REPORT
FOR
TO
UNCOVERED
GOVERNMENT SCHOOLS
OF
DISTRICT SHOPIAN
Proposals:
It is proposed to lay 25mm / 20mm dia G.I. pipe line and connect
it with PVC tank fixed on iron stand for facilitating water
supply to the respective schools.
Cost:
The total financial implication for providing the water supply to
the uncovered schools including pipe material cost is
`33.28 lacs.
Executive Engineer,
PHE. Divn. Shopian
GENERAL ABSTRACT
Detailed Estimate for provding Water Supply to Schools
Amount
S. No. Description
(Rs in lacs)
1 25/20mm dia pipe (10600 mtrs) @Rs 130/- Mtr 13.78
Executive Engineer
PHE Division Shopian
LIST OF UNCOVERED SCHOOLS OF PHE DIVISION SHOPIAN FOR THE YEAR 2018-19
List verified with reference to the communication from Chief Education Officer vide his No.
1 HS Nazneenpora Uncovered 0.30 0.40 0.70
his No.
List verified with reference to the communication from Chief Education Officer vide his No.
28 PS Nadigund Uncovered 0.15 0.20 0.35
29 PS Baskuchan Uncovered 0.50 0.25 0.75
30 PS Thokerpora Uncovered 0.15 0.20 0.35
31 PS Nadpora Cheiki Sangren Uncovered 0.50 0.25 0.75
32 PS Malnard Sugan Uncovered 0.50 0.25 0.75
33 PS Bongam Aglar Uncovered 0.50 0.25 0.75
34 PS Heff Uncovered 0.50 0.25 0.75
Executive Engineer
PHE Divn. Shopian.