Beruflich Dokumente
Kultur Dokumente
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A Document Verification
Final Disposition Report was reviewed by the Contractor and Schedule "Q",
A1 submitted to Saudi Aramco within two weeks of acceptance of Att. III,
material or equipment. Para. 3.15
All materials, except carbon steels, shall be alloy verified by the 32-SAMSS-011,
A5
Exchanger Manufacturer in accordance with SAES-A-206. Para. 7.1.13
Exchangers have been Code stamped, with nameplates and nameplate 32-SAMSS-011,
A6 mounting brackets located such that they are not covered by insulation, Para. 9.5.5 &
and are easily readable. 9.5.6
The minimum tube sheet and plug sheet thickness shall be 25 mm 32-SAMSS-011,
A9
including any corrosion allowance. Para. 6.1.6.1.6
For exchangers specified in cyclic service, the tube sheet thickness shall 32-SAMSS-011,
A10
be a minimum of 32 mm plus corrosion allowance. Para. 6.1.6.1.6
32-SAMSS-011,
A11 Minimum tube outer diameter is 25.4 mm.
Para. 6.1.11.1
Air cooled heat exchanger has no visible damage to the shell, fans or its Schedule "Q",
B1
appurtenances. Att IV, Para. 5
Each tube bundle have one header free to move with thermal expansion
32-SAMSS-011,
B2 of the tubes and l have teflon sliding plates at the moving end both on
Para. 6.1.1.14
structure and on bundle.
Page 1 of 5
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Receiving Inspection of Air Cooled Heat Exchanger SAIC-E-2005 25-May-05 MECH-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Steel used for slide plates shall be type 316 stainless steel. 32-SAMSS-011,
B3
(NOTE: Carbon steel slide plates shall not be used. ) Para. 7.3.7
Plugs shall be coated with thread lubricant suitable for the design 32-SAMSS-011,
B4
conditions of the exchanger. Para. 6.1.7.10
For exchanger drain connections and other connections, where a
32-SAMSS-011,
B5 process stream is likely to be stagnant, the projection has not exceeded
Para. 6.1.9.23
three times the connection nominal diameter.
Integrally reinforced openings (with no reinforcing pads) shall be provided 32-SAMSS-011,
B6
for all services and design conditions. Para. 6.1.9.24
All nozzles shall be attached to the header by full penetration full fusion 32-SAMSS-011,
B7
welds. Para. 6.1.9.25
The maximum tube length shall be 12,200 mm, unless otherwise 32-SAMSS-011,
B8
approved by the Saudi Aramco Engineer. Para. 6.1.11.2
The fin type shall be as follows:
1) Fins shall be extruded (integral) type for process inlet
temperature of up to and including 290°C.
2) Mechanically embedded fins may be used for a process fluid 32-SAMSS-011,
B9
inlet temperature of up to 400°C. Para. 6.1.11.7
3) Welded fins, carbon steel on carbon steel, may be specified for
a process fluid inlet temperature of up to 450°C.
4) Embedded fins shall be used for cyclic service.
Fins, which are bonded to the outside surface of the tubes by hot-dip 32-SAMSS-011,
B10
galvanizing or brazing, shall not be used. Para. 6.1.11.7
Attachments to fan orifice rings, used for reducing fan tip clearances, are 32-SAMSS-011,
B11
bolted. Para. 6.2.3.17
The clearance between the fan tip and fan ring, the fan ring length and
SAES-E-007,
B12 the shape, are acceptable in conformance with the manufacturer's
Para. 9.1
design drawings.
Actuators for auto-variable pitch fans are provided with maximum pitch
32-SAMSS-011,
B13 stops and the the design blade setting are marked on the hub
Para. 6.2.3.18
nameplate.
Removable fan guards are provided for both the forced and the induced 32-SAMSS-011,
B14
draft exchangers. Para. 6.2.6.1
Belt tensioning adjustment shall be possible without removal of fan 32-SAMSS-011,
B15
guards. Para. 6.2.8.2.14
Automatic belt tensioners shall be provided for fans equipped with 32-SAMSS-011,
B16
plenum hot air re-circulation. Para. 6.2.8.2.15
32-SAMSS-011,
B17 All louver actuators are provided with positioners.
Para. 6.2.8.2.16
32-SAMSS-011,
B18 All control louvers shall be provided with side mounted hand wheels.
Para. 6.2.10.25
All external non-pressure welded attachments shall have their corners 32-SAMSS-011,
B19
rounded to a minimum radius of 50 mm and shall be fully seal welded. Para. 8.1.1.10
A sign: "Caution – Exchanger Has Been Postweld Heat Treated – Do Not
32-SAMSS-011,
B20 Weld", is painted on a postweld heat treated exchanger and located such
Para. 8.2.8
that it is clearly visible from grade.
All Walkways, Platforms, Ladders, Hoops, Handrails, Guards & Stairs, 32-SAMSS-011,
B21
are as per drawings and free from mechanical damage. Para. 6.3.5.
Type Coating applied is suitable for the service condition of the of the SAES-E-007,
C1
equipment per SAES-H-101. Para. 11.3
Page 2 of 5
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Receiving Inspection of Air Cooled Heat Exchanger SAIC-E-2005 25-May-05 MECH-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Apllied coating is free of application deficiencies, mechanical damage or
Schedule Q,
C2 pre-mature failure, ie: signs of corrosion and blistering.
Para. 7.1
(Refer to SAES-H-100)
D Insulation (if furnished by Vendor)
The extent and thickness of external insulation installed meets the SAES-E-007,
D1
thickness requirement stated in the data sheet. Para. 11.1
Insulation installed is acceptable using Inspection Checklist, SAIC-N- Schedule Q,
D2
2010 (for cold insulation) or SAIC-N-2016 (for hot insulation). Para. 7.1
E Fireproofing
F Nozzles
SAES-E-007,
F1 NPS 2½, 3½, and 5 nozzles are not be used.
Para. 8.1.3
SAES-E-007,
F2 All main flow nozzles are flanged.
Para. 8.1.4
Threaded or socket-welded connections are not used in hydrogen, lethal,
wet sour and caustic services.
SAES-E-007,
F3 (NOTE: For other services, smaller than NPS 1½ threaded or socket
Para. 8.1.5
welded connections with 6000-lb rating conforming to ASME B16.11
may be used.)
For services other than hydrogen, lethal, wet sour and caustic, threaded
SAES-E-007,
F4 or socket-welded connections smaller than NPS 1½ are class 6000-lb
Para. 8.1.5
rating conforming to ASME B16.11.
SAES-E-007,
F6 Pressure ratings of flanges are in accordance with ASME B16.5.
Para. 8.2.3
G Gaskets
Spiral wound gasket Type 304 or 316 stainless steel windings with solid
32-SAMSS-011,
G1 Type 304 or 316 stainless steel outer centering rings are used for
Para. 7.3.8 (1)
exchangers with design metal temperatures from -100°C to 0°C.
Spiral wound gasket Type 304 or 316 stainless steel windings with solid
32-SAMSS-011,
G2 carbon steel outer centering rings are used for exchangers with design
Para. 7.3.8 (2)
metal temperatures from 1°C to 425°C.
Type 321 or 347 stainless steel windings with solid Type 304 or 316
32-SAMSS-011,
G3 outer centering rings are used for exchangers with design metal
Para. 7.3.8 (3)
temperatures above 425°:
For exchangers in vacuum service, inner confining ring shall be of the
32-SAMSS-011,
G4 same material as the windings corresponding to the design metal
Para. 7.3.8 (4)
temperature.
Page 3 of 5
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Receiving Inspection of Air Cooled Heat Exchanger SAIC-E-2005 25-May-05 MECH-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
For exchangers in continuous vacuum service, irrespective of design
SAES-E-007,
G5 temperature or design pressure, spiral wound gaskets are specified with
Para. 8.4.2 (3)
solid outer centering rings and inner confining rings.
The Contractor's Handling, Storage & preservation procedure is available Schedule "Q",
H1
and approved. Att IV, Para. 5
Shipping protection was maintained as follows:
1) The internals of exchangers are protected from corrosion by
use of a non-toxic vapor phase corrosion inhibitor such as 32-SAMSS-011,
H2
CORTEC VCI-309 or 307 or equivalent. Para. 10.3.4
2) Alternatively, nitrogen blanketing or temporary coatings as
per MIL-C-16173-D Grade IV (eg. Tectyl 846) was used.
Corrosion inhibitors for use on exchangers with stainless steel and monel
32-SAMSS-011,
H3 tubes are chloride free, suitable for intended use, and do not result in
Para. 10.3.4
crevice corrosion.
Flanged connections and all other machined surfaces have been
32-SAMSS-011,
H4 protected by a suitable coating and fitted with a 3 mm thick steel or wood
Para. 10.3.5
cover, and neoprene gaskets.
The covers have been securely attached by a minimum of four bolts 32-SAMSS-011,
H5
equally spaced. Para. 10.3.5
For ocean shipment, flanged connections are covered with heavy duty 32-SAMSS-011,
H6
plastic bags securely taped to the nozzles. Para. 10.3.5
Lube-oil and seal-oil exchangers are demonstrated to meet the 32-SAMSS-011,
H7
cleanliness requirements of API STD 614. Para. 10.3.6
Exchangers are completely dried and cleaned from all loose scales, weld 32-SAMSS-011,
H8
slags, dirt and debris. Para. 10.3.7.
REMARKS:
REFERENCE DOCUMENTS:
1. SAES-E-007, Design Critiera of Air-Cooled Heat Exchangers, (31 May, 2003)
2. 32-SAMSS-011, Manufacture of Air-Cooled Heat Exchangers, (31 May, 2003)
3. Schedule "Q", Quality Requirements, (November, 2003)
4. SAES-H-100, Painting Requirements for Industrial Facilities, (31 December, 2000)
5. API 614, Lubrication, Shaft-Sealing and Control-Oil Systems, (Fourth Edition, April 1999)
ATTACHMENTS:
1. Attachment 1 - Acceptable Materials for Heat Exchangers
Page 4 of 5
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Receiving Inspection of Air Cooled Heat Exchanger SAIC-E-2005 25-May-05 MECH-
Page 5 of 5