Contents of Delivery
2 © Nokia 2016
1. KIT Delivery Contents Code
2U Blank Filler 3BK50599AA
OMK3 190mm Depth 3BK63581AA
Re-hosting Kit
Power Cable [1, 2 pcs] 3BK63251AA
Air Blocking Panel 3BK63516AA
NOTE:
1, The list of ASMI module is for information only ad former Nokia HW will be ordered separately.
2, The AMIA and ASIA accessory bag are delivered with AMIA/ASIA.
3 © Nokia 2016
Install ASMI in LRI Cabinet Configuration#26
4 © Nokia 2016
INSTALLATION PREPARE REMOVE
SETUP ASMI COMPONENTS
5 © Nokia 2016
1. Installation Setup
STEP 1: Open Frame Door
6 © Nokia 2016
LRI Cabinet Configuration #26
2. Prepare the ASMI
STEP 3: Prepare the ABIA
ABIA Module
7 © Nokia 2016
2. Prepare the ASMI
STEP 4: Prepare the ASIA
8 © Nokia 2016
2. Prepare the ASMI
STEP 5: Prepare the AMIA
① Remove the AMIA rear cover by loosening and removing six torx screws.
② Set the hardware aside for being reused in a later step.
③ Gently pull off the rear cover to prevent damage to the EMI spring gasket.
10 © Nokia 2016
2. Prepare the ASMI
STEP 7: Remove the Power Bus Bar
11 © Nokia 2016
2. Prepare the ASMI
STEP 8: Check the Air Flow Direction
① Pull the fan out and see the air flow direction arrow on fan mechanics points.
② Make sure the air flow direction is front-to-back. If the air flow direction is back-to-front,
turn the fan 180 degrees and insert the fan back.
③ Route the fan cable between the top lid and fan.
④ Repeat the above steps for the second fan.
12 © Nokia 2016
2. Prepare the ASMI
STEP 9: Reinstalling the Rear Cover
13 © Nokia 2016
3. Remove Components
STEP 10: Disconnect the CCM(Alarms) Cable
① Disconnect the CCM (Alarm) cable from the RUC by pushing on the RJ-45’s locking tab and
disengaging.
② Leave the other end hanging.
③ This cable will not be reused.
14 © Nokia 2016
3. Remove Components
STEP 11: Disconnect the RUC INT Alarm Cable (if any)
① Disconnect the eAMiB INT cable from the RUC by pushing on the RJ-45’s locking tab and
disengaging.
② Leave the other end handing.
③ This cable will be reused in later step.
Fibers Disconnected
NOTE:
CPRI and backhaul Ethernet cables and associated SFP reused are foreseen. If not, please refer to ASMI
installation Document for CPRI/backhaul cabling.
16 © Nokia 2016
3. Remove Components
STEP 13: Remove BBU Power Cable
① Remove the BBU power cable between
the PDP and the BBU (RUC).
② Pull and slide down the black protective
boots to expose terminals.
③ Loose the M4 hardware using a wrench
with 7mm socket.
④ Remove the other end of the BBU
power cable by squeezing the locking
tab on the Molex Mini-FIT SR connector
and disengaging from the PDP for BBU.
⑤ The power cable will not be reused.
17 © Nokia 2016
3. Remove Components
STEP 14: Remove the RUC Ground Cable
① Remove the ground strap from the BBU (RUC’s) center terminal by removing the M4
hardware using a torque driver with 7mm socket.
② Remove the other end of the ground cable from the cabinet inter terminal by removing
the M6 hardware using a torque driver with 10mm socket.
③ The RUC ground cable will not be reused.
① Remove the ground strap from the BBU (Subrack) by removing the M4 hardware using a
torque driver with 7mm socket.
② Remove the other end of the ground cable from the cabinet inter terminal by removing
the M6 hardware using a torque driver with 10mm socket.
③ The BBU Subrack ground cable will not be reused.
① Remove the BBU from the right and left bracket. Loosen and remove four M6 screws.
② The BBU will not be reused.
③ Set the four screws aside for being reused in a later step.
BBU Removed
20 © Nokia 2016
4. Install Components
STEP 17: Install 2U Blank Filler
① Install the 2U blank filler to the OMK2 where the BBU has been removed.
② Secure it to the OMK2 by using four M6 screws remained in previous step.
③ Torque to 2.8Nm.
21 © Nokia 2016
4. Install Components
STEP 18: Install the Air Blocking Panel
Case 1: there is an air blocking panel in cabinet
22 © Nokia 2016
4. Install Components
STEP 18: Install the Air Blocking Panel
Case 2: there is no air blocking panel in cabinet
23 © Nokia 2016
4. Install Components
STEP 19: Install OMK3
① Install OMK3 to the vertical mounting rails below the TRDUs (above the air blocking panel).
② Align the mounting holes and use two M6 screws per bracket supplied with OMK3.
③ Torque to 2.8 Nm.
AMIA Installed
25 © Nokia 2016
4. Install Components
STEP 21: Install ESD Wrist Strap
① Attach the end of the wrist strap to one of the ‘ESD buttons’ on the AMIA.
② Place the other end around the user’s wrist.
26 © Nokia 2016
4. Install Components
STEP 22: Install ASIA into the AMIA
ASIA Installed
27 © Nokia 2016
4. Install Components
STEP 23: Install ABIA into the AMIA
ABIA Installed
28 © Nokia 2016
5. Install Cables
STEP 24: Reconnect the RUC INT Alarm Cable (if any)
① Reconnect the RUC INT alarm cable to D4U RUC.
Case 1: if the D4U has single CCM, connect to the lower RJ45 connector of lower RUC of D4U.
Case 2: if the D4U has two CCMs, connect to the lower RJ45 connector of upper RUC of D4U.
② Change 3G node B D4U BTSpackaging type to 9711 LightRadio indoor DC compact to allow
cabinet alarm management by the 3G system by using TIL commissioning tool.
(For commissioning method refer to 9YZ-06496-0090-PCZZA document)
29 © Nokia 2016
Case 1 Case 2
5. Install Cables
STEP 25: Install ASMI Ground Cable
① Ground the ASMI to the cabinet’s grounding point using items provided in ASIA accessory
bag.
② Attach one end of the cable to the ground tab on the ASIA with an M5 screw.
③ Torque to 2.8 Nm
④ Secure the other end to the cabinet’s grounding point with a flange nut.
⑤ Torque to 2.8 Nm
30 © Nokia 2016
5. Install Cables
STEP 26: Install ASMI Power Cable
① Using MC-TRDU power cable as ASMI power cable.
② Cut the end used to connect MC-TRDU.
③ Strip 4 cm of this end(if necessary) and 18 mm of the wires’ insulation using the cable
stripper.
CUT OFF
31 © Nokia 2016
5. Install Cables
STEP 26: Install ASMI Power Cable (continuing)
④ Lift the latch of the power cable input of ASIA plug-in unit.
⑤ Insert stripped end of the power cable into the power cable input.(0V black wire to the left of
terminal and -48V blue wire to the right of terminal). Push it all the way to the back of
terminal. Make sure there are no stray conductor strands.
DC IN TERMINAL
32 © Nokia 2016
5. Install Cables
STEP 26: Install ASMI Power Cable (continuing)
33 © Nokia 2016
5. Install Cables
STEP 27: Reconnect CPRI and Backhaul Ethernet Cables
① Reconnect backhaul Ethernet cable to EIF2 connector of ASIA.
② Reconnect 3 CPRI cables to RF1, RF2, RF3 connectors of first ABIA.
ASIA
ABIA
34 © Nokia 2016
6. Power Up
STEP 28: Power Up the Base Station
35 © Nokia 2016