TOP OF CURB

FOR SLOPE
REQ.'S SEE
12 3/4"
NOTE 1.
7" 7"

FLOWLINE FLOWLINE

2-2" G.I. PIPE OR PVC PIPE

8" MIN.,OVER 12' DEEP


5'
12" MIN. UP TO 6' FROM
TOP OF CURB.

5' 12" 15"

3000
PIPE
P.S.I.
CONC.

1/2' D

6" 6' 4" 6' 4"


6" UP TO 12' DEEP
12"OVER12'DEEP

IF STRUCTURE IS GREATER THAN


12' DEEP, FOOTING IS TO EXTEND
6" BEYOND THE STRUCTURE

NOTES:

1. THE SLOPE OF THE GUTTER TO THE CATCH BASIN ON THE UPHILL SIDE SHALL BEGIN 10'
FROM THE CATCH BASIN. THE SLOPE OF THE GUTTER TO THE CATCH BASIN ON THE
DOWNHILL SIDE , SHALL BEGIN 5' FROM THE CATCH BASIN.

2. STEPS SHALL BE INSTALLED IN ALL CATCH BASINS OVER 3' IN DEPTH. DEPTH SHALL BE
MEASURED FROM THE TOP OF THE GUTTER TO THE INVERT OF THE CATCH BASIN.

3. SOLID CONCRETE BRICKS MAY BE USED IN 4" X 4" X 16" OR 4" X 8" X 16" SIZES.

4. NCDOT APPROVED PRECAST CONCRETE BOXES ACCEPTABLE, USING STANDARD 5' CASTINGS.

5. DOMESTIC CASTING REQUIRED WITHIN STREET RIGHT OF WAY.

CITY OF RALEIGH
PUBLIC WORKS DEPARTMENT

REVISIONS DATE: 9/1/13 NOT TO SCALE

DOUBLE WIDTH
CATCH BASIN

SW-10.02