Project : MECP, Delhi

Month : Apr'18
Daywise Workplan 8-Apr-18
Completed Month
Sl. Till 31st Mar Today Completed Balance As
Total planned Qty: UOM Total Actual Till
No. 2018 Actual Till Date on Date
Date
Flyover
1 Pile No.s 502 502 - - 502.00 -
3 Pilecap: No.s 104 104 - - 104.00 -
4 Open foundation: No.s 35 34 - - 34.00 1.00
5 Pier: No.s 139 110 1.00 5.50 115.50 23.50
6 Pier cap: No.s 17 17 - - 17.00 -
7 Portal beam: No.s 61 30 - - 30.00 31.00
8 Girder Supply MT 5,470 2,990 - - 2,990.00 2,480.00
9 Girder Fabrication MT 5,470 1,782 - - 1,782.00 3,688.00
10 Transportation MT 5,470 584 21.48 657.75 1,241.75 4,228.25
11 Girder Erection MT 5,470 300 - - 300.00 5,170.00
12 RE wall erection: sqm 3,700 3,214 - - 3,214.00 486.00
13 RE wall filling: Cum 12,596 10,956 - - 10,956.00 1,640.00
Underpass :
1 Raft: Rmtrs 1,287 527 - - 527.00 760.00
2 Retaining wall: Cum 2,574 254 - 25.50 279.00 2,295.00
3 Crash barrier type2: Rmtrs 1,287 419 - - 419.00 868.00
4 Friction slab: Rmtrs 2,574 534 - - 534.00 2,040.00
5 Crash barrier type1: Rmtrs 2,574 - - - - 2,574.00
6 Skywalk pier: No.s 43 18 - - 18.00 25.00
7 Skywalk piercap: No.s 43 3 1.00 1.00 4.00 39.00
Note * Work hampered Due
to Rain (08-04-2018)