Rollup Cumulative Lead

Times GUI program. This concurrent program populates the field Cumulative Total in
the item definition form. Cumulative Total Lead Time is the total time required to
make an item if no inventory exists and you have to order all
the raw materials and make all subassemblies level by level.

For buy items:


Cumulative Total Lead Time = Preprocessing Lead time + Processing Lead Time +
Postprocessing Lead Time
This is the formula we shall be referring to most frequently when analysing how
Planning schedules buy items.

For make items:


Cumulative Total Lead Time = Cumulative Manufacturing Lead Time + the maximum of
the Cumulative Total Lead Time of the previous (lower) level components