PP Exam Questions

01. Which objects can affect the calculation of capacity requirements for an
operation?
Note: There are 3 correct answers to this question.
a) Standard values (routing)
b) In-house production time (material master)
c) Transport time (routing)
d) Formulas (work center)
e) Operation control key (routing)

02. A user of the SAP ECC system wants a rolling planning time fence (firming type = 1) to
be set up for a material; in other words, new planned orders are firmed within a planning
time fence. When an unforeseen production failure occurs, it can happen that such firmed
planned orders are not being processed because time passes. What solution would
automatically delete firmed planned orders?
Note: Please choose the correct answer.
a) In the material master, an MRP type is used in which the roll-forward mechanism
is activated (Customizing for requirements planning).
b) The demand adjustment activated in the Customizing for demand adjustment is
used.
c) Firmed planned orders can only ever be deleted manually because of the header
data firming.

03. In the Customizing for requirements planning, a project team notices that the
alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type Pd)
The number in each of these alternatives represents a firming type.
What does a firming type define?
Note: There are 2 correct answers to this question.
a) Handling existing procurement proposals outside the planning time fence.
b) Handling existing procurement proposals within a planning time fence.
c) Handling new requirements within the planning time fence.
d) Handling new procurement proposals that need to be created due to new
requirements within the planning time fence.

04. What options does the SAP ECC system offer to retrieve the available capacity for
work centers?
Note: There are 3 correct answers to this question.
a) Attendance list
b) Standard available capacity
c) Shift plan
d) Interval of available capacity
e) Shift sequence

05. Which of the following master data can be used with process orders?
Note: There are 3 correct answers to this question.
a) Serial numbers
b) Master recipes
c) Resources
d) Production/resource tools
e) Production versions

06. Which of the following organizational units does the manufacturing, planning, and
execution process use?
Note: There are 2 correct answers to this question.
a) Storage Location
b) Sales Area
c) Purchase Organization
d) Plant

07. You want to enhance the system statuses of a production order with user
statuses. How do you do this?
Note: Please choose the correct answer.
a) Define the user statuses in the order type-dependent parameters.
b) Define a status profile in Customizing and assign it to the production scheduling
profile.
c) Define a status profile in Customizing and assign it to the order type.
d) Define the user statuses in the Customizing table of the system statuses.

08. You enter a new BOM (Bill of Materials) in SAP ECC but forget to enter a plant
reference. Which of the following statements describes what happens when you try to
save it?
Note: Please choose the correct answer.
a) When saving the BOM, a group BOM is created which can, under certain
conditions, be assigned to a plant later.
b) When saving the BOM, a dialog box appears prompting the user to enter a plant.
c) When saving the BOM, an error message appears stating that it is not possible to
save a BOM without a plant reference.
d) When saving the BOM, a warning message appears. In the corresponding dialog
box, it is possible to create a plant-specific engineering BOM.

09. You want to use the different options for planning in SAP ECC. What is the correct
sequence of the planning procedures?
Note: Please choose the correct answer.
a) Sales and operations planning -> Demand management -> Long-term planning
-> Material requirements planning -> Capacity planning
b) Demand management -> Sales and operations planning -> Capacity planning ->
Long-term planning -> Material requirements planning
c) Material requirements planning -> Demand management -> Sales and operations
planning -> Long-term planning -> Capacity planning
d) Long-term planning -> Sales and operations planning -> Demand management
-> Material requirements planning -> Capacity planning

10. In the SAP ECC system, you interpret the result of a routing schedule. When
scheduling a routing in the SAP ECC system which of the following time
elements are interoperation times?
Note: There are 2 correct answers to this question.
a) Safety time
b) Floats before and after production
c) Processing time
d) Move time

QUESTION: QUESTION: QUESTION:


QUESTION: QUESTION: 05Answer:
01Answer: a, 03Answer: b, 04Answer: b,
02Answer: a b, c, e
d, e d d, e
QUESTION:
QUESTION: QUESTION: QUESTION: QUESTION: 10Answer:
06Answer: a,
07Answer: c 08Answer: a 09Answer: a b, d
d