Sie sind auf Seite 1von 9

2/3/2019 Teaching the World About Wholesale Distribution

Emergency systems are the circuits and equipment that supply illumination, power, or
both within 10 sec [700.12] after interruption of the normal electrical supply [700.1]
(Fig. 1). The requirements for the installation, operation, and maintenance of these
systems are found in Art. 700.

One use of emergency systems is to provide lighting for safely evacuating buildings
that large numbers of people occupy (e.g., hospitals and sports arenas). These systems
may also provide power to maintain life, fire detection and alarm systems, elevators,
fire pumps, and public safety communications systems. They may even provide power
to industrial processes to prevent the serious life safety or health hazards that would
result from loss of power. But don’t confuse emergency systems with standby systems
(see SIDEBAR: Standby Versus Emergency).

Fig. 1. Article 700 applies to the installation, operation, and maintenance of emergency systems for illumination
and/or power within 10 sec (700.12) of the interruption of the normal electrical supply.

Testing and maintenance

To ensure the emergency system meets or exceeds the original specifications, the AHJ
must conduct or witness an acceptance test of the system after installationand before

https://www.ecmweb.com/training/teaching-world-about-wholesale-distribution 1/9
2/3/2019 Teaching the World About Wholesale Distribution

turnover to operations [700.3]. The initial testing also establishes baseline data for
maintenance of the system and its components.

The NEC requires periodic testing for maintenance. By “periodic,” the NEC means
doing the testing at intervals recommended by the applicable standards, industry
norms, and manufacturer literature. The AHJ refers to these to determine if the
testing frequency is adequate.

Load shedding

The emergency system must be able to supply all emergency loads simultaneously
[700.4(A)]. If an alternate power supply has adequate capacity, it may supply
emergency loads [Art. 700], legally required standby loads [Art. 701], and optional
standby system loads [Art. 702]. When the emergency supply also supplies power for
nonemergency loads, the emergency loads take priority. If it doesn’t have adequate
capacity to carry all loads, it must have automatic selective load pickup and load
shedding to ensure adequate power in this order of priority [700.12(B)]:

1) Emergency circuits

2) Legally required standby circuits

3) Optional standby circuits

A temporary alternate source of power must be available whenever the emergency


generator is out of service for more than a few hours for maintenance or repair.

Transfer equipment

Transfer equipment must be automatic, identified for emergency use, and approved
by the AHJ [700.5 (A)]. It must supply only emergency loads (Fig. 2). Automatic
transfer switches must be electrically operated, mechanically held, and listed for
emergency system use. You must use multiple transfer switches where a single
generator supplies emergency loads plus other loads.
https://www.ecmweb.com/training/teaching-world-about-wholesale-distribution 2/9
2/3/2019 Teaching the World About Wholesale Distribution

Fig. 2. The alternate power source is permitted to supply other loads in addition to emergency loads; however,
the transfer switch for emergency loads can only supply emergency loads.

Wiring

At the service-entrance equipment, place a sign indicating the type and location of on-
site emergency power sources [700.7]. Permanently mark the system’s boxes and
enclosures as components of an emergency system [700.10(A)]. That requirement
includes transfer switches, generators, and power panels for emergency circuits.

To ensure that a fault on the normal wiring circuits won’t affect the performance of
emergency wiring or equipment, keep all wiring to emergency loads independent of all
other wiring. These exceptions apply to:

https://www.ecmweb.com/training/teaching-world-about-wholesale-distribution 3/9
2/3/2019 Teaching the World About Wholesale Distribution

Fig. 3. To ensure a fault on the normal wiring circuits won’t affect the performance of emergency wiring or
equipment, keep all wiring to emergency loads independent of all other wiring, except for wiring in transfer
equipment.

• Wiring in transfer equipment (Fig. 3).

• Luminaires supplied from two sources of power.

• A junction box attached to luminaires supplied from two sources of power.

• Wiring within a common junction box attached to unit equipment, containing only
the branch circuit supplying the unit equipment and the emergency circuit supplied by
the unit equipment.

Wiring from an emergency source can supply any combination of emergency, legally
required, or optional standby loads — but only under one of these conditions [710(B)
(5)]:

https://www.ecmweb.com/training/teaching-world-about-wholesale-distribution 4/9
2/3/2019 Teaching the World About Wholesale Distribution

• It’s supplied from separate vertical switchboard sections or from individual


disconnects mounted in separate enclosures.

• It’s supplied from single or multiple feeders without overcurrent protection at the
source. You can provide overcurrent protection at the source (or for the equipment), if
the overcurrent protection is selectively coordinated with the downstream overcurrent
protection.

• The legally required and optional standby circuits don’t originate from the same
vertical switchboard section, panelboard enclosure, or individual disconnect enclosure
as emergency circuits.

How can you accomplish separation of the circuits served by a generator source for
emergency, legally required, and optional standby circuits? By running feeders from a
single generator to individual overcurrent devices or to a distribution switchboard that
separates emergency circuits in different vertical sections from other loads.

Design and locate emergency wiring circuits so as to minimize the hazards that might
cause failure due to flooding, fire, icing, vandalism, and other adverse conditions
[700.10(C)].

Power sources

You have six choices for the emergency power supply:

1) Storage battery

2) Generator set

3) UPS

4) Separate service

5) Fuel cell
https://www.ecmweb.com/training/teaching-world-about-wholesale-distribution 5/9
2/3/2019 Teaching the World About Wholesale Distribution

6) Individual unit equipment

Storage batteries must be of suitable rating and capacity to supply and maintain the
total load for 1½ hr, without the voltage applied to the load falling below 87½% of
normal [700.12(A)].

A generator set can be any of several configurations. If it’s prime mover-driven, it


must be:

• Approved by the AHJ.

• Sized per 700.5.

• Able to automatically start the prime mover when the normal service fails.

If you use internal combustion engines as the prime mover, provide an on-site fuel
supply sized for at least 2 hr of full-demand operation [700.12(B)(2)].

If an outdoor generator has a readily accessible disconnecting means within sight of


the structure, you don’t need an additional disconnecting means (on or at the
structure) for the generator feeder conductors that serve or pass through the
structure.

You don’t need to locate the generator disconnecting means within sight of the
structure served, if you satisfy these two requirements:

1) Conditions of maintenance and supervision ensure that only qualified persons will
monitor and service the installation.

2) Documented safe switching procedures are established and maintained for


disconnection.

https://www.ecmweb.com/training/teaching-world-about-wholesale-distribution 6/9
2/3/2019 Teaching the World About Wholesale Distribution

A UPS serving as the emergency power source must comply with the applicable
requirements for batteries and generators.

By individual unit equipment (IUE), the NEC means an emergency lighting battery
pack [700.12(F)]. These are traditionally shaped much like a lunchbox, and thus are
sometimes called “lunchboxes” in the field. They must include (Fig. 4):

Fig. 4. The battery-powered emergency light must contain a relay device to automatically energize the lamp
when there’s loss of power to the unit.

1) Rechargeable battery,

2) Battery charging means,

3) Provisions for one or more lamps mounted on the equipment, or terminals for
remote lamps (or both),

4) Relaying device that energizes the lamps automatically upon failure of the supply to
the unit.

IUE must be permanently fixed in place. A locking receptacle is optional. You can use
a flexible cord and plug connection for IUE designed for this purpose, if the cord
https://www.ecmweb.com/training/teaching-world-about-wholesale-distribution 7/9
2/3/2019 Teaching the World About Wholesale Distribution

doesn’t exceed 3 ft.

The branch circuit wiring that supplies IUE must be the same branch-circuit wiring
that supplies the normal lighting in the area. Don’t connect IUE to the emergency
circuit. It won’t operate upon loss of normal power, because it will still have power.

Connect the IUE ahead of any local switches. The branch circuit that feeds the IUE
must be clearly identified at the distribution panel per 110.22(A) and 408.4.

Emergency lighting systems must be designed and installed so that the failure of any
individual lighting element, such as the burning out of a lamp, won’t leave any space
that requires emergency illumination [700.16] in total darkness. So a single remote
head is never sufficient. This is why you always see two lighting heads on IUE boxes.

Overcurrent protection

The branch circuit overcurrent devices for emergency circuits must be accessible to
authorized persons only [700.25]. You don’t have to GFCI protect the alternate power
supply for emergency systems. But 700.7(D) requires ground fault indication of the
emergency power supply. Overcurrent devices for emergency systems must be
selectively coordinated with all supply-side overcurrent devices [700.27]. With
selective coordination, the overcurrent protection scheme confines the interruption to
a particular area. For example, if a short circuit or ground fault occurs with selective
coordination, the only breaker/fuse that will open is the one protecting that branch
circuit. The local fault won’t bring down the feeder or whole system.

Holt is the owner of Mike Holt Enterprises, Inc. in Leesburg, Fla. He can be reached
at www.mikeholt.com.

SIDEBAR: Standby Versus Emergency

A standby system automatically provides power to critical equipment if normal power


is interrupted. Standby systems may be optional (Art. 702) or legally required (Art.
701). A glass plant, for example, would want a standby system so that molten glass
https://www.ecmweb.com/training/teaching-world-about-wholesale-distribution 8/9
2/3/2019 Teaching the World About Wholesale Distribution

doesn’t solidify in the equipment and thus destroy it. A chemical plant might be legally
required to power systems that prevent an environmental release or a runaway
reaction.

Emergency systems are legally required and classed as emergency by a governmental


agency having jurisdiction. These systems automatically supply illumination and/or
power essential for safety to human life.

Sometimes, an emergency system simply provides power for exit lighting and exit
signs upon loss of the main power or in the case of fire. Its purpose isn’t to provide
power for normal business operations, but rather to provide lighting and controls
essential for egress to a safe area.

https://www.ecmweb.com/training/teaching-world-about-wholesale-distribution 9/9

Das könnte Ihnen auch gefallen