BILL OF MATERIALS
SCOPE OF WORK QTY. UNIT MAT'L UNIT AMT. MAT'L TOTAL AMT.
I. CONSTRUCTION PLANS AND SPECS
Plans 1 set 5000 5000
SUBTOTAL 5000
II. APPLICATION OF PERMIT
Permits 1 lot 9250 9250
SUBTOTAL 9250
III. MOBILIZATION
Electricity and Water Meter 1 setup 10000 10000
Temporary Toilets 1 setup 22000 22000
Temporary Storage 1 setup 12000 12000
Perimeter Fencing 1 lot 12000 12000
Site Clearing 1 lot 11000 11000
SUBTOTAL 67000
IV. EXCAVATION WORKS
Soil Poisoning 200 sq.m 100 20000
Layout and Staking 1 lot 12000 12000
SUBTOTAL 32000
V. CONCRETE AND MASONRY WORKS
Cement 1238 bags 195 241,410
Sand 75 cu.m. 225 16,875
Gravel 74 cu.m. 400 29,600
CHB #4 208 pcs 10 2,080
CHB #6 5496 pcs 15 82,440
SUBTOTAL 372,405
VI. REBAR WORKS
10 mm dia. 1295 pcs 122 157,990
12 mm dia. 73 pcs 177 12,921
16 mm dia. 550 pcs 317 174,350
Tie Wire 209 kgs 75 15,675
SUBTOTAL 360,936
VII. FORMWORKS AND SCAFFOLDINGS
4' x 8' x 1/4" Plywood 19 pcs 260 4,940
Structural Steel 61 pcs 132 8,052
Structural Steel Ties 23 pcs 75 1,725
1.2m x 2.4m Metal Sheet 6 pcs 1220 7,320
2' x 3' Coco Lumber 918 bdft 177 162,486
2' x 2' Coco Lumber 898 bdft 159 142,782
SUBTOTAL 327,305
VIII. STEEL WORKS
Angle Bar 73 pcs 290 21,170
C - Purlins 41 pcs 350 14,350
Base Plate 0.56 sq. m. 280 157
10 mm dia. 5 pcs 127 635
Cutting Disc 2 pcs 57 114
Welding Rod 5 kgs 83 415
Hacksaw 1 pc 159 159
Hacksaw Blade 3 pcs 55 165
SUBTOTAL 37,165