Beruflich Dokumente
Kultur Dokumente
Abstract
Side frictions of three groups of drilled piles under different loading methods in Xinwan interchange
of Qianjiang Passageway and Connecting Project were monitored. Group 1 was loaded by static
loading test method. The other two groups were loaded by dead load of superstructures, which were
constructed using segmental hanging basket method and overall support cast-in-place method
respectively. Axial forces and Side friction in all the piles increased gradually during the load-adding
procedure. Group 1 was loaded two months after the finish of pile foundation construction, while
group 3 started bearing the action of superstructure dead load six months after the finish of pile
foundation construction. Piles in Group 1 and Group 3 have different repose time. Side frictions
monitored from piles in Group 3, which have longer repose time, were larger than those in Group 1
under the same load. Side frictions monitored from piles in Group 2, which have longer off-time
between two loading stage, were larger than those in Group 1 under the same load.
1 Introduction
The use of drilled piles in construction engineering has gradually increased since 1980s.
Researches on the long-term bearing characters of piles after piles are founded were carried out by
more and more engineers and technicians. Yang et al. (2013)’s study showed that axial force of pile
were adjusted and enhancing effect of dynamic side friction were obtained in sand soil under
long-term cyclic loading. In different periods of the same pile static load test, Chen (1987) showed that
pile side resistance increased with time, while resistance at pile end has no obvious change. Static load
tests of two drilled piles in soft soil were carried out for 28 days and 1750 days after they were
constructed. In-situ test showed that the ultimate bearing capacity of these two single piles increased
about 30 % (Zheng et al. 2003). Chen (2006) study indicates that the time-effect can affect more than
Corresponding author
Selection and peer-review under responsibility of the Scientific Programme Committee of ICTG 2016 445
c The Authors. Published by Elsevier B.V.
doi:10.1016/j.proeng.2016.06.056
In-Situ Monitoring of Side Friction of Drilled Piles by Different Loading Methods Li-Qing et al.
10 percent of the ultimate bearing capacity of single pile. By a volume of single pile and a volume of 4
piles foundation, tests were carried out under long-term sustained loading individually and by loading
directly, Li (2011) show that under long-term load full consolidation before loading, soil bearing
capacity increase, and the phenomenon of pile groups more obvious than single pile. Through field
monitoring for bearing behavior of drilled pile in the whole bridge construction, side friction increases
gradually in the process of bridge construction (2014). All the researches above indicate that the
bearing capacity of drilled piles changes after the build-up of piles.
At present, a large number of Bridges need to be upgraded in China, and using the existing pile
foundation in bridge upgraded is economic and reasonable. It is required in reference [8] that after the
long-term action of superstructure, vertical bearing capacity of pile can increase by 20% compared
with the original design value when settlement of pile foundation was basically terminated, but the
support materials were not given. If the foundation displacement exceeds the design expectations,
checking and evaluation for bearing capacity of foundation should be conducted, but the method and
requirements not give also in the reference [9]. Although evaluation for bearing capacity of existing
pile foundation are put forward in these code, but there is no field monitoring data to support these
evaluation method.
In conclusion, clear and reasonable methods to evaluate the bearing capacity of pile foundation
need to fully grasp the long-term bearing capacity of pile foundation by monitoring.
In order to analyze the influence of side friction of drilled piles by different load-adding route,
three groups of drilled piles of three bridges constructed by different method in Xinwan interchange of
Qianjiang Passageway and Connecting Project were monitored.
Group 1 has three piles located in the main line viaduct, and loaded by static load test.
Group 2 has two piles located in the main line viaduct, loaded by dead load of superstructures,
which were constructed by segmental hanging basket.
Group 3 has two piles located ramp bridge, loaded by dead load of superstructures, which were
constructed by overall support cast-in-place.
2 Test Overview
446
In-Situ Monitoring of Side Friction of Drilled Piles by Different Loading Methods Li-Qing et al.
3 Monitoring Results
Calculation equation for pile side friction as follows:
qsi (Qi Qi 1 ) /(uli ) (1)
Where, qsi is pile side friction between pile section i and i+1 in kPa; Qi is axial force at pile section i
447
In-Situ Monitoring of Side Friction of Drilled Piles by Different Loading Methods Li-Qing et al.
-2
Q/kN
-4
-6
-8
-10
-12
-14
-16
-18
-20
-22
s/mm
Fig.11: Q~scurve of G12-2
G Fig.2: s~lgt curvee of G12-2
-10 -10
1st stage(40000kN)
-20 -20
2nd stage(60000kN)
-30 -30 3rd stage(80000kN)
1st stage(4000kN) 4th stage(100000kN)
2nd stage(6000kN
N) -40 5th stage(120000kN)
-40
3rd stage(8000kN) 6th stage(140000kN)
-50 4th stage(10000kN
N) -50
7th stage(160000kN)
5th stage(12000kN
N) 8th stage(180000kN)
-60 -60
6th stage(14000kN
N) 9th stage(190000kN)
-70 7th stage(16000kN
N) -70 10th stage(200000kN)
8th stage(18000kN
N)
-80 9th stage(19000kN
N) -80
Elevation of sectio
on i/m 10th stage(20000k
kN) -90
Elevattion of sectioni/m
-90
Fig.3: Axial fforce at differennt load stages off G12-2 Fig.4: Side frictionn at different load stages of G112-2
448
In-Situ Monitoring of Side Friction of Drilled Piles by Different Loading Methods Li-Qing et al.
-4
-6
-8
-10
-12
-14
-16
s/mm
m
Fig.55: Q~scurve of
o G15-5 Fig.6: s~lgt c
curve of G15-55
-2
20 -20 1st stage(40
000kN)
1st stage(4000kN) 2nd stage(6000kN
6 )
-3
30 -30
2nd stage(60000kN) 3rd stage(80000kN)
-4
40 4th stage(100000kN)
3rd stage(80000kN) -40
5th stage(122000kN)
-5
50
4th stage(100000kN)
-50 6th stage(144000kN)
5th stage(120000kN)
7th stage(166000kN)
-6
60 6th stage(140000kN) -60
8th stage(188000kN)
7th stage(160000kN) 9th stage(199000kN)
-7
70 -70
8th stage(180000kN) 10th stage(20000kN
2 )
-8
80 9th stage(190000kN) -80
10th stage(200000kN)
Elevation of sectionni/m on of sectioni/m
Elevatio
-9
90 -90
Fig.7: Axial fforce at differennt load stages off G15-5 Fig.8: Side frictionn at different load stages of G115-5
-2 Q/kN
-4
-6
-8
-10
-12
-14
-16
-18
-20
-22
-24
s/mm
m
Fig.99: Q~scurve of
o G17-5 Fig.10: s~lgt c
curve of G17-55
449
In-Situ Monitoring of Side Friction of Drilled Piles by Different Loading Methods Li-Qing et al.
0
Pile side friction qsi/kPa
0
-10 -10
1st stage(4000kN)
-20 -20 2nd stage(6000kN)
-30 1st stage(4000kN) -30
3rd stage(8000kN)
2nd stage(6000kN) 4th stage(10000kN)
-40
3rd stage(8000kN) -40 5th stage(12000kN)
4th stage(10000kN) 6th stage(14000kN)
-50 -50
7th stage(16000kN)
5th stage(12000kN)
-60 -60 8th stage(18000kN)
6th stage(14000kN)
9th stage(19000kN)
7th stage(16000kN)
-70 -70 10th stage(20000kN)
8th stage(18000kN)
-80 9th stage(19000kN) -80
10th stage(20000kN) Elevation of sectioni/m
-90 Elevation of sectioni/m -90
Fig.11: Axial force at different load stages of G17-5 Fig.12: Side friction at different load stages of G17-5
0 0
-10 -10
-20 -20
Pile cap poured
-30
Pier body poured -30 Pile cap poured
0# segment poured Pier body poured
-40 1# segment poured -40
0# segment poured
2# segment poured 1# segment poured
-50 -50
3# segment poured 2# segment poured
-60 4# segment poured -60 3# segment poured
5# segment poured 4# segment poured
-70 6# segment poured -70
5# segment poured
Closure segment poured
-80 -80 6# segment poured
Elevation of sectioni/m Closure segment poured
-90
Elevation of sectioni/m -90
Fig.13: Axial force at different load stages of G38-3 Fig.14: Side friction at different load stages of G38-3
10
0
0
-10
-10
-20
-20
Pile cap poured Pile cap poured
-30
-30 Pier body poured Pier body poured
0# segment poured -40 0# segment poured
-40
1# segment poured 1# segment poured
2# segment poured -50
-50 2# segment poured
3# segment poured 3# segment poured
-60 -60
4# segment poured 4# segment poured
5# segment poured -70 5# segment poured
-70
6# segment poured 6# segment poured
-80 Closure segment poured -80
Closure segment poured
Elevation of sectioni/m -90 Elevation of sectioni/m
-90
Fig.15: Axial force at different load stages of G38-4 Fig.16: Side friction at different load stages of G38-4
450
In-Situ Monitoring of Side Friction of Drilled Piles by Different Loading Methods Li-Qing et al.
0 0
-10 -10
-20 -20
Pile cap poured
-30 Pile cap poured -30
Pier body and girder poured
Pier body and girder poured
-40 -40
-50 -50
-60 -60
-70
Elevation of sectioni/m -70
Elevation of sectioni/m
Fig.17: Axial force at different load stages of J2-1 Fig18: Side friction at different load stages of J2-1
0 0
-10 -10
-20 -20
Pile cap poured
Pier body and girder poured
-30 Pile cap poured -30
Pier body and girder poured
-40 -40
-50 -50
-60 -60
-70
Elevation of sectioni/m -70
Elevation of sectioni/m
Fig19: Axial force at different load stages of J2-2 Fig.20: Side friction at different load stages of J2-2
451
In-Situ Monitoring of Side Friction of Drilled Piles by Different Loading Methods Li-Qing et al.
5 Conclusions
Side frictions of three groups’ drilled piles (total 7 piles) were monitored during the Xinwan
interchange of Qianjiang Passageway and Connecting Project construction. The following conclusions
were drawn based on the present study.
(1) Axial force and Side friction in all the piles increased step by step during the load-adding
procedure.
(2) Piles in Group 1 and Group 3 have different repose time. Side frictions monitored from piles
in Group 3, which have longer repose time, were larger than those in Group 1 under the same load.
This shows that repose time affects side friction.
(3) Side frictions monitored from piles in Group 2, which have longer off-time between two
loading stage, were larger than those in Group 1 under the same load. It can be seen that load-adding
route also affects side friction.
(4) Pile bearing performance were monitored only in the local area in this paper, more similar
monitoring in different types of engineering geology needed to be conducted so as to accumulate more
data and find the rule.
6 Acknowledgements
The research work presented herein is sponsored by the Construction Technology Funds of the
Ministry of Transport of China.
References
[1] YANG Long-caiˈGUO Qing-haiˈZHOU Shun-huaˈet al. Dynamic behaviors of pile foundation of high-speed
railway bridge under long-term cyclic loading in soft soil [J]. Chinese Journal of Rock Mechanics and
Engineeringˈ2005, 24(13): 2362-2368.
[2] Writing committee. Handbook for pile engineering [M]. Beijing˖China Architecture and Building Pressˈ1995.
[3] ZHENG Gang, REN Yan-hua. Effects of time-effect of pile’s bearing capacity on pile-soil interaction and on
settlement of pile-raft foundation[J]. Rock and Soil Mechanics, 2003, 24(1): 65-69.
452
In-Situ Monitoring of Side Friction of Drilled Piles by Different Loading Methods Li-Qing et al.
[4] CHEN Lan-yun, CHEN Yun-min, ZHANG Wei-min. Time-effect on vertical bearing capacity of single drilled
grouting pile in saturated soft soil[J]. Rock and Soil Mechanicsˈ2006, 27(3): 471-474.
[5] LI Yong, TENG Yan-jing. Experimental Study on Redesign of Pile Foundation[J]. Building Science, 2011,
27(3): 84-86.
[6] LI Yong. Experimental study on redesign of pile foundation for increasing storey on built building [MS.
Thesis][D]. Beijing: China Academy of Building Research, 2010.
[7] ZHANG Li-qing, LV Ying-zhao, YANG Yu. Field monitoring for bearing behavior of super long bored pile in
the whole bridge construction[J]. Journal of Zhejiang Institute of Communications, 2014, 15(1): 15-20, 30.
[8] Railway Transport Order [2004] No. 120, Code for evaluation of railway bridge[S]. Beijing: China Railway
Press, 2004.
[9] JTG/T J21-2011, Specification for inspection and evaluation of long-bearing capacity of highway bridges[S].
Beijing˖People’s Communications Press, 2011.
453