Beruflich Dokumente
Kultur Dokumente
01
Date: 25/04/12
Activities
1. Formwork to third floor roof window hoods
2. Masonry work i.e plaster work & block work and demolitions at revised areas.
3. plumbing work
4. Chasing walls for electrical and data conduits.
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.
Activities
1. Masonry work i.e plaster work & block work
3. plumbing works
4. Painting
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.
3.0 CANTEEN
Activities
1. Plaster work at wall plate level
-1-
2. Alignment of window openings
3. Cleaning/ sweeping
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.
Activities
1. Electrical installations
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.
5.0 WEIGHBRIDGE 01
Activities
1. Placing of the floor screed.
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.
6.0 WEGHBRIDGE 02
Activities
1. Placing of the floor screed.
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.
7.0 WORKSHOP
-2-
Activities
1. Painting
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.
8.0 STORE
Activities
1. Painting
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.
Activities
1. Painting
2. Masonry work i.e plaster work & block work
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.
Activities
1. Fixing of iron sheets on steel trusses
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.
Activities
1. Fixing/welding of pipes inside the shed
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.
Activities
1. Welding/fixing tank roof
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.
14.0 CUM
Activities
1. Fixing trusses to the pump shed
2. Building corrections to CUM house.
REMARKS
-4-
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.
15.0 SLIPWAY
Activities
1. Excavation for the valve house foundation
2. Welding of LPG PIPE
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.
Activities
1. Casting of boundary wall ring beam
2. Masonry work i.e plaster work & block work
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.
Activities
1. Laying cabro at LPG loading area.
2. Leveling
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.
-5-
18.0 MATERIAL PRODUCTION AND DELIVERIES
Materials delivered on site this week
Below is a list of materials delivered to site during the week.
ITEM DESCRIPTION QTY DATE
1. Tiles Ref. delivery invoices 18/04/12 - 27/04/12
20.0 MANPOWER
20.1 Workers on site
Below is a list of manpower on site during the week
Designation Admin. Gate Power
W/ W/
W/ Abltn
Water Fire
Comp. Ldng Bndr Slip
Total
Canteen Brdg Brdg Store pump Water Cum
block bldg hse shop blck shed shed wall way
01 02 shed tank
Site agent 1
Asst. site agent 1
Painters 4 4 4 4 4 4 4 4 4
Electrical - - - - - - - - -
Plumbing - - - - - - - - -
Masons/Tillers 6 6 6 6 6 6 6 6 6
Laborers 10 10 10 10 10 10 10 10 10
Carpenters/ Fitters 3 3 3 3 3 3 3 3 3
Welding 1 1 1 1 1 1 1 1 1
-6-
21.0 INSPECTION AND TESTING
No material presented on site for testing and inspection.
-7-