Beruflich Dokumente
Kultur Dokumente
Dear Sir,
Benefits :
Thanking you once again and assuring you our best services.
Yours truly,
Johnson.p
A. System Definition
Plant Size:
DC Solar Array capacity: 1000 KWp
Grid Tied Inverter Capacity: 50KWp *20 No’s
PV Solar Panels – 320Wp panels – 3125Nos
Energy Production:
Expected Annual production: 14,85,000 KWH @ 4.5units/per KW/per day (As per simulations,
with losses)
Note:
Energy production projections are estimated energy only based on site’s solar data and our
experience with similar systems. We make no guarantee as to actual production output from this
system. Actual generation is subject to orientation, tilt angle of solar panels and losses (10 -15%).
On-Grid/Load Interfacing:
Solar system output shall be connected to a suitable load bus capable of taking the input. This
input point shall be selected in field in consultation with client’s Electrical Engineer.
B. System Components
Poly Crystalline Solar Modules Make: High Efficiency Modules (Frameless)
Model: PV Modules -72
Watage: 320 Wp
No. of Cells: 72
Voc: 44.14 V
Isc: 8.89 A
Vmp: 36.86 V
Imp: 8.68 A
Cell Efficiency: 18.1%
Module Efficiency: 15.1 %
Dimensions: 2030 X 1030 X 10 (mm)
Weight: 50 kg
Operating Conditions: -40°C to +60 °C
Maximum System Voltage:1000 VDC
Grid Tie Inverter
Grid Tie Inverter: 50KWp*20 no.s
Make: IEC approved, Reputed make
AC maximum output: Total 1000KWp
MPP voltage range: 270VDC - 850VDC
Maxi Open Array Voltage: 250VDC-1000VDC
Maximum efficiency: >98%
Power connection: 3-phase
C. Bill of Material
As required
Panel Mounting
3 Reputed Make M.S per the site
Structure
condition
4 AC & DC cables As Per site requirement As per ISO As per site
Remote Monitoring
5 As per the Inverter Make Monitor Lot
System
Earthing and
6 As Per IS Standard As per site
Lightning Arrestor
D. Solar On-Grid Power Plant
E. Installation Details
Area required:
The Total Area required for the System Installation shall be approx. 78,000 Sq. feet, without any
shades, facing North/south
Structural Anchoring:
Panels shall be mounted on M.S frames inclined to north/south depending on the site
conditions. The structure is designed in such a manner that module can be replaced easily and
in line with site requirements and it is easy to install and service in future. The frames will
be supported by M.S columns of suitable lengths to provide the pre-determined inclination
as per the drawing submited to you in the earlier.
Inverter Installation:
The inverter is available in IP65 housing; however, an enclosed space to be provided for the
same. Actual installation location and methods will be determined during Installation phase.
For maximum efficiency and minimum losses, it is advised to place the inverter close to Solar
Panels.
Electrical:
Proposed fire hose shaf will be used for running electrical cables down to the electrical panel
board. A detailed electrical design with single-line diagram and specifications will be prepared
during full design phase after receiving the PO, for the client’s approval
Scope of Work:
1) We shall conduct a detailed site visit with specialists to take accurate measurements,
photographs, and other site-specific information for full design.
2) Prepare full system design to include civil, structural, electrical and mechanical
components, with construction drawings and specifications.
3) Procure equipment and materials and deliver to site.
4) Perform complete system installation.
5) Test all electrical components in accordance with manufacturer instructions.
6) Commission the system to full operability
7) M.S fabrication work for Roof to mount PV solar panels.
F. Client Scope
Site-specific considerations will require assistance and cooperation from the client as outlined
below:
Provide access to work site for delivery of equipment and materials prior to and during
project implementation.
Provide a suitable and secure space for storage of equipment and materials.
Facilitate access of work crew to the work site 7 days a week.
Facilitate interfacing with the client’s resident engineering staff for consultation as
needed.
Separate electrical loads as per agreed loads and connect solar output to building load
system. Civil works, if any.
All the Statutory clearances, if any, required for the Project.
Net meter approval from Discom at extra charge.
Raising of pillars up to required height.
Provide free, un-interrupted power, security to material and personnel.
G. Delivery Schedule
H. Project Cost
The above rate includes PV Modules, Civil works, M.S. Fabrication works, installation of
modules, and B.O.S.incl. Installation & Commissioning.
A Total Capital expenditure for Solar Plant without GST Rs. 5,95,50,000.00
B A.D Benefit up to 40% Not considered
C Annual Savings @ Rs.8.5/- per unit x 14,85,000 units Rs. 1,25,22,500.00
D Payback Period: (A divided by C) 4.5 Years
E Free Power for balance 20.5 Years
F Total Power Plant life 25 Years
*Accelerated Depreciation (A.D) and yearly escalation of power tariff not considered.
If considered payback period will be even less/quick.
Authorized Signatory