Project Title:
Location:
Item No. Work
Estimated Quantity: 8.64 Cu.M. Decription: RC COL FTNG ( F-4 )
1. QUANTITY TAKE-OFF
No of Ftngs/Bldg 12 Volume/Bldg, CuM 4.32
Short Side, M 1.20 Total Volume, CuM 8.64
Long Side, M 1.20
Thickness, M 0.25
No of Bldgs 2
2. MATERIALS
REINFORCEMENT DETAILS:
Quantity Unit Unit Price Kgs/Pc No Bars Bar Cut Form No Of Waste /
Ea Side Size Bar Re-Use 6m-Bars 6m-Bar
RM Conc, 20.68Mpa 8.64 CuM 2,700.00 Bars-Short Side 7 16mm 1.20 68.00 0.00
16mm Def Steel Bars 68.00 Ea 325.00 9.47 Bars-Long Side 7 16mm 1.20
GI Wire Ga16 7.00 Kg 50.00 GI Wire Ga16 7.00
1/4 Ord Plywood 4.00 Ea 290.00 1/4 Ord Plywood 4 4.00
2x2 Lumber, coco 92.00 BdFt 12.00 2x2 Lumber Frame 4 92.00
2x3 Lumber, coco 11.00 BdFt 12.00 2x3 Lumber Brace 4 11.00
CW Nails 3.00 Kg 55.00 CW Nails 3.00
3. LABOR
Production No Of
No Of Men Rate / Day SqM/Day Days say
a. Formworks
Carpenters 2 300.00 16.00 1.80 2
Helpers 2 278.00 2
4
b. Re-Bar Works Kgs/Day
Steel Men 5 300.00 320.00 2.01 2
Helpers 5 278.00 2
10
c. Concrete Works CuM/Day
Masons 3 300.00 24.00 0.36 1
Helpers 3 278.00 1
6
4. EQUIPMENTS
Production No Of
No Of Eqpmt Rent / Day Cum/Day Days say
Conc Vibrators 2 500.00 1
Rent / CuM Amount
Pumpcrete 1 200.00 1,728.00