PLINTH AREA ESTIMATE

Name of work: - Construction of Elect. Secondary Works Div. Haldwani, at 132 kv S/S ,
Kathgodam

Per Sqm area rates as per CPWD letter No 62 62/SE(TAS)/Plinth Area Rates/399
dated 24/12/2012

1 For LOAD BEARINGCONSTRUCTION


2.1.1Single storeyed = Rs. 15000.00/Sqm

3 (3.1)Internal water supply


sanitary installations 4% = Rs. 600.00/Sqm
3 (3.3) Internal electric installation @ 12.50% = Rs. 1875.00/Sqm
4 (3.6.1) Power wiring and plugs 4% = Rs. 600.00/Sqm
5 (3.6.6) Computer conducting 0.5% = Rs. 75.00/Sqm
Total = Rs. 18150.00/Sqm

Plinth area of building = 132.46 Sqm

Total cost of building 132.46 Sqm x 18150.00/Sqm = Rs 2404149.00

Say Rs. 2400000.00+ Service Tax

J.E S.D.O E.E

plinth area
2

PLINTH AREA ESTIMATE

Annexure-A

Name of work: - Construction of dormitory (d/s) at woodland inspection house, Nainital

Per Sqm area rates as per CPWD letter No 62/SE(TAS)/Plinth Area rates/399 dated
24.12.12

1 For R.C.C framed structure construction


1.1.1(b) floor Height 3.35 Mt = Rs. 19000.00/Sqm

2 (1.2.8) resisting earth quake forces = Rs. 1140.00/Sqm

3 (3.1) Internal water supply and sanitary


installation @ 12.00% Item no 01 = Rs. 2280.00/Sqm
4 (3.2) External service connection @ 5.00% = Rs. 950.00/Sqm
5 (3.3) Internal electric installation @ 12.50% = Rs. 2375.00/Sqm
6 (3.6.7) Quality assurance @ 1.00% = Rs. 190.00/Sqm
Total = Rs. 25935.00/Sqm

Plinth area of building)


(G.F) = 6.0*6.0+1.50*4.50+4.55*2.00 = 51.85.Sqm
(F/F) = 6.0*6.0+1.50*4.5+0.90*8.00 = 49.95 Sqm
Total = 101.80.Sqm
Total cost of building 101.80 Sqm x 25935.00/Sqm = Rs 2640183.00

say Rs. 2650000.00

J.E S.D.O E.E

plinth area
3

PLINTH AREA ESTIMATE

Annexure-B

Name of work: - Construction of Parking garage at woodland inspection house, Nainital

Per Sqm area rates as per CPWD letter No 62/SE(TAS)/Plinth Area rates/122 dated
12.12.07

1 For R.C.C framed structure construction


1.1.1(b) floor Height 3.35 Mt = Rs. 19000.00/Sqm
2 (1.2.8) resisting earth quake forces = Rs. 1140.00/Sqm
3 (1.2.11) Stronger structure members to take heavy load
above 500 Kgs. / Sqm.
upto 1000 Kgs./Sqm = Rs. 1500.00/ Sqm.
4 (3.3) Internal electric installation @ 12.50% = Rs. 2375.00/Sqm
5 (3.6.7) Quality assurance @ 1.00% = Rs. 190.00/Sqm
Total = Rs. 24205.00/Sqm

Plinth area of building = 114.05 Sqm

Total cost of building 114.05 Sqm x 24205.00/Sqm = Rs 2760580.25

Say Rs 2760000.00

J.E S.D.O E.E

plinth area
4

PLINTH AREA ESTIMATE

Annexure-C

Name of work: - Construction of V.I.P. Suite over parking garage at woodland inspection
house, Nainital

Per Sqm area rates as per CPWD letter No 62/SE(TAS)/Plinth Area rates/122 dated
12.12.07

1 For R.C.C framed structure construction


1.1.1(b) floor Height 3.35 Mt = Rs. 19000.00/Sqm
2 (1.2.8) resisting earth quake forces = Rs. 1140.00/Sqm
3 (3.1) Internal water supply and sanitary
installation @ 12.00% Item no 01 = Rs. 2280.00/Sqm
4 (3.2) External service connection @ 5.00% = Rs. 950.00/Sqm
5 (3.3) Internal electric installation @ 12.50% = Rs. 2375.00/Sqm
6 (3.6.7) Quality assurance @ 1.00% = Rs. 190.00/Sqm
Total = Rs. 25935.00/Sqm

Plinth area of building = 33.06 Sqm

Total cost of building 33.06 Sqm x 25935.00/Sqm = Rs 857411.10

say Rs 857000.00

J.E S.D.O E.E

plinth area
5

PLINTH AREA ESTIMATE

Name of work: - Construction of Electricity Secondary Works Circle , Division and Sub
division office Haldwani at 132 KV S/S, Kathgodam
Per Sqm area rates as per CPWD letter No 62/SE(TAS)/Plinth Area Rates/399 dated
24/12/2012

1 For R.C.C framed structure construction


1.1.1(b) floor Height 3.35 Mt = Rs. 19000.00/Sqm
2 (3.1) Internal water supply and sanitary
installation @ 4.00% Item no 01 = Rs. 760.00/Sqm
3 (3.2) External service connection @ 5.00% = Rs. 950.00/Sqm
4 (3.3) Internal electric installation @ 12.50% = Rs. 2375.00/Sqm
5 (3.6.1) Power Wiring & plugs @ 4.00% = Rs. 760.00/Sqm
6 (3.6.6) Computer conduiting @ 0.50% = Rs. 95.00/Sqm

Total = Rs 23940.00/Sqm

Plinth area of building)


(G.F) =145.53 Sqm
(F/F) = 77.78 Sqm
Total = 223.31 Sqm
Total cost of building 223.31 Sqm x 23940.00/Sqm = Rs 5346041.40

say Rs. 53.46 lacs

J.E S.D.O E.E

plinth area
6

PLINTH AREA ESTIMATE

Name of work: - Construction of 6 no. type I & 10 no. type II quarters at 132 kv S/S
Kathgodam ( Haldwani ) , Nainital

Per Sqm area rates as per CPWD letter No 62/SE(TAS)/Plinth Area Rates/399 dated
24/12/2012

1 For R.C.C framed structure construction


(1.1.2(b)) floor Height 2.90 Mt = Rs. 14500.00/Sqm
Extra for
2 (1.2.3.) Every 0.3 mt. additional height of floor above
normal floor height of 3.35 mt./2.90 mt. = Rs. 270.00/Sqm
3 (3.1) Internal water supply and sanitary
installation @ 12.00% Item no 01 = Rs. 1740.00/Sqm
4 (3.2) External service connection @ 5.00% = Rs. 725.00/Sqm
5 (3.3) Internal electric installation @ 12.50% = Rs. 1812.50/Sqm
Total = Rs 19047.50/Sqm

TotalPlinth area of building:


type I (G.F) = 6*35.00 Sqm = 210.00 Sqm
(F/F) = 6*35.00 Sqm = 210.00 Sqm
Total Plinth Area = 420.00 Sqm
type II (G.F) = 10*54.00 Sqm = 540.00 Sqm
(F/F) = 10*54.00 Sqm = 540.00 Sqm
Total Plinth Area =1080.00 Sqm

Cost of building : type I 420.00Sqm x 19047.50/Sqm = Rs 7999950.00


Cost of building : type II 1080.00Sqm x 19047.50/Sqm = Rs 20571300.00
Total = Rs. 28571250.00

say Rs. 286.00 lacs

J.E S.D.O E.E

plinth area
7

PLINTH AREA ESTIMATE

Name of work: - Construction of Electricity Secondary Works Circle , Division and Sub
division office Haldwani at 132 KV S/S, Kathgodam

Per Sqm area rates as per CPWD letter No 62/SE(TAS)/Plinth Area Rates/399 dated
24/12/2012

1 For R.C.C framed structure construction


1.1.1(b) floor Height 3.35 Mt = Rs. 19000.00/Sqm

2 (3.1) Internal water supply and sanitary


installation @ 4.00% Item no 01 = Rs. 760.00/Sqm

3 (3.3) Internal electric installation @ 12.50% = Rs. 2375.00/Sqm


Total = Rs 22135.00/Sqm

Plinth area of building)


(G.F) =139.68 Sqm
(F/F) = 74.55 Sqm
Total = 214.23 Sqm
Total cost of building 214.23 Sqm x 22135.00/Sqm = Rs 4741981.05

say Rs. 47.42lacs

J.E
S.D.O
E.E

plinth area
8

PLINTH AREA ESTIMATE

Name of work: - Construction of 02 no. type IV quarters at 33/11 kv S/S


Ramnagar , Nainital

Per Sqm area rates as per CPWD letter No 62/SE(TAS)/Plinth Area Rates/399 dated
24/12/2012

1 For R.C.C framed structure construction


(1.1.2(b)) floor Height 2.90 Mt = Rs. 14500.00/Sqm
Extra for
2 (1.2.3.)Every 0.3 mt. additional height of floor above
normal floor height of 3.35 mt./2.90 mt. = Rs. 270.00/Sqm
3 (1.2.8) Residential earthquake Forces = Rs. 1140.00/sqm
4 (3.1) Internal water supply and sanitary
installation @ 12.00% Item no 01 = Rs. 1740.00/Sqm
5 (3.3) Internal electric installation @ 12.50% = Rs. 1812.50/Sqm
6 (3.6.7)Quality assurance @ 1.00 % = Rs. 145.00/sqm
Total = Rs 19607.50/Sqm

Total Plinth area of building:


Area of 1 qtr. = 115.00 sqm
Total area of Qtrs. = 2 x 115.100 = 230.00 sqm
Cost of building =230.00Sqm x 19607.50/Sqm = Rs 4509725.00

say Rs. 45.09 lacs

J.E S.D.O E.E

plinth area
9

PLINTH AREA ESTIMATE

Name of work: - Construction of 04 no. type IV quarters (D/S) at 132 kv S/S


Kathgodam, Nainital

Per Sqm area rates as per CPWD letter No 62/SE(TAS)/Plinth Area Rates/399 dated
24/12/2012

1 For R.C.C framed structure construction


(1.1.2(b)) floor Height 2.90 Mt = Rs. 14500.00/Sqm
Extra for
2 (1.2.3.)Every 0.3 mt. additional height of floor above
normal floor height of 3.35 mt./2.90 mt. = Rs. 270.00/Sqm
3 (1.2.8) Residential earthquake Forces = Rs. 1140.00/sqm
4 (3.1) Internal water supply and sanitary
installation @ 12.00% Item no 01 = Rs. 1740.00/Sqm
5 (3.3) Internal electric installation @ 12.50% = Rs. 1812.50/Sqm
6 (3.6.7)Quality assurance @ 1.00 % = Rs. 145.00/sqm
Total = Rs 19607.50/Sqm

Total Plinth area of building:


Area of 1 qtr. = 115.00 sqm
Total area of Qtrs. = 4 x 115.100 = 460.00 sqm
Add area of stair case = 22.50 sqm
Total plinth area = 482.50 sqm
Cost of building = 482.50Sqm x 19607.50/Sqm = Rs 4509725.00

say Rs. 45.09 lacs

J.E S.D.O E.E

plinth area
10

PLINTH AREA ESTIMATE

Name of work: - Construction of Chief Engineer(distribution ) office at old diesel power


house,Kathgodam
Per Sqm area rates as per CPWD letter No 62/SE(TAS)/Plinth Area Rates/399 dated
24/12/2012

1 For R.C.C framed structure construction


1.1.1(b) floor Height 3.35 Mt = Rs. 19000.00/Sqm
2 (3.1) Internal water supply and sanitary
installation @ 4.00% Item no 01 = Rs. 760.00/Sqm
3 (3.2) External service connection @ 5.00% = Rs. 950.00/Sqm
4 (3.3) Internal electric installation @ 12.50% = Rs. 2375.00/Sqm
5 (3.6.1) Power Wiring & plugs @ 4.00% = Rs. 760.00/Sqm
6 (3.6.6) Computer conduiting @ 0.50% = Rs. 95.00/Sqm

Total = Rs 23940.00/Sqm

Plinth area of building) = 381.76 Sqm

Total cost of building 381.76 Sqm x 23940.00/Sqm = Rs 9139334.40

say Rs 91.40 lacs

plinth area
11

PLINTH AREA ESTIMATE

Name of work: - Construction of Shed for workshop at 33/11 kv s/s Phoolchor ,


haldwani

Per Sqm area rates as per CPWD letter No 62 62/SE(TAS)/Plinth Area Rates/399
dated 24/12/2012

1 For LOAD BEARING CONSTRUCTION


2.4 Garrages/ shed = Rs 10000.00/Sqm

Plinth area of building =15.46x6.46 sqm

Total cost of building 99.87 Sqm x 10000.00/Sqm = Rs 998700.00

Say Rs. 998000 + Service Tax

J.E S.D.O E.E