11Time and Action Calendar- (PRODUCT DEVELOPMENT)

S.NO PROCESS START DATE FINISH DATE


1 Order Confirmation 15/04/2019
2 Order of Shell Fabric 15//04/2019
3 Receipt of Breakdown 17/04/2019
4 Order of Sewing/Finishing Trims 17/04/2019
5 Fit Submission 17/04/2019 7/05/2019
6 Fit Approval a 14/05/2019
7 Wash submission 17/04/2019 16/05/2019
8 Wash Approval 23/05/2019
9 Receipt Sewing Trims 16/05/2019
10 YTS Submission 17/05/2019 30/05/2019
11 YTS Approval 15/06/2019
12 GTS Submission 15/06/2019 25/06/2019
13 GTS Approval 27/06/2019
14 Hand Over Production file to PPC 17/06/2019
15 Bulk fabric I/H 10/06/2019
16 Shade Shrinkage Process 10/06/2019 13/06/2019
17 Lot segregation as per shrinkage and shade 14/06/2019
18 Patterns Ready 15/06/2019
19 Receipt of Bulk Fabric 17/06/2019
20 Size Set making 17/06/2019 20/06/2019
21 Size Set Review 20/06/2019 22/06/2019
22 Shade Band Approval 23/06/2019
23 Pre Production Sample 24/6/2019
24 PPM 25/06/2019
PRODUCT AND DELIVERY

S.NO PROCESS START DATE FINISH DATE


1 Bulk Cutting 27/06/2019
2 Sewing 29/06/2019 09/07/2019
3 Inspection 29/06/2019 09/07/2019
4 Washing 1/07/2019 10/07/2019
5 Finishing 3/07/2019 12/07/2019
6 Pressing 3/07/2019 12/07/2019
7 Final Checking 3/07/2019 12/07/2019
8 Packaging 3/07/2019 12/07/2019
9 Internal Quality Audit 15/07/2019
10 External Quality Audit 17/07/2019
11 Quantity delivered to internal Warehouse 17/07/2019
12 Goods Dispatched from warehouse to Buyer 17/07/2019