,080. 3,194.00/3,194. 3,270.00/3,270. 1180 mg/l.
* Fresh water analysis: Salinity: 300 mg/l --
FL Temp ºC 75 79 81 83
Hardness: 120 mg/l.
Density @ ºC SG 1.30@71 1.32@75 1.35@78 1.35@79 1.25 1.35
FV @ ºC sec/qt 51@71 58@75 60@78 60@79 45 60 * Arrange chemical area.
PV @ ºC cp 16@40 17@40 21@40 21@40 * Treated active mud with sodium bicarbonate
YP lbs/100ft2 18 22 22 22 18 25 while drilling cement.
* Treated active mud with PAC-L and
GELS lbs/100ft2 9/11/15 8/11/15 9/12/16 9/12/15
DEXTRID LTE
600/300 50.0/34.0 56.0/39.0 64.0/43.0 64.0/43.0 * Increased M.wt from 1.3 sg to 1.35 sg by
200/100 28.0/19.0 31.0/23.0 33.0/24.0 33.0/24.0 using CaCO3 f and Salt.
6/3 9.0/8.0 8.0/6.0 9.0/6.0 9.0/8.0 * Changed 1 damaged shale shaker screen
Filtrate (API) mL/30min 3.0 3.0 2.8 2.8 0.0 3.0 with new one.
HTHP @ ºC mL/30min .
Cake (API/HTHP) 32nd in 1/0 1/0 1/0 1/0
Corr Solid % by vol 7.5 8.1 8.6 8.6
NAP / Water % by vol 0.0/86.0 0.0/85.5 0.0/85.0 0.0/85.0
NAP / Water Ratio
Rig Activity
Sand % by vol 0.10 0.10 0.10 0.10
MBT ppb eq. 2.5 2.5 2.5 2.5 2.0 4.0 Washed down from 2915m to 2954m with
1500 lpm. Tagged top of cement at
pH @ ºC 9.2@36 9.2 9.2 9.3
2954m.Confirmed TOC by slacking of 5 tons
ALK Mud (Pm) mL 1.30 1.30 1.30 1.30 twice. Drill out shoe track cement,
ALK Filt (Pf/Mf) mL 0.70/1.10 0.70/1.10 0.70/1.10 0.70/1.10 Plugs, Float Collar, Float Shoe and pocket
Chlorides mg/L 120,000 120,000 120,000 120,000 from 2954 m to 2990 m. Drill out Float Collar
Total Hardness mg/L 540 650 640 540 @ 2959 m, Float Shoe @ 2985 m & rat hole to
2990 m.
LGS / HGS % by vol 3.8/3.8 3.5/4.5 2.7/5.9 2.7/5.9
Two passes to check & clear entire shoe track.
LGS / HGS ppb 34.29/55.64 32.32/66.74 24.65/87.04 24.65/87.04 Pump 5m3 hi vis. Cement hardness:
ASG SG 3.402 3.498 3.698 3.698 moderately hard to hard. Drilled 8 1/2" hole in
Additional Properties Nahr Umr Formation
Mg+2 mg/L 36 36 36 36 in rotary mode from 2990 m to 3036m
Average ROP 9-10 m/hr. No downhole losses.
Ca+2 mg/L 480 480 480 480
Current MW = 1.30 - 1.32 sg. Mark Top of
KCL % % by vol 3.0 3.0 3.0 3.0 Shuaiba at 3036m
Gem-Gp/BXR-L % by vol 1.0 1.0 1.0 1.0 - Pump 5m3 hi vis every connection. Drilled 8
1/2" hole in Shuaiba Formation in rotary mode
from 3036m to 3089m with flow rate: - No
Product Name Units Start Rec Used End Cost Solids Control Equipment Time
BA. BARO-TROL - 25 K 25 KG BAG 52 16 36 Shaker Screens Hrs Drilling 24.0
BA.IRON-THIN - 50 LB 50 LB BAG 10 10 Derrcik 140 140 120 100 24.0 Circulating
BARACARB 1200 25 kg BAG 48 48 Coring
Derrcik 140 120 120 100 24.0
BARACARB 25 1 tonne BAG 4.000 4.000 CutOffDrilling
Derrcik 140 140 120 100 24.0 Dir Work
BARA-DEFOAM W300 180 kg DRUM 3 3
Fishing
BARAZAN D 25 kg BAG 157 3 154
Logging
BARITE 41 - 1.5 TON 1.5 TON BAG 18.000 18.000
N. Up BOP
BAROLIFT 15 lbm BOX 34 1 33 Plug Back
BARO-LUBE GOLD SEAL 55 Gal DRUM 8 8 Reaming
BENTONITE 1 tonne BAG 9.000 9.000 Hydrocyclone Cones Screens Hrs
Repair
BXR L 55 Gal DRUM 14 1 13 Desander 3 - 16 Rig
CALCIUM CARBONATE FINE 1 tonne BAG 28.000 18.000 10.000 DESILTER 12 - 16 Rig Up/Dn
CALCIUM CARBONATE COA 1 tonne BAG 3.000 1.000 2.000 Other
CAUSTIC SODA 25 kg BAG 88 18 70 Centrifuge Speed Feed Rate Hrs Total 24.0
CITRIC ACID 25 kg BAG 40 40 Centrifuga 2800 0.00 Rotating 24.0
200 kg DRUM 3 3 ROP 11.7
CON DET E
Dil Rate
DEXTRID LTE 25 kg BAG 170 30 140
EZ SPOT 195 kg DRUM 8 8 Fluid Volume BreakdownPrimary Active Fluid: Enhanced LSND KCL / GEM Polymer Mud
EZ-MUD 25 kg CAN 15 2 13 Active m3 Additions m3 Losses m3
GEM GP 220 kg DRUM 9 1 8 Annulus 77.09 Base Fluid Dumped
MICROBIOCIDE 20 L PAIL 32 32 Pipe Cap 28.05 Drill Water Transferred
N-SEAL 30 lbm BAG 60 60 Total Hole 105.14 Dewatering SCE -8.00
PAC-L - 25 KG BAG 25 KG Bag 140 30 110 Active Pits 130.00 Sea Water Downhole
POTASSIUM CHLORIDE 1000 kg BAG 3 3 Total Circ 235.14 Whole Mud Misc Other -2.00
SALT 1 tonne BAG 78.000 25.000 53.000
Reserve * 110.02 Barite
SCR ATL MTL TM API 200CR ATL MTL TM API 200 4 4
Prev Vol * 335.29 Chemicals 20.17
SCR ATL-MTL-TM-210 TM API 120 5 1 4
Net Change * 9.87 Other
SCR ATL-MTL-TM-250 TM API 140 10 1 9
SODA ASH 25 kg BAG 80 20 60 Total Vol * 345.16 Total 20.17 Total Losses -10.00
Active Fluid Type Vol m3 Deviation Information
Daily Products Cost $0.00 Total Daily Cost $0.00 Primary Active In Hole Reserve Survey Date
Cumulative Products Cost $0.00 Total Cumulative Cost $0.00 þ Enhanced LSND KCL / GEM Polymer
105.14 Mud
110.02
* Survey MD m
RASHAD MOHAMMAD MOUSA Mostafa EL Khayat ¨ LCM pill # 1 ( 40 ppb) 18.00 Survey TVD m
Baroid Representatives
¨ LCM pill # 3 ( 180 ppb) 18.00 Angle º
Office DIST # 29, WESTERN BURJESIA BASRAH Telephone Direction
Warehouse DIST # 29, WESTERN BURJESIA BASRAH Telephone Horiz Displ. m
This report, the software, any data contained in this report and any interpretations based on this report are offered “as-is” and ”where-is.” There are no representations or warranties, expressed or implied, including implied warranties of merchantability and/or fitness for a particular purpose and or non-infringement. In no event will
Halliburton or its affiliates or suppliers be liable for any damages, whatsoever, including, but not limited to direct, indirect, consequential, incidental, special, punitive or exemplary damages (including, without limitation, loss of data, profits or use of hardware or software). Customer uses at their own risk.
Daily Drilling Fluid Report API No: AQBC88RGH0NVFH8G Report No: 025
Date 05-21-2019 11:59:00 PM Well Name ZB-387 Spud Date 04-27-2019
Operator ENI DGS - 002,ZUBAIR Country Iraq Depth (MD / TVD) 3,270.00 / 3,270.00 m
Operator Rep Khuram Khuram,Anil Anil State Al Basrah Rig Name KCADT-601
Contractor KCA DEUTAG DRILLING GMBH County Rig Activity Drilling 8.5" section
Contractor Rep Imad Duraid,Moustafa Ahmed Field or Block Zubair Field Unit System WSE API(Copy)

Fluid Treatments
* Water well analysis: Salinity Cl- : 39,000 mg/l , Ca++: 600 mg/l, Mg++: 389, Total Hardness: 1180 mg/l.
* Fresh water analysis: Salinity: 300 mg/l -- Hardness: 120 mg/l.

* Arrange chemical area.


* Treated active mud with sodium bicarbonate while drilling cement.
* Treated active mud with PAC-L and DEXTRID LTE
* Increased M.wt from 1.3 sg to 1.35 sg by using CaCO3 f and Salt.
* Changed 1 damaged shale shaker screen with new one.
.

* Formation and Lithology: -

- Top of FM Shuaiba at 3036 m ( Limestone )


- Top of Upper Shale Mbr FM at 3194 m. (Shale black ,gray )

* Daily no of HOC : 2 Total no of HOC :46


*Daily no of JSA : 1 Total no of JSA : 15

.
Rig Activity
Washed down from 2915m to 2954m with 1500 lpm. Tagged top of cement at 2954m.Confirmed TOC by slacking of 5 tons twice. Drill out shoe track cement,
Plugs, Float Collar, Float Shoe and pocket from 2954 m to 2990 m. Drill out Float Collar @ 2959 m, Float Shoe @ 2985 m & rat hole to 2990 m.
Two passes to check & clear entire shoe track. Pump 5m3 hi vis. Cement hardness: moderately hard to hard. Drilled 8 1/2" hole in Nahr Umr Formation
in rotary mode from 2990 m to 3036m Average ROP 9-10 m/hr. No downhole losses. Current MW = 1.30 - 1.32 sg. Mark Top of Shuaiba at 3036m
- Pump 5m3 hi vis every connection. Drilled 8 1/2" hole in Shuaiba Formation in rotary mode from 3036m to 3089m with flow rate: - No downhole losses.
Current MW = 1.32 - 1.35 sg - Mark Top of Upper Shale at 3089m - Pump 5m3 hi vis. Drilled 8 1/2" hole in Upper Shale Formation in rotary mode from 3089m to 3194m
with flow rate: 2100-2200 lpm, SPP: 3100-3150 psi,WOB: 8-14 ton, TQ: 15-19K Ft-lb. RPM = 110 -150. Average ROP 16-17 m/hr. -
No downhole losses. Current MW in/out= 1.35 sg- Mark Top of Upper Sandstone at 3194m . Drilled 8 1/2" hole in Upper Sandstone Formation in rotary mode from 3194m to 3278m -
No downhole losses. Current MW in/out= 1.35 sg - Survey @ 3192.9m Inclination: 2.3 degree Azimuth: 217.36 degree

This report, the software, any data contained in this report and any interpretations based on this report are offered “as-is” and ”where-is.” There are no representations or warranties, expressed or implied, including implied warranties of merchantability and/or fitness for a particular purpose and or non-infringement. In no event will
Halliburton or its affiliates or suppliers be liable for any damages, whatsoever, including, but not limited to direct, indirect, consequential, incidental, special, punitive or exemplary damages (including, without limitation, loss of data, profits or use of hardware or software). Customer uses at their own risk.