- Structural Plan
a. Design and Structural load computations (duly certified by a Structural/Civil B. DURING CONSTRUCTION
Engineer) subject to review and approval by PETRON CTESG 1. Building Permit. A copy to be posted on a conspicuous place.
b. Details and Specifications 2. Fire Extinguishers. Number required will depend on volume of hazard at site. Minimum of TWO units,
c. Floor Framing Plans 10 lbs. dry chemical (ABC).
d. Structural load computation for mezzanine, if any. 3. Certificate of Final Electrical Inspection (CEI). LESSOR will provide temporary electric power to
e. Foundation Plan LESSEE. A meter and bill deposit will be required from LESSEE.
f. Roof Framing Plan 4. Construction plan approved by PETRON-CTESG. A copy should be available at job site.
GENERAL PROVISIONS
4. LESSOR shall return to LESSEE three (3) sets of APPROVED plans. One copy to be kept at job site.
5. Once plans are approved, LESSEE must obtain the following and submit to the Business A. APPROVALS
Development Executive a copy of the following: 1. LESSEE shall prepare six (6) sets of COMPLETE Construction plans for approval of PETRON-CTESG
and submit thru PETRON-ALLIED BUSINESS GROUP.
1. Permits
- Barangay Permit
- Building Permit Allow 15 days for processing and reviewing of plans. LESSOR’s approval of Design and Working
- Electrical Wiring Permit Drawings is required prior to the commencement of LESSEE’s construction. It is understood that all
- Sanitary / Plumbing Permit comments and notations made by LESSOR on Working Drawings are acceptable, approved and have
- Mechanical Permit to be implemented by the LESSEE.
- Other permits and fees (as necessary)
- List of Construction Workers with ID pictures (Colored 1” x 1”) duly endorsed 2. Addition/changes to approved construction plans. LESSEE must submit revised plans for approval by
by the LESSEE PETRON-CTESG. No work may commence without prior approval.
2. Contractors’ All Risk Insurance
3. Any authorized installation of electrical, air-conditioning, sprinkler, and plumbing works shall be H. IDENTIFICATION SYSTEM
undertaken by licensed reputable Contractors, duly approved by the LESSOR 1. LESSEE’s contractors must submit to Business Development Executive the list of workers with ID
4. LESSOR and/or his authorized representative has the right to inspect construction work any time to pictures (Color 1” x 1”) and position, duly endorsed by LESSEE.
ascertain that work conforms with approved plans. 2. IDs to be surrendered to Business Development Executive upon completion of construction.
Otherwise, LESSOR may ask LESSEE to redo the work if it does not conform to the approved plans or I. UTILITIES AND FACILITIES
LESSOR may do the work at the expense of the LESSEE. 1. Electricity and water consumed during construction shall be charged to LESSEE.
E. INSURANCE
All contractors engaged by the LESSEE shall secure a CONTRACTOR’S ALL RISK INSURANCE
(CARI) from Anchor Insurance Brokerage Corp. based on project’s contract amount (VAT exclusive) and
25% of the project amount to cover damages of Petron Properties within the construction area.
Comprehensive General Liability Insurance (CGLI). Coverage for third party bodily injury and third party
property damage to third parties with a minimum coverage of P500,000.00 each.
Contractor shall submit to the Business Development Executive a copy of the insurance policies
together with the official receipts prior to start of construction. Otherwise, LESSOR will not allow construction
to commence.
STATION IS OPERATIONAL
Supplies and materials shall be delivered directly to LESSEE’s area. Except for bulky and heavy
equipment which require approval from Business Development Executive, no gate pass required.
However, deliveries from 9:00 PM onwards need work permit for delivery approved by Business
Development Executive.
G. CONSTRUCTION HOURS
a. Regular construction hours – 7:00 a.m. to 9:00 p.m.
b. To expedite construction, extension can be requested by LESSEE in writing to Business Development
Executive accordingly. Secure Work Permit with Service Request Form, three days before
implementation of works.