Sie sind auf Seite 1von 6

Feature Report

Aging Relief Systems —


Are they Working Properly?
Common problems, Symptoms
Inadvertent Relief lines
relief-valve and/or headers
cures and tips blocking vibrations

to make sure your Equipment


and/or piping
Relief valve
chattering
Other
symptoms
failure
pressure relief valves
Problems
operate properly Unprotected equipment Relief system
when needed or piping during
overpressure scenarios
components malfunction

Level 1
Sebastiano Giardinella causes
Inelectra S.A.C.A.
Improperly

R
Lack of a relief Undersized relief installed relief Miscellaneous
elief systems are the last line of device device device deficiencies
defense for chemical process fa-
cilities. Verifying their capabil-
Level 2
ity to safeguard equipment in- causes
tegrity becomes important as process
plants age, increase their capacities to Undersized Inappropriate
adjust to new market requirements, relief lines or relief line routing
equipment
undergo revamps or face new environ-
mental regulations.
Incorrect relief Block valves
In the past, approximately 30% of device set without involuntary
the chemical process industries’ (CPI) pressure closure prevention
losses could be attributed, at least in
part, to deficient relief systems [1]. Level 3
Furthermore, in an audit performed causes

by an independent firm at more than


250 operating units in the U.S., it was Overpressure Higher relief loads
scenario unforeseen than forseen
determined that more than 40% of the during design during design
pieces of equipment had at least one re-
lief-system-related deficiency [2]. These
indicators underscore the importance Figure 1. A problem tree for relief system shows causes, problems and symptoms
of checking the plant relief systems.
This article presents the most com- ply with “recognized and generally ac- ficiencies can be classified into one of
mon types of relief system problems cepted good engineering practices” [3] three types [2]:
with their possible solutions and offers in relief systems design. The recognized 1. No relief device present on equip-
basic guidelines to maintain problem- and generally accepted good engineer- ment with one or more potential
free relief systems. ing practices are criteria endorsed by overpressure scenarios
widely acknowledged institutes or orga- 2. Undersized relief device present on
Common problems in nizations, such as the Design Institute equipment with one or more poten-
existing relief systems for Emergency Relief Systems (DIERS) tial overpressure scenarios
Problems and their causes or the American Petroleum Institute 3. Improperly installed pressure relief
Relief system problems or deficiencies (API). For instance, in the petroleum device
can be identified, with respect to the refining industry, the accepted good en- The first type of deficiency refers to
U.S. Occupational Safety and Health gineering practices are collected in API the lack of any relief device on a piece
Admin. (OSHA) regulation 29 CFR Standards 520 and 521. of equipment that is subject to poten-
1910.119, as items that do not com- The most common relief system de- tial overpressure. The second type
38 Chemical Engineering www.che.com July 2010
Table 1. Relief-system problem identification during overpressure-scenario modeling
Relief System Deficiency Identified When:
Undersized Insufficient relief- Calculated relief-device area > installed relief device area
relief device device area
Improperly Excessive relief-valve Friction pressure drop in pressure-relief-device inlet line > allowable friction
installed inlet-line pressure drop losses (typically 3% of the set pressure)
relief device
Excessive relief valve Relief valve backpressure > allowable backpressure (typically 10% for conven-
backpressure tional valves, or 50% for balanced bellows valves considering backpressure
capacity-reduction factor)
Incorrect relief-valve Pressure in protected vessel or line > Maximum allowable accumulated pres-
set pressure sure (typically 10, 16 or 21% of the MAWP for pressurized vessels with single
relief valves for non-fire scenario, multiple relief valves for non-fire scenario, and
relief valves for fire-scenario), AND pressure at PSV inlet < PSV set pressure
Miscellaneous Excessive line velocity Line Mach number > allowable Mach number (typically 0.7)
Insufficient knockout Effectively separated droplet size at maximum relief load > allowable droplet
drum liquid separation size (typically 300–600 µm)
Excessive flare radia- Calculated radiation level at a specific point > allowable radiation level (typi-
tion cally 1,500 Btu/h-ft2 where presence of personnel with adequate clothing is
expected for 2–3 min during emergency operations, or 500 Btu/h-ft2, where
continuous presence of personnel is expected, both including sun radiation)

refers to an installed relief device data, “the employer shall document 3. Overpressure scenario identifi-
with insufficient capacity to handle that equipment complies with rec- cation. In this step, the P&IDs are
the required relief load. The third ognized and generally accepted good examined in order to identify credible
type encompasses relief devices with engineering practices” [3] overpressure scenarios for each piece
incorrect set pressures, possibility 2. Process hazards analysis, which of equipment.
of involuntary blocking or hydraulic may include: What-if, hazard and op- 4. Overpressure scenario model-
problems. In addition to these prob- erability (HAZOP) study, failure mode ing. The fourth step is to model each
lems, other less frequent ones can be and effects analysis (FMEA), fault-tree credible overpressure scenario. Each
cataloged as miscellaneous deficien- analysis or equivalent methodologies. model is developed in accordance with
cies. A relief-system problem tree is In order to document that the plant the chosen reference standard (for
shown in Figure 1. equipment complies with recognized instance, API 520 and 521). The fol-
In a previous statistical analysis of and generally accepted good engineer- lowing calculations are typically per-
272 process units in the U.S., it was ing practices, the plant management formed during this step:
observed that [2]: must validate that the facilities are • Required relief load for each over-
• 15.1% of the facilities lacked relief de- protected against potential overpres- pressure scenario
vices on equipment with one or more sure scenarios, in accordance with • Required relief-device orifice area
potential overpressure scenarios accepted codes and standards, such for each overpressure scenario
• 8.6% of the relief devices were un- as API standards 520 and 521. An ef- • Relief line’s hydraulics
dersized fective relief-system-validation study • Knockout drum (KOD) liquid-sepa-
• 22% of the relief devices were im- comprises the following steps: ration verification
properly installed 1. Plant documents and draw- • Flare or vent radiation, dispersion
ings gathering. The first step in- and noise level calculations
Identifying potential problems volves obtaining and classifying the The overpressure scenario modeling
There are work methodologies that existing plant documents and draw- can be done in different ways, be it
allow identifying potential problems ings: process flow diagrams (PFDs), by hand calculations, spreadsheets
in relief systems. OSHA regulation mass and energy balances, product or by the use of steady-state or dy-
29 CFR 1910.119 is based on safety compositions, equipment and instru- namic relief-system simulation soft-
audits that use techniques such as ment datasheets, P&IDs, relief device ware. The results of the models are
process hazard analyses performed at datasheets, relief loads summaries, re- analyzed to identify potential prob-
regular intervals. The work methodol- lief line isometrics, one-line diagrams, lems. Table 1 summarizes the pos-
ogy established by this regulation to unit plot plan, and so on. sible relief system problems and the
identify safety hazards comprises two 2. Plant survey. The second step con- ways to identify them on the calcula-
basic steps [3]: sists of inspecting the installed relief tion results.
1. Process safety data gathering, devices to verify that they are free of
which includes the following: mechanical problems, to update and Available solutions
• Process chemical safety data fill-out missing data in the plant docu- There are various solutions for each
• Process technology data ments and to verify consistency be- type of relief system problem. The
• Process equipment data [materials tween the documents and drawings available solutions can be classified
of construction (MOCs), piping and and the actual as-built plant. During as: (a) modification of existing relief
instrumentation diagrams (P&IDs), plant surveys, other typical indica- system components, (b) replacement
design standards and codes, design tions of relief system problems are the of existing relief system components,
and basis of design of the relief sys- presence of pockets, leaks or freezing (c) installation of new relief system
tems, among others]. As part of these in relief lines and headers. components, or (d) increasing the reli-
Chemical Engineering www.che.com July 2010 39
Table 2. Conditions that increase the probability
and impact of relief system failure
Conditions that increase the probability of Conditions that increase the impact of
Feature Report relief system failure relief system failure
The plant has over 20 years of service The plant handles toxic, hazardous or
flammable fluids
ability of the emergency shut- The plant currently handles different prod- The plant handles gases
ucts to those it was originally designed for
down systems.
The modification of exist- The plant operates at a different load or The plant operates at high pressures
at different conditions to those it was origi-
ing relief-system components nally designed for
includes changes made to in- There have been contingencies that have The plant operates at high temperatures
stalled components, without required the replacement of equipment or
requiring their replacement. lines in the past
Some examples of this type of Rotating equipment (pumps, compressors) The plant has furnaces, or equipment
solution include the following: has been modified (for instance, new im- that adds considerable heat input to the
1. Recalibrating the pressure pellers) or replaced fluids
relief valve by readjusting The relief valves have not been checked or The plant has high-volume equipment
the set pressure (solution validated in the last ten years (such as columns, furnaces)
to incorrect set pressure) or Modifications have been made to existing The plant has exothermic reactors, or
relief valve lines (that is, they have been chemicals that could react exothermi-
the blowdown (solution to rerouted) cally in storage
inlet-line friction losses be- A complete and up-to-date relief valve in- The plant has large relief valves (8T10),
tween 3% and 6% of the set ventory is not available or the relief header has a large diameter
pressure) The relief load summary has not been up- The plant has a high number of opera-
2. Adding locks to relief lines’ dated in the last ten years tions personnel
block valves (to prevent in- A relief header backpressure profile is not The plant is located near populated
voluntary valve closure) available, or the existing model has not areas
The replacement of existing been updated in the last ten years
relief system components in-
volves substituting inadequate relief in which redundant instrumentation Deficiency No. 2
system elements for newer, appropri- and emergency shutdown valves are This type of deficiency involves under-
ate ones. Some examples of this solu- installed in order to cutoff the over- sized relief devices that are present on
tion are the following: pressure sources during a contingency. equipment with one or more potential
1. Replacing the installed pressure The main advantage of this type of overpressure scenarios.
relief valve, either for one with a solution is that it can significantly re- Case 2: Insufficient orifice area
larger orifice area (solution to un- duce the required relief loads, hence after changes in the stream com-
dersized relief device) or for one of a posing an economical alternative to position. In a petroleum refinery, a
different type (solution to excessive the installation of new relief headers, desalter that was originally designed
backpressure) knockout drums or flares. to process heavy crude oil was pro-
2. Replacing relief line sections to tected against a potential blocked
solve hydraulic problems, such as: examples of problems outlet by a relief valve on the crude
excessive relief-valve inlet-line fric- in aging systems outlet. When the refinery started
tion losses, excessive backpressure, What follows are examples of some processing lighter crude, simulations
excessive fluid velocity, pockets, typical relief-system problems that showed partial vaporization in the
among others can be found in aging process facilities relief valve. The vapor reduced the
The installation of new relief system and the recommended remedy. PSV capacity until it was insufficient
components involves the addition of to handle the required relief load. In
relief system elements that were not Deficiency No. 1 this case, the recommendation was to
included in the original design, such The first type of deficiency is when no replace the original PSV for one with
as the following: relief device is present on equipment a larger orifice and appropriate relief
1. New pressure relief valves, either with one or more potential overpres- lines.
on equipment lacking overpressure sure scenarios.
protection, or as supplementary Case 1. New overpressure scenario Deficiency No. 3
valves on equipment with under- after pump replacement. In a pro- The third type of deficiency involves
sized relief valves cess unit, a centrifugal pump was re- improperly installed pressure relief
2. New headers, knockout drums or placed for another one with a higher devices.
flares, when the revised relief loads head, without considering the down- Case 3: Excessive backpressure due
exceed the existing relief system stream system’s maximum-available to discharge line modifications. An
capacity, or when relief system seg- working pressure (MAWP). Since the existing vacuum-distillation column’s
regation (that is, acid flare/sweet downstream system was designed at PSV outlet lines were rerouted from the
flare, high-pressure/low-pressure the previous pump’s shutoff pressure, atmosphere to an existing flare header
flare) is required the installation of a higher shutoff due to new environmental regulations.
Increasing the reliability of the emer- pressure pump created a new blocked The installed PSVs were a conven-
gency shutdown systems is typically outlet scenario. Therefore, the instal- tional type, so with the new outlet-line
done via implementation of high in- lation of a new pressure safety valve routing, the backpressure exceeded
tegrity protection systems (HIPS), (PSV) was recommended. the allowable limit. A recommendation
40 Chemical Engineering www.che.com July 2010
Incorrect Correct

LO CSO

LO CSO

No measures are taken The block valves on PSV lines are kept
to prevent involuntary open via locks (LO) or car seals (CSO)
PSV blocking

Incorrect Correct

A PSV installed over the mist A PSV installed below the mist
eliminator is ineffective when eliminator is effective even if
the latter gets clogged the latter is clogged

Figure 2. The risk of blocking in a pressure safety valve Figure 3. Non-free-draining lines in installed relief lines, such
(PSV) can sometimes be readily identified on P&IDs as shown in these two constructions, may cause accumulation
of liquids that can hamper relief valve performance

was made to replace the existing PSVs tations, a non-ideal line arrangement only for a fire, additional discharges
for balanced bellows PSVs. is installed, creating pockets on relief were not considered by the designer.
Case 4: Incorrect PSV set pressure lines that may cause liquid accumu- However, the power failure also af-
due to static pressure differential. lation and hamper relief valve perfor- fected these drums. When this case
A liquid-full vessel’s relief valve was mance (Figure 3). was evaluated, the backpressure was
set to the vessel’s MAWP; however, the too high for the installed PSVs, so they
relief valve was installed several feet Deficiency No. 4 had to be replaced by piloted valves.
above the equipment’s top-tangent The fourth category of deficiencies is a
line. The static pressure differential miscellaneous grouping. MAINTAINING PROBLEM-
was such that the pressure inside the Case 8: Problems in an existing FREE RELIEF SYSTEMS
vessel exceeded the maximum-allow- flare network due to additional Some practical guidelines are offered
able accumulated pressure before the discharges. The additional dis- below to help the plant management
PSV would open. The problem was charges of various distillation-column to assess, identify and troubleshoot re-
solved by modifying the existing PSV, relief valves were rerouted to an exist- lief system problems.
recalibrating it to the vessel MAWP ing flare network because of new envi-
minus the static pressure differential. ronmental regulations. The additional Tip No. 1: Assess the risk
Case 5: Incorrect PSV set pressure discharges exceeded the system capac- Some factors tend to increase the prob-
due to higher operating tempera- ity, and the entire flare network and ability and impact of a relief system
ture. The temperature of a stream was emergency shutdown system had to be failure. Table 2 qualitatively shows
increased with the addition of new heat redesigned by selecting the optimum some of them. If several of the condi-
exchangers, and no attention was paid tie-in locations for the discharges, and tions shown on Table 2 apply, then the
to the set pressure of the thermal relief by implementing HIPS in order to re- plant management should consider
valve in the line. By increasing the tem- duce the required relief loads. planning a detailed study, such as a
perature, the pipe MAWP was reduced. Case 9: Sweet and sour flare mix- quantitative risk analysis (QRA), or a
The PSV set pressure was lowered to ing. When revamping a section of a relief-system validation study.
the new MAWP at the new working process unit’s relief headers, some acid
temperature plus a design margin. discharges were temporarily routed Tip No. 2: Maintaining up-to-
Case 6: Risk of blocking the relief to the sweet flare header in order to date relief-valve information
valve. A relief valve can be blocked for maintain operations. Soon afterwards, The plant management should main-
various reasons. Some of the most com- the header backpressure started to in- tain accurate, up-to-date relief-valve
mon include the lack of locked-open crease and scaling was detected upon data for maintenance and future ref-
(LO) or car-seal-open (CSO) indica- inspection. The acid gases could also erence. The following documents are of
tions in the PSV inlet- and outlet-line generate corrosion, as the sweet flare particular interest: (a) relief valve in-
block valves, and installing the PSV header material was inadequate to ventory, (b) relief loads summary and
above the mist eliminator on a sepa- handle them. (c) relief header backpressure profile.
rator. Both deficiencies can be readily Case 10: High- and low-pressure Relief valve inventory. The relief
identified on P&IDs (Figure 2). flare mixing. The discharges of low valve inventory is a list that contains
Case 7: Pockets. Relief lines going pressure PSVs located on drums were basic information and status for each
to closed systems should be self- routed to the closest flare header, which relief valve, which should include the
draining. It is not uncommon during was a high pressure header. Since the following:
construction that, due to space limi- design case for relief of the drums was • Valve tag
Chemical Engineering www.che.com July 2010 41
Feature Report

Table 3. Relief system validation study typical execution phases and deliverables
Phase Deliverable Deliverable description
Survey and Updated relief de- A list containing up-to-date, accurate data for each relief device located in the
data gathering vice inventory plant. The minimum data to be included on the list are as shown in Tip No. 1, and
they should be obtained by combining relief-valve manufacturer documentation
with onsite inspections
Updated P&IDs P&IDs showing the existing installed relief-device information: connection diam-
eters, orifice letter, set pressure, inlet- and outlet-line diameters and block valves
List of pockets A document identifying pockets on relief lines, with the appropriate photographs
Existing relief Updated relief A list containing the required relief loads for each applicable overpressure sce-
system model- loads summary nario of each relief device, the required orifice area and the relieving fluid prop-
ing erties, based on actual process information
Updated relief- A document showing a general arrangement of the relief headers and subhead-
network back- ers, along with updated backpressure profiles for the major plant contingencies
pressure profile
Updated relief de- A document containing the calculations for each relief device under actual op-
vice calculations erating conditions
List of relief sys- A document listing all of the deficiencies found in the existing relief system, cat-
tem deficiencies egorized by type
Relief system Conceptual engi- A document defining the modifications required to solve the relief system defi-
troubleshooting neering ciencies

• Process unit and area for each phase are described in Table be available to provide technical in-
• Location 3. If the plant management has spe- formation and verify the validity of
• Discharge location cific document formats, it should the consulting firm’s calculations. The
• Connection sizes provide them as part of the deliver- typical information that the consult-
• Connection rating able description. ing firm will request in order to com-
• Orifice letter The study may require a number of plete the study includes: relief device
• Manufacturer resources that are not readily avail- inventory, relief loads summary, relief
• Model able in the plant. If the plant man- device datasheets, mass and energy
• Type (conversion, ball, pilot) agement has available resources but balances, PFDs, P&IDs, equipment
• Set pressure lacks specialized software licenses, datasheets and relief line isometrics
• Allowable overpressure then it can assign some of the tasks for each evaluated process unit/area.
• Design case to inner resources, for example, survey The consulting firm may also request
• Installation date and data gathering. Tasks requiring process simulations, if available.
• Last inspection date expertise or software packages above
• Last calculation date the plant’s capabilities, such as com- Tip No. 4: When modeling, go
Relief loads summary. The relief plex distillation column, reactor sys- from simple to complex
loads summary contains all the over- tem or dynamic simulations, should Replacing a relief valve or header
pressure scenarios and relief loads be outsourced. section generates labor, materials, in-
for each relief device at the plant. The A consulting firm should be se- stallation and loss of production costs
data in this document can be used to lected based on its experience in that can only be justified when the
identify the critical overpressure sce- similar projects, technological ca- results of an accurate model identify
narios in the plant. pabilities (specialized software li- the need for it. However, developing
Relief-header backpressure pro- censes) and a reasonable cost esti- an accurate model for every relief de-
file. A backpressure profile of the en- mate. In order for the consulting firm vice in the plant can be impractical
tire relief network is valuable when to deliver an accurate estimate, the and costly, especially if only a small
evaluating the critical contingencies plant management should provide number of relief devices require re-
in the system, as it can be used to the scope definition along with suf- placement at the end.
identify relief valves operating above ficient information to identify each A practical compromise is to verify
their backpressure limits. relief device within the scope of the each system starting from a simple
project, its location and the possible model with conservative assump-
Tip No. 3: Planning and overpressure scenarios. These data tions, and developing a more accu-
executing a relief system study are available in the relief loads sum- rate model for those items that do
The execution of a typical, relief-sys- mary and relief device inventory. not comply with the required param-
tem validation study comprises three One person should be assigned on eters under such assumptions. This
phases: (a) survey and information the plant management side to manage approach minimizes the time and
gathering, (b) existing relief system the project, along with administrative effort dedicated to items, and con-
modeling and (c) relief system trou- personnel, and at least one in charge centrates on those items that could
bleshooting. The typical deliverables of technical issues; the latter should present problems.
42 Chemical Engineering www.che.com July 2010
For instance, for a blocked outlet rally wish to implement the quickest, References
downstream of a centrifugal pump most practical and least costly one. 1. American Institute of Chemical Engineers,
“Emergency Relief System (ERS) Design
and control valve system, the sim- For instance, when a relief valve’s Using DIERs Technology”, New York, 1995.
plest model is to assume a relief load inlet losses are between 3 and 6% of 2. Berwanger, Patrick, others, Pressure-Relief
equal to the pump’s rated capacity. If the set pressure, the valve blowdown Systems: Your Work Isn’t Done Yet, www.hy-
drocarbononline.com, July 7th, 1999.
the relief-valve orifice area is insuffi- can be adjusted instead of replacing 3. Occupational Safety and Health Administra-
cient under the previous assumption, the entire valve inlet line. tion, 29 CFR 1910.119 “Process Safety Man-
agement of Highly Hazardous Chemicals”.
the next step would be to read the
required relief load from the pump Tip No. 6: What to do after
curve with the control valve’s rated validation and troubleshooting Author
discharge coefficient and the valve’s A routine revalidation of the relief Sebastiano Giardinella is
a process engineer at Inelec-
downstream pressure equal to the re- system’s correct operation not only tra S.A.C.A. (Av. Principal con
lief pressure, ignoring piping friction bring that security to the plant man- Av. De La Rotonda. Complejo
Business Park Torre Este
losses. If the orifice area still seems agement over the integrity of its fa- Piso 5, Costa Del Este. Pan-
insufficient, then a rigorous hydraulic cilities, but also to third parties, such amá. Phone: +507-340-4842;
Fax: +507-304-4801; Email:
calculation of the entire circuit should as occupational safety organizations sebastiano.giardinella@
inelectra.com). He has six
be performed to determine the re- and insurance companies. The cost of years’ work experience in
quired relief load. a relief valve study may very well be industrial projects with a
special focus in relief systems design and evalu-
paid with a reduction in the plant in- ation, equipment sizing, process simulation and
Tip No. 5: Evaluate various surance premium. Furthermore, the bids preparation. He has participated in several
relief system evaluation studies, revamps and
solutions to problems image of a company that worries over new designs. Giardinella graduated as Chemical
As was mentioned earlier, there are the safety of its employees and the Engineer, Summa Cum Laude, at Universidad
Simón Bolívar in Venezuela and holds an M.S.
multiple solutions that are possible environment constitutes an impor- degree in project management from Universidad
Latina de Panamá. He has taken part as speaker
for a single relief system problem, and tant intangible benefit. n or coauthor on international conferences and is
the plant management would natu- Edited by Gerald Ondrey affiliated to Colegio de Ingenieros de Venezuela.

SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE


SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE
SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE
SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE
July
2008

SUBSCRIBE SUBSCRIBE SUBSCRIBE SUBSCRIBE


B S C SUBSCRIBE
R I B E SUBSCRIBE
T O SUBSCRIBE SUBSCRIBE SUBSCRIBE
Incorp
oratin

S U
www. So g
Into lids
6
che. Liquid
com s

Focu
s on
Gas
New Detec
Engin tion
eering
Closed Mater
Liquid ials
Dispe
Findin nsing
g the
To Fit Right
the Ap Gloves
Facts plicat
at Yo ion
ur Fin
Vacu gertip
um Pu s:
mps
Flowm
eter
News

Augu
st
2008

Written for engineers, by engineers


www. Sterili
8
che. zation
com PAG
E 34
r

More and more, business in the Chemical Process Industries (CPI) is not
Rever
se
PAG Osmo
E 34 sis
Heat
Transf
er
Fluids
Hydro

local, it’s global. To keep up with this rapidly evolving marketplace, you
car
Prope bon
rties

Focu
Filtra
s on
need a magazine that covers it all, not just one country or region, not just
one vertical market, but the whole CPI.
tion
Facts
at Yo
r Finge ur
Lesso rtips:
ns-Le
Syste arned Valve
ms s
Preven
ting
Cakin
g

With editorial offices in Europe, Asia, and North America, CHEMICAL


ENGINEERING is well-positioned to keep abreast of all the latest innovations
in the equipment, technology, materials, and services used by process
plants worldwide. No other publication even comes close.
The #1 choice
of worldwide To subscribe, please call 1-847-564-9290
CPI organizations or visit clientservices@che.com
www.che.com

Chemical Engineering www.che.com July 2010 43

Das könnte Ihnen auch gefallen