Beruflich Dokumente
Kultur Dokumente
APRIL 2019
APRIL- 2019
Index
1. KEY PERFORMANCE INDICATORS (KPI): ................................................................................................... 4
2. Executive Summary ................................................................................................................................... 5
3. HSE MANAGEMENT ................................................................................................................................... 8
3.1. Fulfillment of HSE Plan – KPI # 9 ....................................................................................................... 8
3.2. HSE Inspection – KPI #10 ................................................................................................................... 8
3.3. Watch Cards: Number of Watch Cards per Supervisor – KPI # 11 ................................................... 9
3.4. Percentage of HSE Training Man-hours – KPI # 12 ........................................................................... 9
3.5. Expired Corrective Actions required – KPI # 13 .............................................................................. 10
3.6. Number of Lost Time Incidents (LTI)– KPI # 14 ............................................................................... 10
3.7. Recordable Incident Rate (RIR) - KPI # 15 ....................................................................................... 11
3.8. Severe Vehicular Accident - KPI # 16 .............................................................................................. 11
3.9. Number of Environmental Issue (Oil spill, hazardous chemical spill)- KPI # 17 ........................... 12
4. Planning Management ............................................................................................................................ 13
4.1. Schedule Compliance ...................................................................................................................... 13
5.1.1. Schedule Compliance of Total (Corrective+Preventive) Work Orders. KPI #4 ...................... 13
5.1.2. Compliance of Preventive Jobs. .............................................................................................. 14
5.1.3. Safety Critical Equipment Preventive Work Orders Compliance. KPI#5 ............................... 15
5.1.3.1. Safety Critical Equipment Report – April 2019 ....................................................................... 15
5.1.3.1.1. Detail of device in Preventive Maintenance ...................................................................... 15
5.1.3.1.2. Corrective Maintenance ...................................................................................................... 16
5.1.4. Quantity of Work Orders Completed ..................................................................................... 16
5.2. Proactive to Corrective Ratio – APRIL 2019 .................................................................................... 16
5.3. Feedback of Work Orders – APRIL 2019 - KPI #7 ........................................................................... 18
5.4. Backlog – APRIL 2019 ...................................................................................................................... 18
5. Human Resources Management ............................................................................................................. 20
5.1. Manpower Craft Availability KPI #3 ............................................................................................... 20
5.2. Hiring personnel .............................................................................................................................. 20
5.3. Resignation of personnel: ............................................................................................................... 20
5.4. Turnover indicator. (Target =3%) .................................................................................................... 21
6. Appendix .................................................................................................................................................. 22
2
Figure 2. Number of HSE Inspection .................................................................................................................. 8
Figure 3. Number of Watch Cards per Supervisor. ............................................................................................ 9
Figure 4. Percentage of HSE Training Man-hours .............................................................................................. 9
Figure 5. Expired Corrective Actions required ................................................................................................. 10
Figure 6. Number of Lost Time Incidents (LTI) ................................................................................................. 10
Figure 7. Recordable Incident Rate (RIR) ......................................................................................................... 11
Figure 8. Number of Severe Vehicular Accident .............................................................................................. 11
Figure 9. Number of Environmental Issue (Oil spill, hazardous chemical spill ................................................ 12
Figure 10. Schedule Compliance tendency of total Work Orders.................................................................... 13
Figure 11. Schedule Compliance Tendency of Preventive Activities ............................................................... 14
Figure 12. Schedule Compliance of Preventive Work Orders APRIL ................................................................ 14
Figure 13. Safety Critical Equipment tendency of Preventive Work Orders Compliance ................................ 15
Figure 14. Schedule Compliance of Safety Critical Equipment from APRIL-2019 ............................................ 15
Figure 15. Work Orders per maintenance type ............................................................................................... 16
Figure 16. Preventive to Corrective man-hour Ratio ....................................................................................... 17
Figure 17. Man hours distribution ................................................................................................................... 17
Figure 18. Feedback Report Compliance ......................................................................................................... 18
Figure 19.Backlog tracking by discipline .......................................................................................................... 19
Figure 21. Monthly Manpower availability tendency ...................................................................................... 20
Figure 22. Accumulated personnel turnover indicator. ................................................................................... 21
3
Monthly Maintenance Report – APRIL 2019
Non-
Measureme Contractual New
Perspective #KPI KPI Compliance APRIL YTD
nt unit Target Target
Penalty
Failure to provide stipulated
Maintenance
#1 service due to absence of Value N/A 0 0 0 0
process
contractor
Maintenance Re work associated to any
#2 Value N/A 0 0 0 0
process Safety Critical Equipment
Maintenance
#3 Manpower Craft Availability % Penalty 2% 90% 95% 97% 97.3%
process
4
2. Executive Summary
Executive Summary
HSE
General: During April PLNG service reached 580.000 WH with no LTI, during April a MVA
incident occurred, root causes analysis was developed and corrective actions were taken.
HSE Inspections: HSEQ fulfilment from the inspection is more than 95%, during April HSEQ
inspection reduced but even though they were 10 % more than objective and deviation stood
under 2.0 % during this month.
Most representative deviation on the HSEQ inspections conducted on April were Procedures
and instructions, as well as PTW and JSA, deviation detected on this aspects don’t include high
potential non compliances, however corrective actions are conducted for assure jobs related
and decrease deviations on daily activities.
During April PTW audits were increased as a measure to improve procedure compliance on
all disciplines crews, as well as continues disclosure of procedures and instructions to avoid
recurrence on deviations.
Barricades Pro
33%
Excavation
Procedures
33%
Proc. LOTO
34%
5
Per capita on April compliance of HSEQ aspects had a result of 83% on the lowest result for
mechanic crew, although a compliance goal has not been set yet, results does not show
critical trend.
HSE Audit: No external or internal audits performed during April, neither open actions from
past audits.
HSE Campaigns:
During April recognition program continued and the chosen worker for April was Eduardo
Palomino from Mechanic crew.
During April a safety week campaign was deployed as a celebration for the world safety day on
April 28th with participation of other contractors on site.
WATCH observation program to improve workers participation continue, observations during
April reached 747 observation registered, 33 substandard conditions identified and 4 near
misses reported.
ATS Pending
The findings recorded in the Action Tracking System due MVA were closed in a timely manner.
Action in progress: 0, Close actions during April: 4, Overdue actions: 0.
Maintenance
Backlog:
6
Painting Backlog is 29.6 weeks from this Backlog 7.9 Weeks (8450 Man hour) will enter to the
Painting Extraservices, only is considered the base load (18 painters), respect to insulation Backlog
in the same way is considered the base load crew (3 Technician), a proposal was issued on April 9th
to reduce the backlog after that Hunt request add to the proposal 4.5 weeks of new planned jobs.
Preventive Maintenance Compliance: the compliance of Preventive Maintenance Plan of April was
99%, the pending job has already completed on May 2th.
Highlights of April:
7
3. HSE MANAGEMENT
Fulfillment of HSE Plan (%): # of executed actions vs. # of programmed actions on monthly basis.
8
3.3. Watch Cards: Number of Watch Cards per Supervisor – KPI # 11
% of HSE Training Man-hours: # of Man-hours utilized in HSE trainings vs. # of total man-hours
worked by Contractor on monthly basis
9
Table 5. HSE Training Man-Hour by month
10
3.7. Recordable Incident Rate (RIR) - KPI # 15
Number of Recordable Incidents *1,000,000/Total Hours worked
11
3.9. Number of Environmental Issue (Oil spill, hazardous chemical spill)- KPI # 17
12
4. Planning Management
General Considerations.
Month is the period when the Work Order were completed: Actual finish date within the period
of 1st to 30th of APRIL
Scheduled WO: Is any WO which has been scheduled in the month
To see the Data Base, check the Annexed 5.
13
5.1.2. Compliance of Preventive Jobs.
Compliance is the ratio of preventive Activities performed versus the number of activities with
target date in the month.
Target of preventive Work Orders Compliance is 95%.
14
5.1.3. Safety Critical Equipment Preventive Work Orders Compliance. KPI#5
Target of SCE Compliance is 100%
Figure 13. Safety Critical Equipment tendency of Preventive Work Orders Compliance
Discipline Functional Location Work Orders Quantity Instrument/Equipment Tested ISBL (Equipment/Instrument) OSBL (Equipment/Instrument)
Gas Detector 2 26 26 0
Flame Dtectors 4 24 24 0
Head Detector 4 8 6 2
Manual Station 1 10 10 0
Strobe light 11 50 50 0
Instrumentation Smoke Detector 2 61 0 61
Manual Station 32 31 11
Smoke Detector 27 0 27
Strobe light 5 26 20 6
HS 6 6 0
Panel (JX-F-1192) 1 0 1
Electrica Lighting System 2 2 1 1
FIRE TRUCK E-ONE 1 1 0 1
CRANE-HYD INSP. MAINT.
1 1 0 1
15TON
CRANE-HYD INSP. MAINT.
1 1 0 1
Automotive 40TON
CRANE-HYD INSP. MAINT.
1 1 0 1
55TON
CRANE-HYD INSP. MAINT.
1 1 0 1
80TON
Mechanical Hydrant 7 53 53 0
15
Table 16. Description of Preventive SCE Work Orders
Discipline Functional Location Work Orders Quantity Instrument/Equipment Tested ISBL (Equipment/Instrument) OSBL (Equipment/Instrument)
Gas Detector 2 2 2 0
Instrumentation
Smoke Detector 1 1 1 0
Mechanical 2 2 2 0
Hydrant
Table 17. Description of Corrective SCE Work Orders for process equipment and lifting equipment.
Table 18. Explanation of SCE corrective action for process equipment (Instrument devices and FWV).
Note: The references come from the ISO 14224 standard in section B.2.5 “Maintenance Activity”
16
Etiquetas de fila Corrective Proactive Total general
Electrical 739.5 739.5
Instrumentation 402 832.6 1234.6
Mechanical 740.1 2126.95 2867.05
Services 460.4 10146.7 10607.1
Total general 1602.5 13845.75 15448.25
17
5.3. Feedback of Work Orders – APRIL 2019 - KPI #7
Target of Feedback reporting
18
Figure 19.Backlog tracking by discipline
2.8 Weeks (1453 M-h) are wash jobs of Painting Work orders.
6.2 Weeks (3146 M-h) is Backlog Ready to perform
o 3.5 Weeks of the Ready BL is distributed on the Rlof Cleaning (600 Mh) and washdown
the 512 insulator below the LNG tanks (3401 & 3402) (1200 Mh) a proposal will be
submitted in order to perform this jobs.
Insulation: A proposal to reduce the insulation backlog was issued on April 9th, then
was planned 744 Mh (4.5 Weeks) to included them in this proposal, the final Gantt chart will
issued on May 10th.
Mechanical: A proposal about Mechanical backlog is on going.
Civil: The proposal to perform the WO 100041361 (Repair grouting sealant
broken on Jetty : Total 2778 Mh) was issued, is in evaluation.
19
5. Human Resources Management
5.1. Manpower Craft Availability KPI #3
20
5.4. Turnover indicator. (Target =3%)
Vacancy of personnel:
Quantity Job Tittle Candidate or Status
1 Sr. Intrumentation Technician IN PROCESS
1 Painter IN PROCESS
1 Painter IN PROCESS
21
6. Appendix
6.1. HSE KPI
22
6.2. Supervisory attendance to Safety meeting.
23
24
25
26