About Wako Gutu Foundation
(WGF)
 Wako Gutu Foundation (WGF) is an Ethiopian
development organisation founded by network of
volunteers who wanted to bring enduring change to the
livelihood of pastoralists and agro-pastoralist communities
in the remote areas of the country.
 The organisation was established as a local NGO in 2006 in
memory of General Wako Gutu, “an Ethiopian pastoralist
elder and a peace and justice activist” who in addition got
also engaged in development activities
Cont.
 Accordingly, WGF is registered under the Ethiopian CSA Act
as a national resident CSO (with registration certificate 0457
pursuant to the Charities and Societies Proclamation number
621/2009) and it is supervised by a board of director following
the legal requirement for memorial foundation in Ethiopia.

 WGF is a member of the Pastoralist Forum Ethiopia, Poverty


Action Network in Ethiopia, Non-State Actors Coalition,
Ethiopian Extractive Industries Transparency Initiatives, and
Zonal and District Disaster and Early Warning Committee.
Cont.
 The organisation has made programmatic positioning in the
pastoralist areas of Oromia and Somali National Regional
States particularly in Bale zone areas namely Dallo Mana,
Madda Wallabu, etc.
 WGF successfully accomplished various projects ranging
from small to large on livelihoods, humanitarian and
emergency, water supply, sanitation and hygiene, gender
empowerment, social accountability, agriculture and
irrigation, natural resource management and conservation,
and more to list.
Cont.
Vision: WGF is committed to see socio-economic
advancement of poor pastoralist communities and further
realization of the strong mutual cooperation of
neighboring communities with similar life style.
Mission: The mission of WGF is to facilitate social and
economic empowerment of the poor and marginalized
communities through the implementation of integrated,
sustainable and pro-poor projects in the remotest and inaccessible
pastoral/agro-pastoralist areas.
Mobile-Phone Enabled Agricultural Livelihoods
& Health Extension for Agro-pastoralists Life
Transformation in Hinterlands (MEAL &
HEALTH) Project
• The project is to be implemented in the Gindhir and
Gura Dhamole districts of the Bale Zone, Oromia
National Regional State

• The project has a total budget of ---------birr for the tw


districts
Cont.
• The project is intended to impact 11, 667 direct
beneficiary households and 156,000 indirect households
from neighboring districts of Guji, Borena, Arsi, Harari
Regional state, DireDawa City Administration, etc.

• The project will last for five years starting from 01


December 2017 and ends on 30 November 2022

• The project assumes 35% of each of the beneficiary


individuals at each activity level will be female/women
Project Objectives
The overall objective of the MEAL and HEALTH
Project is to improve the pastoralists and agro-
pastoralists of agricultural extension and
livelihoods in Gurra Dhamole and Gindhir districts
of Bale zone, Oromia National Regional State.
Cont.
The specific objectives of this project are:
1. To familiarize the use of Mobile Agricultural
Extension Services by 60% for 11,700 (2,340
• women) targeted households at the end of 2022.
1. To adopt 3 innovative agricultural production
methods for 2,340 farmers (546 women) pastoralist
and agro pastoralist communities by the end of the
project period 2022.
Cont.
1. To reduce food gap of at least 7,020 households (2,340
female) pastoralist and agro pastoralist communities in
Gurra Dhamole and Gindhir districts from 7 months to 3
months at the end of 2022.
2. To raise income of 3,900 households (2,340 women)
pastoralist and agro pastoralist communities from x% to
Y% by the end of 2022.
Project Strategies
WGF follows the following strategies on the
course of implementation

A participatory approach that promotes and


stimulates beneficiary involvement from
planning to execution.
Cont.
This is accomplished through hired staffs at the two
project districts and effective monitoring actions
that in turn facilitates to ascertain value for money
(cost effectiveness and cost efficiency).
Gender empowerment, and capacity development
will be integrated as a cross-cutting issues at each
level of this project management (planning to
execution-evaluation)
Project Components
Component 1 (-------birr): Project Start-up Activities

which encompasses the activities like launching


workshops, experience sharing visits, etc.
Component 2 (------birr):Development of Agricultural Extension
Services

This sub-component includes:

generation (extraction of agricultural cycle) major and


sub activities, localization of generated contents;
Cont.
customization (modification to area context); translation
(changing to local languages) of content; curating (uploading)
of the content to server; dissemination (pushing the
information to users) of developed content, TOT for
agriculture and health extension agents, train community
leaders on agricultural and health extension system
Component 3 (-------birr) Maternal and Child Health (MCH)

which includes generation (extraction of agricultural


cycle) major and sub activities,
Cont.
localization of generated contents; customization (modification to
area context); translation (changing to local languages) of content;
curating (uploading) of the content to server; dissemination (pushing the
information to users) of developed content

Component 4 (---birr) Information and Communication


Development
This sub-component involves: information and Development (content of
mobile technology categories), Generator and Cooling funs, and Digital
Classroom System (DCS)/ Digisoft Education
Cont.
Component 5 (------birr): Contracting Airtime which includes:
airtime payment for disseminations of 21 agricultural cycle and
14 reproductive health information by using server PULL for
25,000 minutes, Airtime payment for disseminations of 21
agricultural cycle and 14 reproductive health information by
using server PUSH

Component 6 (-----birr):awareness and Community


Mobilization which includes: publicize and awareness creation
using TV, Radio and mobile van video broadcasting (roadsides,
towns village shows), and Video Edutainment Van
Cont.
Component 7 (-----birr): improvement of food security in Arid
and Semiarid areas which comprises of the following
activities:
Training of HHs on soil and water conservation
management, support model HHs with early maturing and
drought tolerant crops, train and provide HHs (drought
resistant sorghum and soybean), introduction and
demonstration of model farmers on drought-tolerant
amaranth,
Cont.
establish fruit nurseries groups, training of HHs on vegetable
production, train young pastoralists on beekeeping, establish
and support irrigation users & provide them with water
pumps, train model farmers on nutrition & food preparation,
promote and train farmers on animal forage production,
distribution of improved feed seeds for HHs, train & equip
voluntary animal health workers on basic animal health,
recovery of cows and goats for HHs, and construction of
reservoirs for the drinking water supply of farm animals
Project Procurement (----birr)
• The project will procure some equipment and
supplies that are intended to serve the
implementation such as vehicles (2), motor cycles
(6), Laptops (7), desktops(6) and printers(2), Video
camera(2) & set of Audio visual (1), tables (10),
chairs (16), shelves (5) and guest chairs (5),
generator (1)
Baseline, Monitoring and Evaluation (----
birr)
• The project will start with baseline survey during the first
quarter of its implementation (in year 1/2018), and
expected to undertake periodic monitoring actions

• The project conducts mid-term evaluation in the middle


course of implementation

• The project also conducts end-line evaluation


immediately after the project terminates

• Bi-annual audit will be regularly conducted


Project Human Resource
• The project will employ appropriate staffs for the
implementation of this project.

• Thus WGF hires pastoralist livelihood manager,


monitoring and evaluation officer, and ICT expert at head
office, agriculture extension (2), health extension expert
(2) at headquarter

• The project further hires project coordinators(2),


agronomists(2), veterinarians (2), office assistants (2)
Project Coordination
WGF in collaboration with relevant government offices
and target communities will implement the project.
Programmatically the project is directly managed under
WGF head office. Project offices will be established at
Jibri and Gindhir towns, and respective staffs will be
hired to engage in full time implementation of the
project. Accordingly, WGF head office in Finfine will
provide technical and resource support.
Cont.
The Executive Director will give overall leadership, whereas the
pastoralist livelihood manager will be responsible to provide
program related backstopping which include monitoring of timely
implementation of planned activities, tracking effect chain and
impact maps so that the project will be an outcome and impact
oriented. WGF finance section will deal with financial matters-
releases work advances up on approval of the Director; check the
reliability of receipts, and settle the financial accounts; ensure
proper documentation of all financial transaction of the project.
Cont.
• The project staff comprising of agronomist, veterinarian,
agricultural extension and health extension workers guided
by respective project coordinators will be responsible for
coordinating the implementation of project activities;
mobilize the community for participation in planning and
implementation, identify the right holders/beneficiaries,
monitor proper utilization of project resources, supervise
the quality of project outputs, and settle in case there are
any disputes among the community related to the project.
Contact details
Address:
Wako Gutu Foundation (WGF) Lagahar area in front of Yiha City Centre
between Ambassador Garment and Shebelle fashion
P.O. Box 11821, Addis Ababa, Ethiopia
Tel. (+251) 0115318049
E mail: wakogutufound@yahoo.co.uk
Website: www.wakogutufoundation.org
Contact Person: Abdi Edao
Position: Executive Director
Tell. +251 911043027 (mobile)
Tell. (+251) 0115318049 (office)
MEAL and HEALTH Project Life Work-
plan
S/N List of Activities Unit of Number
Measure of Units Year of Implementation
ment
Year 1 Year 2 Year 3 Year 4 Year 5

1 Project Launching

1.1 3 national and regional launching # of ppts 117


events at various levels
1.2 Experience sharing visits to South # of trips 2
Africa and Kenya

2 Agricultural Content

2.1 Generation (extraction of Content 21


agricultural cycle information) 9
major activities and 12 sub
activities, in Afan Oromo and Somali
(lowlands dialect)

2.2 Localization of generated contents Content 21

2.3 Customization (modification to area Content 21


context)
2.4 Translation (changing to local Content 21
language) of content
2.5 Curating (uploading) of the content to Content 21
server

2.6 Dissemination (pushing the Content 21


information over mobile phone and
video on sites

2.7 TOT training for Agriculture and health # of trainees 1,170


extension workers

2.8 Refresher training for DA’s, HEW and # of trainees 1,170


rural agricultural value chains
actors/community leaders

3 Reproductive Mother Neonatal Child


Health (RMNCH)

3.1 Generation (extraction of 14 health Content 14


information) 6 major activities and 8
sub activities

3.2 Localization of RMNCH contents Content 14

3.3 Customization of RMNCH contents Content 14

3.4 Translation of RMNCH contents Content 14

3.5 Curating of reproductive RMNCH Content 14


contents
3.6 Dissemination of RMNCH contents Content 14

4 ICT infrastructure development and


integration:
ICT infrastructure development and
integration (Hardware and software for
IVR, SMS and USSD, including audio
visual for centralized data center

4.1 Information and Development (content Number 4


of mobile technology categories)

4.2 Generator and Cooling funs Number 1

4.2 Digital Classroom System (DCS)/ Digi- Number 10


soft Education

5 Airtime for PULL & PUSH Services of


IVR and including short code rent

5.1 Airtime payment for disseminations of # of months 60


21 agricultural cycle and 14
reproductive health information by
using server PULL for 25,000 minutes
5.2 Airtime payment for disseminations of # of months 60
21 agricultural cycle and 14
reproductive health information by
using server PUSH

5.3 E1 and two short code purchase, # of months 60


installation and monthly lease

6 Mediated video aided agriculture and


Health extension

6.1 Publicize and awareness creation using # of casting 47


TV, Radio and mobile van video /sessions
broadcasting (roadsides, towns village
shows)

6.2 Video Edutainment Van for agriculture No. 1


and health extension services
sensitization

7 Promotion of semi-arid and arid


livelihood diversification

7.1 Training of HH on soil and water # of HHs 702


conservation management
7.2 Support model HHs with early # of model 2,574
maturing and drought tolerant crops HHs

7.3 Train and provide HHs (40% female) on # of HHs 2,340


improved drought resistant sorghum
and soybean

7.4 Introduction and demonstration of # of Farmers 234


drought-tolerant amaranths to model
farmers

7.5 Establish nurseries groups (10 persons/ # of Groups 16


group) and provide skills training on
production of fruit seedlings

7.6 Training of HHs (780 women) on # of HHs 2,340


vegetable production for 3 days

7.7 Train young pastoralists on beekeeping # of trainees 156

7.8 Establish and support irrigation users # of users 47


& provide 47 water pumps

7.9 Train model farmers on nutrition & # of trainees 122


food preparation

7.10 Promote and train farmers on animal # of farmers 390


forage production for 5 days
7.11 Provide improved animal feed # of farmers 780
inputs/seeds for farmers

7.12 Establish, equip and train VCAHWs on # of 234


basic animal health care for 10 days & VCAHWs
equip them

7.13 Recovery of 1,560 cows for 780 HHs # of HHs 1,950


and 2,340 goats at 1,170 HHs

7.14 Construction of reservoirs - 10,000m3 # of 3


each - for the drinking water supply of reservoirs
approximately 15,000 farm animals

8 Baseline setting, Monitoring , and


Evaluation

8.1 Baseline information setting/conduct Number 1


baseline survey

8.2 Monitoring and follow up Quarter 20

8.3 Mid-Term Evaluation Number 1

8.4 Terminal Evaluation Number 1

9 Personnel

9.1 Admin project staff Months

9.2 Program staff Months


10 Administration costs

10.1 Vehicles Running cost, spare parts and Months


maintenance

10.2 Project Office rent Months

10.3 Project office supplies and consumable Months

10.4 Project Motorcycle running cost Months

10.5 Indirect cost/coordination cost (7% of Months


total expenditure)

11 Audit

11.1 Conduct project audit Bi-annual 10

12 Procurement

12.1 Two vehicles and six motor cycle Number 8

12.2 Laptop (7), desktop (6) and printer (2), Number 18


Video camera (2) & set of Audio visual
(1)

12.3 Tables (10), chairs (16), shelves (5) and Number 36


guest chairs (5)
MEAL and HEALTH Project Action Plan for 2018
S/N List of Activities Unit of Number of Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Measurement Units

1 Project Launching

1.1 3 national and regional launching # of ppts 117


events at various levels

1.2 Experience sharing visits to South # of trips 2


Africa and Kenya

2 Agricultural Content

2.1 Generation (extraction of Content 21


agricultural cycle information) 9
major activities and 12 sub activities,
in Afan Oromo and Somali (lowlands
dialect)

2.2 Localization of generated contents Content 21

2.3 Customization (modification to area Content 21


context)
2.4 Translation (changing to local language) Content 21
of content

2.5 Curating (uploading) of the content to Content 21


server

2.6 Dissemination (pushing the information Content 21


over mobile phone and video on sites

2.7 TOT training for Agriculture and health # of trainees 1,170


extension workers

2.8 Refresher training for DA’s, HEW and # of trainees 1,170


rural agricultural value chains actors

3 Reproductive Mother Neonatal Child


Health (RMNCH)

3.1 Generation (extraction of 14 health Content 14


information) 6 major activities and 8 sub
activities

3.2 Localization of RMNCH contents Content 14


3.3 Customization of RMNCH contents Content 14

3.4 Translation of RMNCH contents Content 14


3.5 Curating of reproductive RMNCH Content 14
contents

3.6 Dissemination of RMNCH contents Content 14


4 ICT infrastructure development and
integration:
ICT infrastructure development and
integration (Hardware and software
for IVR, SMS and USSD, including
audio visual for centralized data
center

4.1 Information and Development Number 4


(content of mobile technology
categories)

4.2 Generator and Cooling funs Number 1

4.3 Digital Classroom System (DCS)/ Digi- Number 10


soft Education

5 Airtime for PULL & PUSH Services of


IVR and including short code rent

5.1 Airtime payment for disseminations of # of months 6


21 agricultural cycle and 14
reproductive health information by
using server PULL for 25,000 minutes
5.2 Airtime payment for disseminations # of months 6
of 21 agricultural cycle and 14
reproductive health information by
using server PUSH

5.3 E1 and two short code purchase, # of months 6


installation and monthly lease

6 Mediated video aided agriculture


and Health extension

6.1 Publicize and awareness creation # of casting


using TV, Radio and mobile van video
broadcasting in 47 sessions
(roadsides, towns village shows)

6.2 Video Edutainment Van for No. 1


agriculture and health extension
services sensitization

7 Promotion of semi-arid and arid


livelihood diversification

7.1 Training of HHs on soil and water # of HHs


conservation management
7.2 Support model HHs with early # of model
maturing and drought tolerant crops HHs

7.3 Train and provide HHs (40% female) # of HHs


on improved drought resistant
sorghum and soybean

7.4 Introduction and demonstration of # of


drought-tolerant amaranths to 234 Farmers
model farmers

7.5 Establish groups (10 persons/ group) # of Groups


nurseries and provide skills training
on production of fruit seedlings

7.6 Training of HH (780 women) on # of HHs


vegetable production for 3 days

7.7 Train young pastoralists on # of


beekeeping trainees

7.8 Establish and support irrigation users # of users


& provide water pumps

7.9 Train model farmers on nutrition & # of


food preparation trainees

7.10 Promote and train farmers on animal # of farmers


forage production for 5 days
7.11 Provide improved animal feed # of
inputs/seeds for farmers farmers

7.12 Establish, equip and train VCAHWs on # of


basic animal health care for 10 days VCAHWs
& equip them

7.13 Recovery of cows and goats for HHs # of HHs

7.14 Construction of reservoirs - # of


10,000m3 each - for the drinking reservoirs
water supply farm animals

8 Baseline setting, Monitoring , and


Evaluation

8.1 Baseline information setting/conduct Number 1


baseline survey

8.2 Monitoring and follow up Quarter 4


9 Personnel

9.1 Admin project staff Months 7

9.2 Program staff Months 17

10 Administration costs

10.1 Vehicles Running cost, spare parts and Months 6


maintenance

10.2 Project Office rent Months 12

10.3 Project office supplies and Months 12


consumable

10.4 Project Motorcycle running cost Months 9

10.5 Indirect cost/coordination cost (7% of Months 12


total expenditure)

11 Audit

11.1 Conduct project audit Bi-annual 2

12. Procurement

12.1 Two vehicles and six motor cycle Number 8

12.3 Laptop (7), desktop (6) and printer (2), Number 18


Video camera (2) & set of Audio visual
(1)

12.4 Tables (10), chairs (16), shelves (5) Number 36


and guest chairs (5)