ACITIVITIES SEPT. OCT. NOV. DEC. JAN. FEB. MAR. APR. MAY. JUN. JUL. AUG.

A. Excavation
.05 .05
B. Water/Sewer
.10
C. Footings
.04 .04 .02
D. Columns
.025 .05 .025
E. Floor
.025 .05 .025
F. Walls
.025 .075

G. Roof
.025 .05 0.25
H. Plumbing
.025 .075
I. Electrical
.025 .075
J. Finishes
.025 .075
Program 5% 5% 14% 4% 4.5% 5% 7.5% 12.5% 10% 20% 5% 7.5%
Accomplishments
Cumulative 5% 10% 24% 28% 32.5% 37.5% 45% 57.5% 67.5% 87.5% 92.5% 100%
Accomplishments
S-CURVE 100.00%
100.0%
92.50%
87.50%

80.0%

67.50%

57.50%
60.0%

45.00%
`

37.50%
40.0%
32.50%
28.00%
24.00%

20.0%
10.00%
5.00%

0.0%

Duration