Fanar Residential Project

Look ahead till reaching Ground floor

Start Date Finish Date


Building B I Vertical elements up to GF 21-Feb-12 12-Mar-12
Ground Floor Slab 13-Mar-12 26-Mar-12
MEP embedded items B3 & B2 ongoing ongoing
Block Works 5-Mar-12 7-Apr-12
Building B II Verticals up to B1 20-Jan-12 22-Feb-12
B1 floor slab 28/2012 28-Feb-12
Vertical elements up to GF 29-Feb-12 20-Mar-12
Ground Floor Slab 21-Mar-12 30-Mar-12
MEP embedded items ongoing ongoing
Block Works 24-Mar-12 18-Apr-12
Building A I Verticals up to B2 1-Feb-12 22-Feb-12
B2 floor slab 23-Feb-12 7-Mar-12
Vertivals up to B1 8-Mar-12 21-Mar-12
MEP embedded elements ongoing ongoing
Building A II Slab on Grade 14-Feb-12 21-Mar-12
veticals up to B2 10-Mar-12 27-Mar-12
B3 floor Slab 28-Mar-12 13-Apr-12
verticals up to B1 14-Apr-12 27-Apr-12
B2 floor slab 28-Apr-12 9-May-12
Verticals up to GF 10-May-12 23-May-12
Ground Floor Slab 18-May-12 31-May-12
Block C Excavation works 10-Mar-12 TBA
anchoring 1-Mar-12 TBA
7-Jun-19
Delay
13 days
13 days
-
22 days
14 days
5 days
3 days
3 days
-
18 days
11 days
11 days
11 days
-
5 days
0
0
0
0
0
0
-
-
Beirut Gardens Project
Look ahead till reaching Ground floor

Start Date
Zone 1 3rd Floor Slab 16-Feb-12
Verticals up to 4th floor 26-Feb-12
4th Floor Slab 5-Mar-12
Verticals up to 5th floor 13-Mar-12
5th floor Slab 19-Mar-12
Zone 2 1st Floor Slab 19-Dec-11
verticals to 2nd Floor 12-Feb-12
2nd Floor Slab 10-Mar-12
verticals to 3rd Floor 26-Mar-12
Misc. Technical Area at 1st floor 1-Mar-12
Zone 1 2nd floor extension slab (construction joint) 27-Mar-12
Zone 1 3rd floor extension slab (construction joint) 4-Apr-12
Zone 1 4th floor extension slab (construction joint) 12-Apr-12

New trades Block Works in 1st, 2nd and basements 1-Mar-12


Basement Tiling 1-Mar-12
MEP Works in Basements 5-Mar-12
ect
d floor
7-Jun-19
Finish Date Delay Remarks
25-Feb-12 48
6-Mar-12 48 Reaching upper slabs delays
could be compensated next
12-Mar-12 47 to sunny weather conditions
21-Mar-12 47 and site clearance
1-Apr-12 47
3-Mar-12 75
9-Mar-12 75 An EOT Clain is processed in
this regard, pursuing Contract
25-Mar-12 75 Claus 44.1
5-Apr-12 70
21-Mar-12 75
the technical area delayed
3-Apr-12 25 the zone 1 3rd floor slab,
11-Apr-12 25 J.Hani sorted a technical
19-Apr-12 25 solution to resume works in
the desired areas

- 10 days in adv Site is compesating delays by


- 36 days in adv introducing new trades
- on time ahead of time
Beirut Gardens Project
Look ahead till reaching Ground floor

Start Date
Zone 1 3rd Floor Slab 16-Feb-12
Verticals up to 4th floor 26-Feb-12
4th Floor Slab 5-Mar-12
Verticals up to 5th floor 13-Mar-12
5th floor Slab 19-Mar-12
Zone 2 1st Floor Slab 19-Dec-11
verticals to 2nd Floor 12-Feb-12
2nd Floor Slab 10-Mar-12
verticals to 3rd Floor 26-Mar-12
Misc. Technical Area at 1st floor 1-Mar-12
Zone 1 2nd floor extension slab (construction joint) 27-Mar-12
Zone 1 3rd floor extension slab (construction joint) 4-Apr-12
Zone 1 4th floor extension slab (construction joint) 12-Apr-12

New trades Block Works in 1st, 2nd and basements 1-Mar-12


Basement Tiling 1-Mar-12
MEP Works in Basements 5-Mar-12
ect
d floor
7-Jun-19
Finish Date Delay Remarks
25-Feb-12 48
6-Mar-12 48 Reaching upper slabs delays
could be compensated next
12-Mar-12 47 to sunny weather conditions
21-Mar-12 47 and site clearance
1-Apr-12 47
3-Mar-12 75
9-Mar-12 75 An EOT Clain is processed in
this regard, pursuing Contract
25-Mar-12 75 Claus 44.1
5-Apr-12 70
21-Mar-12 75
the technical area delayed
3-Apr-12 25 the zone 1 3rd floor slab,
11-Apr-12 25 J.Hani sorted a technical
19-Apr-12 25 solution to resume works in
the desired areas

- 10 days in adv Site is compesating delays by


- 36 days in adv introducing new trades
- on time ahead of time