Beruflich Dokumente
Kultur Dokumente
DETAILED ESTIMATES
I. LAY-OUT & EXCAVATION
Materials: Quantity Unit Unit Cost
Assorted Form Lumber 300.00 BF 20.00
Assorted C.W. Nails 5.00 kg 90.00
Nylon Cord 2.00 Rolls 95.00
Labor:
Excavation for Footing 7.68 m3 400.00
Excavation for Wall Footing 5.66 m3 400.00
Excavation for Septic Vault 3.96 m3 400.00
Sub-Total
TOTAL COST P
II. FORMWORKS & SCAFFOLDING
Materials: Quantity Unit Unit Cost
1/2 Org. Plywood 10.00 pc 350.00
2x2x8 Coco Lumber 72.00 BF 20.00
2x2x10 Coco Lumber 100.00 BF 20.00
2x3x10 Coco Lumber 300.00 BF 20.00
4" C.W. Nails 2.00 Box 850.00
3" C.W. Nails 2.00 Box 500.00
2" C.W. Nails 1.00 Box 350.00
1" C.W. Nails 20.00 kg 80.00
Hacksaw Blade 10.00 pc 95.00
TOTAL COST P
III. EMBANKMENT
FILLING MATERIALS: 120.00 m3 200.00
TOTAL COST P
IV. REINFORCED CONCRETE WORKS
FOOTING/COLUMN: Quantity Unit Unit Cost
10 mm ø Def. Bar 15.00 pc 140.00
12 mm ø Def. Bar 68.00 pc 280.00
BEAMS:
10 mm ø Def. Bar 108.00 pc 140.00
12 mm ø Def. Bar 48.00 pc 280.00
16 mm ø Def. Bar 15.00 pc 400.00
ACCESSORIES:
#16 G.I. Wire 2.00 Rolls 1,350.00
Hacksaw Blade 10.00 pc 90.00
FLOOR SLAB:
10 mm ø Def. Bar 200.00 pc 140.00
Materials:
Portland Cement 140.00 Bags 230.00
Washed Sand 11.00 m3 600.00
Washed Gravel 11.00 m3 800.00
TOTAL COST P
V. MASONRY WORKS
Materials:
4" Conc. Hollow Block 2,234.00 pcs 14.00
Portland Cement 195.00 bags 230.00
Washed Sand 19.00 m3 600.00
#16 G.I. Tie Wire 12.00 kg 85.00
10 mm ø Def. Bar 197.00 pcs. 140.00
Hacksaw Blade 4.00 pcs 95.00
TOTAL COST P
Prepared by:
RICARDO S. SAPONG
Civil Engineer
Cost
6,000.00
450.00
190.00
3,072.00
2,264.00
1,584.00
6,920.00
13,560.00
Cost
3,500.00
1,440.00
2,000.00
6,000.00
1,700.00
1,000.00
350.00
1,600.00
950.00
18,540.00
24,000.00
24,000.00
Cost
2,100.00
19,040.00
15,120.00
13,440.00
6,000.00
2,700.00
900.00
28,000.00
32,200.00
6,600.00
8,800.00
134,900.00
31,276.00
44,850.00
11,400.00
1,020.00
27,580.00
380.00
116,506.00
Cost
1,400.00
7,000.00
1,400.00
9,800.00
5,000.00
12,500.00
2,500.00
20,000.00
16,200.00
10,800.00
9,900.00
5,000.00
3,000.00
6,000.00
50,900.00
9,120.00
14,000.00
950.00
1,710.00
4,590.00
30,370.00
16,610.00
8,560.00
2,010.00
790.00
420.00
100.00
28,490.00
139,560.00
Cost
17,550.00
2,520.00
40,500.00
3,000.00
1,800.00
750.00
2,000.00
38,664.00
13,800.00
120,584.00
Cost
33,040.00
2,142.00
4,480.00
864.00
2,300.00
1,400.00
4,500.00
760.00
49,486.00
Cost
1,100.00
11,900.00
13,800.00
3,600.00
4,020.00
5,200.00
1,470.00
1,100.00
1,100.00
2,720.00
560.00
960.00
1,440.00
1,280.00
1,280.00
750.00
720.00
1,200.00
300.00
54,500.00
Project Title: Construction of Engr.Gilliane B. Sapong Residential Building
Project Location: Ramona Subdivision, Napolan, Pagadian City
Owner: Gilliane B. Sapong
SUMMARY OF ESTIMATES
TOTAL 671,636.00
30% Labor 201,490.80
Prepared by:
RICARDO S. SAPONG
Civil Engineer
Project Title: Construction of Engr.Gilliane B. Sapong Residential Building
Project Location: Ramona Subdivision, Napolan, Pagadian City
Owner: Gilliane B. Sapong
TOTAL 36,822.00
30% Labor 11,046.60
RICARDO S. SAPONG
Civil Engineer
Project Title: Construction of Engr.Gilliane B. Sapong Residential Building
Project Location: Ramona Subdivision, Napolan, Pagadian City
Owner: Gilliane B. Sapong
TOTAL
30% Labor
TOTAL COST P
Prepared by:
RICARDO S. SAPONG
Civil Engineer
7,900.00
700.00
360.00
240.00
285.00
250.00
1,760.00
240.00
1,200.00
510.00
190.00
250.00
200.00
7,200.00
4,200.00
925.00
675.00
450.00
540.00
960.00
400.00
360.00
400.00
30,195.00
9,058.50
39,253.50