Beruflich Dokumente
Kultur Dokumente
CM-02
CM-02
66 1/24/2019 WSF MISC SC-10 SLIDE GATE VALVE OF KNO3 SCREW FEEDER
67 1/24/2019 WSF MISC SC-20 SLIDE GATE VALVE OF MKP SCREW FEEDER
68 1/24/2019 WSF MISC SC-30 SLIDE GATE VALVE OF UREA SCREW FEEDER
PG Drain hose provided Extra dosing / leaking of liquid stopped to Bladdder Mixer
Pipe connection for unloading from CPH For CPH unloading, reduced flange arrangement done
Drums From scrap yard. and necessary parts are welded by fitter.
- As per instruction from Anandbhai, for taking 5 ton stone blockfrom Mech
workshop.
Load test as per requirement - by crane it was positioned near hoist trolley.
- Checked and tested , OK .
Belt slipping oil was applied on IAC compressor's Belt which was given by Anand
sir.
Both Air Compressor problem , Double screw rotary Elgi air compressor
Air Pressure not rise above 4 kg cleaning air filter from compressor
, inspecting oil filter.
- Air suction elbow to motor was inspected.
- Cleaning of valve.
- Oil filter(after dryer) Leakage problem, bolt with high layer tefflon tap was applied.
Tail side - material jammed, open flange and clean bearing. Given in line.
Reported RAV tobe checked Also found drive side bearing not ok,replacement job tobe taken tomorrow.
noise problem Vendor came to solve noise problem coming from belt.
Hoist rope cleaning and greasing Diesel was taken from PA Plant for hoist cleaning purpose.
Previous day work in progress
Bearing needs to be changed - arranged oil seal having same size from DAP
New Bearing and Oil seal replaced,Trial taken found working smoothly.
Logistic Deptt.requirement Three nos. of Light dome prepared with wall stand and fixed on WSF warehouse.
Two nos. of SEALPACK machine repaired. Two nos. of Temp. Sensors and four nos.of
Both M/C out of order heating Rod procured & replaced , working checked,now both machine working ok.
Issue related to bottom Mixer /Blander Hydraulic gate not operating properly
Left side gate stopped working.. ,attended.
Hoist rope cleaning by diesel & greasing was done as per instructed &
Hoist rope cleaning Confirm with GSFC.
Inspect both bearing of RAV collecting sillo, both bearing condition are ok..
Inspection & PM Greasing was done to both bearings.
Hose connection for unloading CPH Tank side 1" pipe was attached on flange for filling tank from CPH drum.
Sealing was not working properly Elec+Mech team replaced damaged parts
One side belt coming out from conveyor Belt was adjusted at its postion
CPH unloading pipe and flange was arranged and connected to pump for unloading
Bagging conveyour Belt operation Bagging conveyour Belt, all 8 no. of roller geasing done
as per instruction of GSFC: rotation direction of blender was changed by Electrical
frequently paddle brake down connection pole change
nozzle clogged clogging was cleaned and damaged part was replaced
squeak problem & one v belt was damage dismentled for inspection and found shear pin damaged, shear pin was
replaced , belt was replaced
squeak problem & shear pin found broken shear pin was changed
oil filling in gera box and greasig 1. 4 nos pillw block, 2. 4 nos shaft collar, 3. 2
Oiling and greasing nos UCFC Bearing, 4. 4 nos UCFC Bearing
Required pressure not achieving Cleaing and vissul inspection was done
Arrangement for material unloading flange and hose connection done for unloading cph
abnormal sound FROM CHAIN GUARD Bolt tightening and guard position adjustment done
hose connectoion arrangemetn done throught out the length of take and
vissual level indiator needed connection done to nozzle at bottom
TROLLY HANDLE BRAKE DOWN HANDLE WAS REPAIRED AND FIXED
NOISE OBSERBER IN MATING GEAR GUARD WAS OPENED AND VISSUAL INSPECTION DONE
NEED TO PROVIDE ROUITE FOR SLIDE GATE VALVE OPEN AND BOXUP
MATERIAL UNLOAD
NEED TO PROVIDE ROUITE FOR MATERIAL SLIDE GATE VALVE OPEN AND BOXUP
UNLOAD
CRUSHED MATERIAL SIZE FOUND ABOVE 1 OPEN SIDE COVER AND GAP WAS MEASURED BY FILLER GAUGE.
MM WHICH MUST BE CONSTRAINED. ONE SIDE 1.05 MM OTHER SIDE 0.85 MM
CRUSHED MATERIAL SIZE FOUND ABOVE 1 RUSTOLINE AND WD-40 WAS APPLIED ON STUD FOR NUT ADJUSTMENT SHOWN TO
MM WHICH MUST BE CONSTRAINED. ANAND SIR.
Bellow was jamemd with material. Bellow was loosened and lump was removed.
Motor did not rotate. Problem was temperory solved by mechanical team.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
Under Progress
completed.
completed.
Under Progress
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
under observation
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
under observation
completed.
completed.
completed.
completed.
Under Progress
Under Progress
completed.
completed.
completed.
completed.
Under Progress
completed.
Under Progress
completed.
completed.
MAINTENANCE REPORT -01/02/2019 TO 28
NO Date Area PM / CM/MISC TAG NO EQUIPMENT/ NAME
1 2/1/2019 SAG PM H-05(A) RAV of Product Silo
NOZZLE CLOGGED 4 NOS NOZZLE SHEET REPLACEMEN & 1 NOS NOZZLE INSTALLED
HIGH DUSTING PROBLEM A TEPORARY COVER FRAM WITH TARPOLIN WAS MADE AND INSTALLED
SUCTION PRESSURE
HIGHT DUSTING PROBLEM DUST SUCTION WAS OPEN, CLEANED AND BOXUP FOUND LOW
LINE MODIFICATION 1/2 INCH LINE MODIFICATION DONE FOR DRAINING PURPOSE .
ELEVATOR WAS JAMMED DUE TO BY OPENING BOTTOM GATE MATERIAL REMOVED AS WELL AS TOP SIDE
MATERIAL JAMMED MATERIAL WAS DECHOKED.
ELEVATOR TOP SIDE MATERIAL TOP SIDE PLATE WAS ADJUSTED FOR PROPER MATERIAL FEEDING IN PIPE
FEEDING RESTRICTION
OIL NEEDS TO BE
CHANGED IF
BOTTOM GATE CLOSING PROBLEM PRESSURE RELIEF VALVE BLOCK WAS OPENED AND PARTS ARE CLEANED. FREQUENTLY PROBLEM
ARISES IN FUTURE
REQUIREMENT OF CPH UNLOADING CPH unloading side Drum suction arrangement was done By
FROM 225 LTR DRUM Replacing Flange.
during inspection 2
SPRAY PUMP PRESSURE RAISES UPTO No. of nozzles found
NOZZLE SHEETS WERE CLEANED AND REPLACED
2.5 kg/cm2(REQ 1-1.5 kg/cm2) working(out of 5 no.
nozzles)
during inspection
filter found torn out
STRAINER WAS CARRIED OUT TO CHECK ITS CONDITION, MESH SCREEN
- as well as material
WAS REPLACED. clogging inside
screen
during inspection
STRAINER WAS CARRIED OUT TO CHECK ITS CONDITION, MESH SCREEN
- filter found torn out
WAS REPLACED. and damaged.
-
old filter screen was immersed in CPH to check compatibility of next day screen
found damaged and
Filter screen easily torn.
LEVEL INDICATOR PIPE WAS TIED WITH ANGLE PLATE AS WELL AS ANGLE
- PLATE WAS COLOURED.
SUCTION HDPE PIPE JOINT GOT OUT BUTT FUSION WAS REQUIRED TO JOIN WHICH WAS DONE IN PA PLANT
CPH TANK WAS EMPTY. CPH UNLOADING PUMP SIDED FLANGE WAS NEED
FLANGE CHANGE NEEDED TO BE CHANGED FOR FILLING CPH FROM CPH DRUM.
BUSH NEED TO CHANGE PULLEY AND OTHER PARTS WERE DISMANTLED AND BUSH WAS ABNORMAL SOUND
(ABNORMAL SOUND) CHANGED. STILL PRESENT.
ABNORMAL SOUND
ROLLER GAP WAS SET AS PER PREVIOUS ONE, SUGGESTED FROM P.D. ABNORMAL SOUND
MISTRY SIR AS GRANUAL SIZE WAS ALSO IMPORTANT. STILL PRESENT.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.
completed.