PROCUREMENT TIMELINE (IDEAL)

Date
Posting 24-May-19 01-Jun-19

Pre-Bid Conference 01-Jun-19 13-Jun-19 06-Jun-19

Supplemental/Bid Bulletin 06-Jun-19

Submission 13-Jun-19 25-Jun-19

Post Qualification 25-Jun-19 26-Jun-19

Board Reso 26-Jun-19 11-Jul-19

Approval of HOPE 11-Jul-19 12-Jul-19

Notice of Award 12-Jul-19 22-Jul-19

Contract 22-Jul-19 29-Jul-19

Notice to Proceed 29-Jul-19 13-Aug-19

Posting 13-Aug-19
ACTUAL DATE FROM POST QUA
Date
20-Feb-19 21-Feb-19

21-Feb-19 08-Mar-19 ACTUAL DATE FROM APPROVAL


DATE
08-Mar-19 09-Mar-19 19-Mar-19 20-Mar-19
DATE OF RECEIPT
09-Mar-19 19-Mar-19 19-Mar-19 29-Mar-19

19-Mar-19 26-Mar-19 29-Mar-19 05-Apr-19

26-Mar-19 10-Apr-19 05-Apr-19 20-Apr-19

10-Apr-19 20-Apr-19

From date of receipt


ACTUAL DATE FROM CONTRACT
DATE

08-Mar-19 15-Mar-19

15-Mar-19 30-Mar-19

30-Mar-19