Sie sind auf Seite 1von 15

Table of contents

Sl.no Descriptions Page No


1. GENERAL 3
2 SCOPE OF WORK 3
3 SITE ESTABLISHMENT PROPOSED 3
4 CONSTRUTION WATER SUPPLY 3
5 ELECTRIC SUPPLY 3
6 INITIAL SURVEY 4
7 CONSTRUTION PROGRAM 4
8 TEMPORARY ACCES ROAD 4
9 CONSTRUTION METHDOLOGY 5
10 SAFETY 10
1. General-

This document describes the construction methodology for construction of the main components of the
project. The construction methodology for each type of activity has been described under the relevant
sub sections of this chapter. The type and sizes of the Equipment to be used have also been indicated
while describing the Construction methodology.
Anicut will be constructed in two stages. In first stage work include Right bank side Non gated structure
97m + gated structure 42 m. After completion of first stage RCC work for Right bank, second stage
work for left bank side Non gated structure of 63 m will be carried out.

2. Scope of work

Scope work includes concrete barrage having up stream floor level at 215.00 level and top of concrete
structure 223.900 level. Length of constructed barrage at top would be 203 Mtr. Length with top
elevation 223.900 level.

Main Structure Components of work

Aniucut (Barrage)-

1) Gated elevation of Middle area- 42 Mtr length.


2) Non Gated plan Left & Right side - 161 Mtr. Length.
3) U/S side & D/S side apron
4) Right & left side bank Abutment & wing wall ,slope Protection work.

Height of barrage- 8.900 Mtr.

3. Site Establishment proposed-

 Office for contractor & employer employees.


 Contractor store, laboratory, QA/QC office, OHSE office etc.
 Staff Quarters & Labor colony
 Concrete Batching Plant yard- Cum/hr.
 Reinforcement yard
 Precast Yard
 Material stacking yard
 Equipment parking area
 Car parking area & security office.

2 OF 16
CONSTRUCTION METHODOLOGY
4. Construction water supply

The water for the project will be sourced from river, which will be stored in a surface water tank of
suitable capacities. The pumps of required capacity will be installed for pumping of water from surface
tank to overhead storage tanks at batching plant, office area. Under ground water pipelines will be laid
for distribution of water.

5. Electric supply

Construction power will be drawn from the Grid power/ generating sets. Within central installation area
suitable capacity & number of DG sets will be installed as standby for batching plant, fabrication yard,
site lighting, office, workshop & camp.

6. Initial survey

Initial survey shall be carried out dam alignment & if required bathymetric survey will be carried out
for river bed levels.

 Transfer GTS value at every structure location on reference pillars.


 Transfer centreline of the proposed alignment of structure on reference pillars.
 Establish transverse lines for every expansion joint & wherever immediately possible on
reference pillars.
 Take confirmatory longitudinal cross section for every 20 m along centreline of the proposed
alignment along with water level
 Get all reference pillars with their values painted and certified from the client / supervising
consultant.
 Take existing bed levels at every non gated & gated structure.
 Details collected shall be submitted for approval.

7. Construction Program
The construction program has been prepared considering Yearly monsoon cycle & Project
Milestones to be achieved with in stipulated time frame, available infrastructure and prevailing
conditions and interfacing required for other agencies with following work breakdown structure for
complete scope of works.
The program has been prepared considering 12 hours working, 6 days’ week and public holidays as
off. Monsoon period has been considered in the month of June -September as per prevailing local
conditions with 80% productivity. Unforeseen and natural calamities have not been considered.

8. Temporary access road

3 OF 16
CONSTRUCTION METHODOLOGY
Temporary access road for site office & up to Right bank of Barrage construction site shall be provided
by contractor.

9. Construction Methodology

This chapter deals with method adopting during execution of work and equipment used for for each
stage such as excavation RCC work & fabrication work. Detailed segmental methodology will be
submitted for each section before commencement of work.

 River diversion-

Before Execution work start River diversion work will taken for provide safe & dry construction area
for construction of RCC structure. River diversion will be taken up in two phase as defined in
construction methodology. Phase I -Soil bund prepared with End on soil dumping upstream side of
right bank non gated structure 97 m right side + gated structure of 42 m i. e. total 139 m length of
anicut. Channel will be provided for flow of water. After completion of upstream side river diversion
if required downstream side soil bund will be constructed to provide dry land for excavation and
foundation work of Anicut rcc structure. After completion of Phase I RCC work soil bund for Right
bank side removed and constructed let bank side for balance are of Non gated structure construction.
When All RCC structure work completed the soil bund removed from U/S.

 Excavation for Barrage foundation-

Engineer in charge will be informed before commencement of excavation activity, the grounds are
disturbed , and existing levels will be measured for the purpose of records. After initial survey work
foundation layout marked on river bed level and excavation will be carried with excavators up to
required level as specified in drawing. Excavation for non gated right side & gated structure would be
initiated after construction of 1st stage dyke or soil bund and subsequent diversion of river through left
side. The excavation area or foundation will demarked on ground (river bed) with help of surveyor.
Foundation area shall be excavated up to levelling course bottom level with the help of hydraulic
excavator. Excavated soil will be shifted by dumpers as per direction of engineer’s in charge.
If the excavation strata will occurs rocky strata rock breaker or jack hammers will be used for levelling
of bed surface.
The equipment deployed for river bed excavation Hydraulic excavators with rock breaker, 20 T rear
dumpers, Jack hammers etc.
Second stage of excavation will start after completion of first stage RCC work for gated & non gated
structure.
If their seepage of ground water is more, dewatering shall be required during excavation of foundation
and RCC raft construction. The sump will be constructed outside foundation limit and dewatering
pumps shall be installed. Seepage & other water collected in sumps will be discharged D/S side of river.

4 OF 16
CONSTRUCTION METHODOLOGY
 Drilling & Grouting -
The grouting shall be done for improvement of the water-tightness of foundation for a concrete dam.
Grouting material mainly consists of cement, water, admixture, additive (in case), etc., and it shall be
in accordance with the related quality standard of materials of each present batch of cement, admixture,
admixture, etc., and enclose the quality certificate of the factory.
The grouting test shall be conducted in accordance with the approved grouting segmental construction
procedures and methods in the grouting experiment area, and master the features of rock grouting in
the project area, and inspect the validity of grouting measures. Furthermore, categorize and analyze the
experiment data of per unit water absorption rate and cement consumption amount of each drill-hole
and inspection hole, so as to obtain the reasonable grouting procedure, the good grouting technique and
the high effective grouting parameter.
After laying of leveling course and setting of concrete grouting will be activity will take up.
Rock drilling will be carried out with percussion drilling method by sufficient capacity of drifters. The
Pattern of drilling, location, depth, diameter, direction and so on of the grouting hole shall be drilled
with the requirement of the construction drawing.
Drilled whole shall be washed with water to remove material deposited on the surface during the
drilling operation and to provoke deliberate interconnection between adjoining grout holes to remove
known seams and layer of erodible material.

For routine grouting operation, and simple water test conducted before & after grouting. Water
percolation test shall be carried out to measure the effectiveness of the grouting treatment. The test may
be simple or cyclic. Cyclic testing shall be done for evaluation grouting mixture, and during grouting
operation simple test shall be carried out.
Water tests should be carried out in primary stages before injection to amplify information available
from the site investigation. Tests should be carried out in secondary stages before injection to indicate
the results of primary injections. Test may be carried out in individual test holes at any time to indicate
the results of all treatment carried out before that time. Test holes drilled for this purpose should be
sited midway between completed injection holes.
Jetting operation are carried out in order to deliberately provoke connection between bore holes and to
remove known deposits of erodable material. Jetting should be carried out in group of holes arranged
in a square, triangular or hexagonal pattern known as cells.

For effective treatment of the surface zones, sufficient pressure should be developed to achieve the
spread required with a convenient spacing of holes. Adequate cover should be maintained during
grouting to ensure that adequate pressure is applied without causing upheaval or excessive surface
leakage.
As for the method of injection, grout holes should be injected by direct connection to the pump. Each
pump should be provided with a packer at the surface or with a short strand pipe threaded at its outer
end to accept stand or control fittings, which should be provided with a pressure gauge, bleeder valve
and a valve enabling delivery from pump to be cut-off from the hole. Either single line or circulation
system may be used, usually circulating system is preferred, however when adequate controls are
possible to regulate the pump discharge and pressure by using pumps of suitable design, single line
grouting system can be used. Once the grouting of stage or group of holes has been commenced it

5 OF 16
CONSTRUCTION METHODOLOGY
should be continued without interruption up to completion. In general a stage may be considered
complete when the absorption of grout at the desired limiting pressure is less than 2 l/min averaged
over a period of 10 minutes. As far as practical a continuous flow of grout should be maintained at the
desired pressure and the grouting equipment should be operated to ensure continuous and efficient
performance throughout the grouting operation. After grouting is completed, the grout holes should be
closed by the means of a valve to maintain to grout pressure for a sufficient period to prevent escape of
the grout due to back pressure and flow reversal, due to causes like artesian conditions. For this purpose
a period of one or two hours is generally sufficient, however this should be verified by trial.
The grouting should be conducted in accordance with the principle of the sequence and the density.
The different rows of the grouting holes and the different holes of the same row can be divided into
two sequences construction, and also can be sequenced only by row but not hole or otherwise the
opposite.
The grouting pressure should be adequate to achieve the desired grout and the pressure should be
limited so as to avoid disturbances and upheaval of the ground and should take into account reservoir
pressure. For structures on rock foundations, it is a basic requirement that no disturbance should be
caused to the surface zones of the foundation by the grouting operation.. The most common difficulty
experienced in consolidation grouting is surface leakage. It is therefore customary to pipe through the
entire height of concrete or masonry and carry out the grouting after the rock has been completely
covered. This not only eliminates surface leakage but permits use of higher pressure so that even the
smaller seams can be grouted effectively.

Equipment deployed for grouting are Drifter, grouting mixer & pump, water tank etc.

 Levelling Course-

After completion of excavation and compaction of loose material leveling course will be laid manually.
The concrete will be supplied by transit mixers /dumpers from batching plat. Leveling course will be
compacted & levelled welly.

 Anchor of Bars-
As shown in Drawing 25 mm dia tor steel bar will be anchored at bottom of footing at spacing 1500
mm C/C. Anchor bars provided along the area of footing for non gated & gated structure as shown in
drawing.
The application anchor bars as follows
 Drill hole in leveling course with correct diameter & depth as shown in drawing & specification.
 Clean the drilled hole with wire brush & and remove dust using a manual air blower.
 Inject the grouting material in drilled hole from the base of drilled hole while pulling upwards
as hole fill until 1/3 to ½ of the Volume.
 Insert Rebar slowly with rotating motion until resin is overflowed on the surface.
 Remove the excess grout material from surface.

6 OF 16
CONSTRUCTION METHODOLOGY
 RCC Structure work for Non Gated & Gated structure-

 General
This section deals with material, methods and equipment used for manufacturing, transporting, placing
and curing of normal and plum concrete.
 Raw Material Procurement
Sources of all raw materials required to be procured shall be inspected and approved by engineer in
charge prior to procurement. Materials shall be procured only from approved sources. All materials
shall be inspected/tested in accordance with approved inspection and test plan in line with relevant
standards & code with specific reference to MORHT specification.

 Reinforcement Work-
Reinforcement steel shall be cold bend without use of heat to required shape as per the applicable
specification. The bar bending schedules will be prepared and got it approved before cutting the steel.
The bars ready for use will be properly tagged for clear and easy identification.
Reinforcement will be transported through trailer/Truck from reinforcement yard to site. Reinforcement
shall be accurately placed / fixed by approved means to maintain correct position as shown in drawings.
Cover blocks, spacers and chairs will be provided as per specification to prevent displacement during
concreting.
 Form work-
Form work of steel form panels, backed by whalers and soldiers with standard fittings are deployed or
the RCC work of structures.
 Concrete Production & Transportation ,Placement-
Batching plant of 30 m3 / hr. capacity will be installed at Site to fulfill concrete requirement for normal
concrete. If required temperature control of concrete below 19 degree Celsius ice will be added while
production time. Considering peak quantity for pour of cum the detailing has been worked-out as
below:

Concrete Production:

 Largest pour size of 200 m3 to be cast in 10 hours.(


 Hourly Concrete requirement = 200/10 = 20 m3/ hr.

7 OF 16
CONSTRUCTION METHODOLOGY
 Proposed Batching Plants = 1 No of 30 m3 / hr.
 Installed capacity for production of normal concrete =30 m3 / hr.
 Considering efficiency of 80%, net capacity = 24 m3 / hr.
 24 Cum > 20 Cum hence sufficient capacity of batching plant available.

Concrete shall be transported to Site in transit mixers from the batching plant. Requisite number of
transit mixers of 6 m3capacity shall be deployed for the transportation of concrete. Transit mixers shall
be properly insulated to ensure proper control on temperature.
In general, concrete will be placed at raft level using Pumps through fixed pipe lines / Placer Booms
attached to it. However, as structure height increase during construction stage, concreting will be done
with crane & Crane Bucket.
For placing of concrete 1 nos. pump of 45 m3 / hr. Mobile crane 75/40 T capacity with Crane Buckets
of capacities will be of 1 m3 and 2m3 will be deployed.

 Execution of work.
The construction work execute in 2 phase as described below.
Phase -I
Gated structure & Non gated structure right bank side with abutment & wig wall with slope protection
work
Construction of gated structure with 15 bays of spillway, sluice gate taken up in first stage of RCC
work, simultaneously non gated right bank side RCC structure work will be taken up. RCC structure
work followed by completion of base grouting.
Phase II
Non Gated structure-(Left bank side) with abutment & wing wall Left bank side & slope protection
work.
 Non gated structure-
The non gated structure will be constructed in one stretch between two constructions joint & vertically
in stage wise work progress as width of structure reduced.
The non-gated structure is two parts one is outer shell RCC concrete & inner core is of M15 Plum
Concrete. The bottom raft consist of 500 thickness RCC raft. The height of non gated structure will
reduces towards bank side from approx. 8. 5 m to 2.5 m. At top of structure there is service road from
right bank to let bank.
The vertical structure are of 500 mm thickness RCC shell & inner core filled with M15 plum concrete.
At every approx. 1.2 meter there width will be reduces as shown in drawing.

8 OF 16
CONSTRUCTION METHODOLOGY
 Raft Foundation-
Layout of raft will be given on leveling course for size , pre-cut/bent reinforcement will be will be
shifted from central reinforcement yard. It will be tied as per approved drawing. Chair & cover blocks
are provided as per requirement. Side forms will be fixed to line & levels as required, side supports &
internal spacers/tie members against each other will support side forms. Clearances will be obtained
from clients and rat footing will be take up for concreting.
Concrete will be placed through pumps and compacted with vibrtators. Exposed top surface will be
levelled & key joint left for next stage of concrete. After gaining strength of concrete in 1 days forms
will be removed.

 Shell RCC wall work & Inner core Plum concrete.


After completion of Raft concreting inner core plum concrete will be carried out. Steel shuttering placed
in line & position for plum concrete. While plum concreting placing first layer M15 Concrete will be
placed with help of crane & bucket. After completion of layer immediately place layer of stones will
be placed and subsequently M15 concrete layer will be placed and compacted. Thus cycle repeated till
the completion of work up to top of plum concrete structure. The height of stage construction shall be
taken average of 1200 mm.
Against dowel left through raft, balance reinforcement will be tied for a lift to be corrected. Vertical
rod to be provided with required overlaps. Horizontals will be tied in position. Structural channels &
Insert plates are placed in the position. Outer side forms placed in line & position required. side supports
& internal spacers/tie members against each other will support side forms. After obtaining clearances
1st stage of shell RCC wall concreted.
Final lift for RCC shell wall & inner core completion Top RCC shell concrete taken up & finished
properly.
At structure bottom Concrete opening of 500 mm x 500 mm shall be provided as per location shown in
drawing for sluice gates. The opening will be provided throughout the structure as shown in drawing.
For the above work sacrificial from work will be used. Before placing of concrete form work will
placed in position & supported to raft by bolt drilling.
 Gated Structure-
Gated structure consist of 20 nos. gate with 10 nos. spillways. The spillways are supported by Main
piers 11 nos. & dummy piers of 10 nos. 10 nos. 10 nos. of sluice gates are provided in non gated &
gated structure of barrage.

9 OF 16
CONSTRUCTION METHODOLOGY
 Raft Foundation-
After completion of anchor bar work layout of raft will be given on leveling course for size , pre-
cut/bent reinforcement will be will be shifted from central reinforcement yard. It will be tied as per
approved drawing. Chair & cover blocks are provided as per requirement. Structural channels & Insert
plates are placed in the position & welded/tied with steel for stability. Side forms will be fixed to line
& levels as required, side supports & internal spacers/tie members against each other will support side
forms. Clearances will be obtained from clients and raft footing will be take up for concreting.
Concrete will be placed through pumps and compacted with vibrtators. Exposed top surface will be
levelled & key joint left for next stage of concrete. After gaining strength of concrete in 1 days forms
will be removed.

 Pier & Ogee support for gate


After completion of Raft concreting inner core plum concrete will be carried out. Steel shuttering placed
in line & position for plum concrete. While plum concreting placing first layer M15 Concrete will be
placed with help of crane & bucket. After completion of concrete layer immediately layer of stones
will be placed and subsequently M15 concrete layer will be placed and compacted. Thus cycle repeated
till the completion of work up to top of structure. The height of stage construction shall be taken average
of 1200 mm.
Dowels from Raft will be drawn and reinforcement for pier & ogee structure walls will be tied. Inner
& outer side forms erected, aligned and fixed in position as against already tied reinforcement. The
forms will be side supported with the help of struts taking reaction from already concreted raft slab.
The line and level will be achieved as per approved drawings and then cleared the pour for concreting.
After obtaining clearances 1st stage of rcc concrete completed. After gaining strength of concrete, steel
forms are dismantled. The above procedure repeated till the structure reach top of structure.
Ogee structure’s as concreting of shell wall structure and inner core M15 Plum concrete completed, top
RCC surface concreting will be carried out by steel form work. Surface structure reinforcement laid as
per drawing & specification. Side shuttering form will be placed in line & position. The clearance
obtained for shuttering & steel work completed, the concrete will take up.
The concrete placed at location with crane & crane bucket. Concrete placing progress from bottom of
ogee to top level of ogee. The top surface of ogee RCC structure finished will trowel by skilled mason.
Walk way slab work will be taken up after completion of pier structure work. Walk way slab staging
form will be erected by taking support from ogee top surface slab, after erection of staging deck will
be placed and leveled properly. Reinforcement will be placed and tied properly as per shown in
approved drawings. Obtaining clearance from client’s concrete will be placed and levelled properly.
Gard stone will be casted as per location shown in approved drawing.

10 OF 16
CONSTRUCTION METHODOLOGY
 U/S Apron & D/S Apron
RCC structure of gated & Non gated as soon as completed, excavation for U/S & D/S apron will be
taken up with CK 90 excavator. Excavation shall be carried up to levelling course bottom level &
compacted thoroughly. Levelling course of 100 mm thickness will be laid manually & leveled by
masons with trowels.
Cut-off wall area will be excavated after levelling course completion for U/S side apron
U/S side apron steel reinforcement will be laid as per drawing & specified. Chair & Cover blocks
provided as per requirement. Shuttering will be placed in position & in level. Clearances will be
obtained from clients and RCC apron will be take up for concreting.
D/S Apron layer of 550 mm thickness of M15 grade layed manually on leveling course. Line & levels
are checked from engineer in charge before & after concreting. As M15 layer of concreting completed
& concrete gain in strength, reinforcement will be laid as per drawing & specification.
Chair & Cover blocks provided as per requirement. Shuttering will be placed in position & in level.
Clearances will be obtained from clients and RCC apron will be take up for concreting.
Levels before & after concreting will be checked from engineers In charge.

 Abutment & wing wall-


Abutment wall & Wing wall work will execute simultaneously.
Excavation of footing area will marked at ground level. Excavation will be carried out with the help of
CK 90 excavator. The excavated material will be disposed at location as per engineers in charge
direction by 20 T dumpers.
Levelling core will be layed and leveled manually by trowel. Concrete will be supplied by transit mixer
& placed location with direct dumping from transit mixer by chute arrangement.
Layout for raft foundation will be given on leveling course for size, pre-cut/bent reinforcement will be
shifted from central reinforcement yard. It will be tied as per approved drawing/schedule. Cement
mortar cover blocks will be fixed at sides. Reinforcement chairs will be provided to support top
reinforcement mesh. Side forms will be fixed to line & level as required. Side supports & internal
spacer/tie members against each other will support side forms.
The reinforcement and formwork will be offered for inspection/checking of the client/supervising
consultant. On getting clearance dowels wall will be tied in position.
Formwork form will be fixed in position. Clearance will be obtained from the client/supervising
consultant and the footing will be taken up for concreting. After completion of concrete placing and
gaining strength of concrete, steel form will be removed without damage to concrete.
Inner core Plum concrete will be placed with crane & crane bucket up to RCC shell work 1st stage level.
After completion of Plum concrete outer shell RCC work taken up.

11 OF 16
CONSTRUCTION METHODOLOGY
This sequence of steel reinforcement, form placing & concreting ,plum concreting will be repeated until
the structure work will reach at final top level.

 Slope Protection
After completion of Concrete work for Abutment & wing wall. The soil backfilled up to required level
and slope maintained as per drawing. After completion soil dressing, soil surface compacted properly.
Concrete planks are precast in precast yard and after proper curing will be shifted to site installation
location by trailer & crane. The planks are placed from bottom side to top of the slope. Line & levels
are properly maintained while placing of concrete planks. After completion of precast plank up to
224.100 level, stone pitching will be carried out for slope protection. The stone are transported up to
pitching location by dumper & placed at position with crane & crane bucket. Stones are placed in line
& levels by manually. The stone pitching shll be carried out up to HFL level i.e. 232.00.

 PVC Water stopper-


PVC Water stopper are used to prevent the water leakage from construction joint. Embedded in
concrete, PVC water stop span the joint to form a continues, water tight diaphragm that prevents the
passage of liquid through joint.
PVC water stops are installed prior to concrete placement to ensure proper positioning and concrete
consolidation around the water stopper. The location & embedment of the water stopper should be
determined by the use of the construction drawings of the project.
PVC Water stopper are placed as per shown in approved drawing for Horizontal & vertical construction
joint.
Application Steps
 Place water stops at appropriate position. Make sure that about a half width of it is embedded
in the concrete.
 Contain about 1.5 times of clear coverage between the waterstop and surround reinforcing steel
without any rock pockets and air voids.
 Tie the waterstop to surrounding reinforcing steels by threading steel wire to metal eyelets,
punched holes or hot rings of waterstops to fix the waterstop firmly. Meanwhile, make sure
there is no displacement during fastening.
 Pour the concrete and vibrate concrete nearby the joints (especially those under the waterstop)
to enhance the contact with waterstops.
 Clean debris and dirt of concrete surface after first pour.
 Repeat the above methods for a second pour.
 Water stopper can be join on site with simple electrical heater blade.

12 OF 16
CONSTRUCTION METHODOLOGY
 Fabrication & Erection of structural steel -
In this scope work includes fabricating & erection of MS gate shutter & sluice gates.
MS gate shutter – Size 1.2 M x 1.075 M -20 nos.
Sluice Gates size – Size 1.15 M X 0.9 M – 10 nos.
 MS gate shutter, Sluice gate & Embedded Parts (EPs)-
All these MS gate shutter, sluice gate & EPs shall be made out of material specified in the drawings.
The material shall be drawn and shifted to the Fabrication Shop on platform for marking the dimensions
of that particular fabricated structure. For Structures larger in size, layout shall be marked on platform
and shall be checked by client Engineer. The dimensions will be cross-checked before cutting the
material to the required size. Tack welding will be done to assemble the members. Before starting the
welding process, the measurements shall be re-checked with reference to drawing and welding shall be
done as per welding procedure. During welding, safety precautions shall be taken. After completion of
welding, the fabricated structure shall be cleaned and weighing will be done jointly. Painting shall be
done as specified in the drawing. The fabricated structure shall be stacked properly to avoid damage of
paint.

 Erection of Structure
The scope in this chapter describes erection of embedded parts, Sluice gates & MS gate shutter.
The erection of steel structure shall be carried out as per drawing and sequence discussed and approved
with engineer in charge.
Required fabricated structure & EPs cleared by the Inspector, shall be transported to Site in trucks
loaded manually or by crane. Necessary precautions will be taken to avoid damage during loading and
unloading.
Structural steel frames of sluice gate & MS gate shutter shall be erected plumb and true to tolerance.
All steel frames & Gates shall be checked for plum & Level individually before and after connections
made. Temporary bracing shall be introduced wherever necessary.
A temporary Jig made out of reinforcement bars / structural steel shall be made at the exact location of
EP, taking consideration of size of EP, weight and shape. The Jig shall be such that after lowering EP,
jig should remain in its true position as required. If any difference found, EP will be realigned by giving
proper packing. Wherever necessary the shuttering shall be lowered or punctured for penetration of EP.

Embedded parts consists of inserts, opening frames, with lugs and anchors to be embedded
monolithically in concrete structure. The embedded parts shall be provided and kept in position until
concrete is set completely. Embedded parts shall be accurately placed in position as per drawings. In

13 OF 16
CONSTRUCTION METHODOLOGY
case partial embedment, the length projecting from concrete shall be protected from damage and build
up of rust. Vibrator shall not in contact with embedded parts while placing concrete.

 Painting

Before commencement of painting works surf, mills, rust, rust scale and foreign material shall be
removed to ensure and clean and dry surface is obtained, type of surface treatment shall be decided in
consultation with Engineer Incharge. First coat of primer will be applied within 4 hours of surface
cleaning. Each coat of material shall be applied to form continuous and uniform thickness. Paint
manufacturer’s instructions shall be followed for preparation of paint. Painting shall be carried-out by
spraying. Brushes may be used sparingly at certain location only. For undercoat Epoxy polyamide
micaceous Iron Oxide (MIO) shall be used and synthetic enamel paint will be used for finishing coat.

10. SAFETY

 Drinking Water facilities will be provided on site.


 First Aid Box will be provided nearby working area.
 Vehicles Check List Will Be Maintained.
 Proper Barricading & Safety Sign Board will be placed at site.
 All PPE Equipment will be provided to Workers & Staff.
 Proper earthing & Electrical will be provided in Main Panel& Distribution Electrical Panel
 HIRA & OCP is prepared for each activity.
 Emergency Vehicle will be available round the Clock at site.
 Safe access will be provided for assembly in case of emergency
 Necessary training will be provided persons working on height, before commencement of erection
works.
 All equipment used at site will be tested and certified before use.
 Warning signage and safety precautions will be displayed at all working locations.
 Regular safety briefing will be carried out.
 Workers will undergo Basic Safety Training for land-based construction work
 Job specific safety training and regular refresher training shall be provided to workers to
enhance/maintain their safety awareness of potential hazards associated with work over water/near
water/on vessels, including those during inclement weather.
 Lifting appliances on vessels shall be fixed and securely anchored.
 Suitable personal protective equipment, such as safety helmets, safety belts/safety harnesses and
lifejackets shall be provided.

14 OF 16
CONSTRUCTION METHODOLOGY
 Guard-rails and toe-boards should be installed at edges where persons are liable to fall from height or
into water
 First aid facilities including a stretcher and a portable resuscitation equipment shall be provided and
kept readily accessible for emergency use.

Attachment

 Construction Program for Anicut


 Equipment List

15 OF 16
CONSTRUCTION METHODOLOGY

Das könnte Ihnen auch gefallen