WEEKLY SITE PROGRESS REPORT NO.

01
Date: 25/04/12

1.0 SITE PROGRESS AND SUMMERY OF WORK DURING THE WEEK.

1.0 ADMINISTRATION BLOCK

Activities
1. Formwork to third floor roof window hoods
2. Masonry work i.e plaster work & block work and demolitions at revised areas.
3. plumbing work
4. Chasing walls for electrical and data conduits.
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.

2.0 MAIN GATE BUILDING

Activities
1. Masonry work i.e plaster work & block work
3. plumbing works
4. Painting
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.

3.0 CANTEEN

Activities
1. Plaster work at wall plate level

-1-
2. Alignment of window openings
3. Cleaning/ sweeping
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.

4.0 POWER HOUSE

Activities
1. Electrical installations
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.

5.0 WEIGHBRIDGE 01

Activities
1. Placing of the floor screed.
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.

6.0 WEGHBRIDGE 02

Activities
1. Placing of the floor screed.
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.

7.0 WORKSHOP

-2-
Activities
1. Painting
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.

8.0 STORE

Activities
1. Painting
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.

9.0 ABLUTION BLOCK

Activities
1. Painting
2. Masonry work i.e plaster work & block work
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.

10.0 FIRE WATER PUMP SHED

Activities
1. Fixing of iron sheets on steel trusses
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.

11.0 COMPRESSOR SHED


-3-
Activities
1. Fixing cladding around the shed
2. Chasing/preparing floor slab for instalations
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.

12.0 LOADING GANTRY

Activities
1. Fixing/welding of pipes inside the shed
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.

13.0 WATER TANK

Activities
1. Welding/fixing tank roof
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.

14.0 CUM

Activities
1. Fixing trusses to the pump shed
2. Building corrections to CUM house.
REMARKS

-4-
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.

15.0 SLIPWAY

Activities
1. Excavation for the valve house foundation
2. Welding of LPG PIPE
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.

16.0 BOUNDARY WALL

Activities
1. Casting of boundary wall ring beam
2. Masonry work i.e plaster work & block work
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.

17.0 TERMINAL PAVEMENT

Activities
1. Laying cabro at LPG loading area.
2. Leveling
REMARKS
Some of the items noted in architects report, i.e revisions have not been effected. Contractor
should attend to them.

-5-
18.0 MATERIAL PRODUCTION AND DELIVERIES
Materials delivered on site this week
Below is a list of materials delivered to site during the week.
ITEM DESCRIPTION QTY DATE
1. Tiles Ref. delivery invoices 18/04/12 - 27/04/12

18.1 Materials outstanding and liable to cause delay.


- Electrical fittings.
- Sanitary fittings
- 4 No. doors for disabled rooms
- 7 No. window glasses

19.0 PROJECT MODIFICATIONS AND SITE INSTRUCTIONS

19.1 Site instructions


- Contractor to remove part of boundary wall ring beam which had been casted without proper batching and without vibrating concrete.
- Floor finish at the canteen open area behind the kitchen to be Terrazzo.

20.0 MANPOWER
20.1 Workers on site
Below is a list of manpower on site during the week
Designation Admin. Gate Power
W/ W/
W/ Abltn
Water Fire
Comp. Ldng Bndr Slip
Total
Canteen Brdg Brdg Store pump Water Cum
block bldg hse shop blck shed shed wall way
01 02 shed tank
Site agent 1
Asst. site agent 1
Painters 4 4 4 4 4 4 4 4 4
Electrical - - - - - - - - -
Plumbing - - - - - - - - -
Masons/Tillers 6 6 6 6 6 6 6 6 6
Laborers 10 10 10 10 10 10 10 10 10
Carpenters/ Fitters 3 3 3 3 3 3 3 3 3
Welding 1 1 1 1 1 1 1 1 1

-6-
21.0 INSPECTION AND TESTING
No material presented on site for testing and inspection.

22.0 SAFETY REPORT:


-No reported incident during this week.

7.0 WORK SCHEDULE


7.1 Slowed / stopped works
-Sanitary and electrical fittings work not started due non delivery.
- Tilling delayed because there were no tiles on site but have now been delivered.
7.2 Special observations
– Work is behind schedule by about 13% mainly due to lack of required materials or late delivery of the same.

-7-