Scheduling/Leveling Report - 02-Mar-19 09 - PM.

exe
==================================================

Default Project..................................................EMAAR-T3-
RBL-3

Projects:
EMAAR-T3-RBL-3...................................................EMAAR
PEARL TOWERS - CONSTRUCTION OF TOWER 3 AT PLOT 7 - UPDATED PROGRAM (22-FEB-19)

Scheduling/Leveling Settings:
-----------------------------
General
-------
Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................No
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Retained
Logic
Calculate start-to-start lag from ...............................Early Start
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish Float
Calculate float based on finish date of .........................Each project
Calendar for scheduling Relationship Lag ........................Predecessor
Activity Calendar

Advanced
--------
Calculate multiple float paths...................................No

Statistics:
-----------
# Projects.......................................................1
# Activities.....................................................2478
# Not Started....................................................1472
# In Progress....................................................149
# Completed......................................................857
# Relationships..................................................4801
# Activities with Constraint.....................................0

Errors:
-------
Warnings:
---------
Activities without predecessors..................................1
Project: EMAAR-T3-RBL-3 Activity: MOB-0000 Project Start

Activities without successors....................................1


Project: EMAAR-T3-RBL-3 Activity: HAN-1020 Project Finish

Out-of-sequence activities.......................................16
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV1-01000 Electrical
Cable Trays
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV1-01135 Exposed
Refrigerant Piping with Y Branches
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV16-01020 Electrical
and Communication Wiring
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV16-01130 Embedded
Refrigerant Piping with Electrical Wiring
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV17-01130 Embedded
Refrigerant Piping with Electrical Wiring
Project: EMAAR-T3-RBL-3 Activity: EX-AM-PO2-01135 Exposed
Refrigerant Piping with Y Branches
Project: EMAAR-T3-RBL-3 Activity: EX-RF-00110 Foundation for MEP
Equipment
Project: EMAAR-T3-RBL-3 Activity: EX-RF-00220 External Plaster
(Floor 6 to 10)
Project: EMAAR-T3-RBL-3 Activity: SA-SD-AR-1580 Shop Drawing
Submittal
Project: EMAAR-T3-RBL-3 Activity: SA-SD-EL-1060 Shop Drawing
Submittal
Project: EMAAR-T3-RBL-3 Activity: SA-SD-HVAC-1060 Shop Drawing
Submittal
Project: EMAAR-T3-RBL-3 Activity: SA-SD-HVAC-1080 Shop Drawing
Submittal
Project: EMAAR-T3-RBL-3 Activity: SA-SD-MEP-1040 Shop Drawing
Submittal
Project: EMAAR-T3-RBL-3 Activity: SA-SD-MEP-1060 Shop Drawing
Submittal
Project: EMAAR-T3-RBL-3 Activity: SA-SD-NG-1060 Shop Drawing
Submittal
Project: EMAAR-T3-RBL-3 Activity: SA-SD-NG-1080 Shop Drawing
Submittal

Activities with Actual Dates > Data Date.........................0

Milestone Activities with invalid relationships..................0

Finish milestone and predecessors have different calendars.......0

Scheduling/Leveling Results:
----------------------------
# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................2478
# Relationships with other projects..............................0
Data Date........................................................22-Feb-19 08
Earliest Early Start Date........................................22-Feb-19 08
Latest Early Finish Date.........................................23-Jan-20 18
Exceptions:
-----------
Critical Activities..............................................27
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV12-01140 Metal Ducts
with Insulation and Cladding
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV13-01140 Metal Ducts
with Insulation and Cladding
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV14-01140 Metal Ducts
with Insulation and Cladding
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV15-01140 Metal Ducts
with Insulation and Cladding
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV16-00880 uPVC
Drain/Soil/Waste Piping
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV16-01140 Metal Ducts
with Insulation and Cladding
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV17-00880 uPVC
Drain/Soil/Waste Piping
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV17-01140 Metal Ducts
with Insulation and Cladding
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV18-00880 uPVC
Drain/Soil/Waste Piping
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV18-01140 Metal Ducts
with Insulation and Cladding
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV19-00880 uPVC
Drain/Soil/Waste Piping
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV19-01140 Metal Ducts
with Insulation and Cladding
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV20-00880 uPVC
Drain/Soil/Waste Piping
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV20-01140 Metal Ducts
with Insulation and Cladding
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV21-00880 uPVC
Drain/Soil/Waste Piping
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV21-01140 Metal Ducts
with Insulation and Cladding
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV22-00880 uPVC
Drain/Soil/Waste Piping
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV22-01140 Metal Ducts
with Insulation and Cladding
Project: EMAAR-T3-RBL-3 Activity: EX-AM-LV23-01140 Metal Ducts
with Insulation and Cladding
Project: EMAAR-T3-RBL-3 Activity: EX-RISER-00100 uPVC Piping
for Plumbing Drainage (Podium 2 - 9th Floor)
Project: EMAAR-T3-RBL-3 Activity: EX-RISER-00103 uPVC Piping
for Plumbing Drainage (10th - 18th Floor)
Project: EMAAR-T3-RBL-3 Activity: EX-RISER-00105 uPVC Piping
for Plumbing Drainage (19th - 25th Floor)
Project: EMAAR-T3-RBL-3 Activity: EX-RISER-00140 Ducting for
HVAC (Podium 2 - 9th Floor)
Project: EMAAR-T3-RBL-3 Activity: EX-RISER-00143 Ducting for
HVAC (10th - 18th Floor)
Project: EMAAR-T3-RBL-3 Activity: EX-RISER-00145 Ducting for
HVAC (19th - 25th Floor)
Project: EMAAR-T3-RBL-3 Activity: EX-TC-00120 Testing and
Commissioning of HVAC Equipments with Air Balancing
Project: EMAAR-T3-RBL-3 Activity: EX-TC-00150 Testing and
Commissioning of Plumbing Systems

Activities with unsatisfied constraints..........................0

Activities with unsatisfied relationships........................0

Activities with external dates...................................0