Beruflich Dokumente
Kultur Dokumente
Duration Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Mode Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
1 Design, Supply and Installation 110/20kV Substation 18.88 mons 18.88 mons
4/2 9/30
Kombinat
2 Item Schedule No. 1. Plant and Mandatory Spare Parts Supplied 16.39 mons
from Abroad
3 1 Transformer 9 mons 9 mons
31 13.2 Light and power installation, incl. emergency lighting (lot) 3 mons 3 mons
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: TIME SCHEDULE
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 3/1/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 1
ID Text1 Task Task Name Duration Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Mode Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
35 15 Connection to the transmission network 3 mons
50 8.1 Dead End Tower Design including foundation Design 1 mon 1 mon
51 8,2 Angle tension tower Design including foundation Design 1 mon 1 mon
52 8.3 Detailed Design for connection to the substation 0.5 mons 0.5 mons
56 1.1 Site elevation of the terrain by at least1 (one) meter from the 1 mon 1 mon
actual level (lot) Control and 20kV switchgear building
57 1.1.1 Structural work (lot) 1.5 mons 1.5 mons
66 1.2.8 Connections to drinking and waste water points (lot) 0.7 mons 0.7 mons
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: TIME SCHEDULE
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 3/1/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 2
ID Text1 Task Task Name Duration Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Mode Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
68 1.3 Oil separator for the 110/20kV power transformer (lot) 1 mon 1 mon
73 1.8 Foundations for line gantries (lot) 1.5 mons 1.5 mons
74 1.9 Cable trenches for 20kV cables for power transformer and 1.6 mons 1.6 mons
aux. transformer (lot)
75 1.10 Cable trenches for control cabling (lot) 2 mons 2 mons
76 1.11 Cable trench for 20kV outgoing cables approx. 20m 2 mons 2 mons
78 1.13 Perimeter fence and access gates 2.5 mons 2.5 mons
79 1.14 Ground level finishing works: graveling, borders of access 3 mons 3 mons
paths, cleaning, etc. (lot)
80 2 Electromechanical works Erection (incl. cabling and 5 mons 5 mons
earthing), site testing, commissioning
81 3 Factory acceptance tests 1 mon 1 mon
85 6.1 Removal and storage on part of existing 110 kV OHTL 2 mons 2 mons
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: TIME SCHEDULE
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 3/1/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 3