Gantt Chart
Excel does not offer Gantt as chart type, but it's easy to create a Gantt chart by customizing the stacked bar chart
Chapter
type. Below you can find our Gantt chart data.
Charts
Column Chart
Line Chart
Pie Chart
Bar Chart
Area Chart
Scatter Chart
Data Series
Axes
Chart Sheet
Trendline
Error Bars
1 of 12 08-11 06:40 PM
Gantt Chart in Excel - Easy Excel Tutorial http://www.excel-easy.com/examples/gantt-chart.html
Sparklines
Combination Chart
Gauge Chart
Thermometer Chart
Gantt Chart
Pareto Chart
2 of 12 08-11 06:40 PM
Gantt Chart in Excel - Easy Excel Tutorial http://www.excel-easy.com/examples/gantt-chart.html
3 of 12 08-11 06:40 PM
Gantt Chart in Excel - Easy Excel Tutorial http://www.excel-easy.com/examples/gantt-chart.html
3. Click Add and add the two Series (Start Date and Duration).
4. Click Edit under Horizontal (Category) Axis Labels and select the range A4:A11.
4 of 12 08-11 06:40 PM
Gantt Chart in Excel - Easy Excel Tutorial http://www.excel-easy.com/examples/gantt-chart.html
5. Click OK.
5 of 12 08-11 06:40 PM
Gantt Chart in Excel - Easy Excel Tutorial http://www.excel-easy.com/examples/gantt-chart.html
7. The tasks (Foundation, Walls, etc.) are in reverse order. Right click the tasks on the chart, click Format Axis
and check 'Categories in reverse order'.
6 of 12 08-11 06:40 PM
Gantt Chart in Excel - Easy Excel Tutorial http://www.excel-easy.com/examples/gantt-chart.html
8. Click Close.
7 of 12 08-11 06:40 PM
Gantt Chart in Excel - Easy Excel Tutorial http://www.excel-easy.com/examples/gantt-chart.html
9. Right click the red bars, click Format Data Series, Fill, No fill.
8 of 12 08-11 06:40 PM
Gantt Chart in Excel - Easy Excel Tutorial http://www.excel-easy.com/examples/gantt-chart.html
Dates and times are stored as numbers in Excel and count the number of days since January 0, 1900. 1-jun-2012
is the same as 41061. 13-jul-2012 is the same as 41103.
11. Right click the dates on the chart, click Format Axis and set the Minimum to 41061, Maximum to 41103 +
duration last task = 41103 + 2 = 41105 and Major unit to 7.
9 of 12 08-11 06:40 PM
Gantt Chart in Excel - Easy Excel Tutorial http://www.excel-easy.com/examples/gantt-chart.html
10 of 12 08-11 06:40 PM
Gantt Chart in Excel - Easy Excel Tutorial http://www.excel-easy.com/examples/gantt-chart.html
Note that the plumbing and electrical work can be executed simultaneously.
View Forms
Upload Resume@Naukri.com
Best SIP Investment Plans
Submit Resume Now
Class 1 to Class 12
Example Gantt Charts
Start Download
Be Certified in Big Data
75% Off Hotels In Goa
11 of 12 08-11 06:40 PM
Gantt Chart in Excel - Easy Excel Tutorial http://www.excel-easy.com/examples/gantt-chart.html
12 of 12 08-11 06:40 PM