abcd Power Energy Systems Indonesia

PT PJB UP Paiton
ESP#1 Rehabilitation
To : Bpk Lavi Rumandioko (PT.PJB UP Paiton- Manajer Pemeliharaan)
: Bpk Yudiansyah Harahap (Alstom Project Manager-TSEAID)

Cc : Bpk Edi Santosa (Alstom Project Manager)


: Bpk Marwoto (PT.PJB UP Paiton-Teknisi Listrik)
: Bpk Agua Wahyudi (PT.PJB UP Piaton-Rendal Listrik)

Fax :

Reported by : Marki (Alstom Site Manager)

Re : Daily Report D9 (June 26, 2012)


Date Reporting : June 26, 2012
1. Summary
Mechanical work progress= 33%
Electrical work progress=35%
Total progress=37%.

2. Safety
 No accident.
 No nearmiss.

3. Manpower
No Title Qty Working Location Remarks
1 Direct Staff
Site Manager 1 ESP
Supervisor 1 ESP
QC Inspector 1 ESP
Construction Engineer 2 ESP
Site Project controller 1 ESP
Technical Field Advisor 0 ESP
EHS Officer 2 ESP
QC Assistant 0 ESP

2 Indirect Staff
Material Control Spv 1 ESP
Project Admin 1 ESP
Secretary 0 ESP

3 Direct Labour
Foreman 2 ESP
Lead Man 4 ESP
Skill Fitter 21 ESP
Semi skill 19 ESP
Electrician 4 ESP
GTAW Welder 1 ESP
SMAW Welder 6 ESP
FCAW 0 ESP
Rigger 10 ESP
Millwright 1 ESP
Helper 19 ESP

26 June 2012 1of 5


abcd Power Energy Systems Indonesia
PT PJB UP Paiton
ESP#1 Rehabilitation
PWHT operator 0 ESP

4 Indirect labour
Tool keeper 2 Warehouse
Office boy/girl 1 Office
Driver 2 Outside

4. Material and Tools & Equipment Status


Material arrival status: 100%

5. Weather
 Bright

6. Major item completed


ESP#A
 Install drive house bottom

ESP#B
 Install and alignment hot roof modification at B10

Gas Distribution
 Install shock beam for screen A/B at GD-A1/A2/B1/B2
 Install rapping shaft for screen A/B at GD-A1/A2/B1/B2
Electrical
 Cut control cable

7. Major item in progress


ESP#A
 Install DE rapping mechanism
ESP#B
 Install DE rapping mechanism

Gas Distribution
 Remove MIGI shaft at GD-A1
 Remove MIGI shaft at GD-B2

Electrical
 Remove existing electrical part at T/R controller cabinet
 Wiring for new retrofit kit
 Wiring for new MCC
 Cut control cable as required

8. Major item to start


 Continue all item at Point 7

9. Problem encounter


10. Miscellaneous

11. Attachment
 S-Curve

26 June 2012 2of 5


abcd Power Energy Systems Indonesia
PT PJB UP Paiton
ESP#1 Rehabilitation
 Photograph showing construction progress

Approved by

Marki
(Alstom Site Manager)

26 June 2012 3of 5


26 June 2012
Attachments:

Progress(%)
PT PJB UP Paiton
ESP#1 rehabilitation

0.0%
5.0%
10.0%
15.0%
20.0%
25.0%
30.0%
35.0%
40.0%
45.0%
50.0%
55.0%
60.0%
65.0%
70.0%
75.0%
80.0%
85.0%
90.0%
95.0%
100.0%
18-Jun-2012
0% 11%
19-Jun-2012
2% 16%
20-Jun-20124% 18%
21-Jun-20125% 19%
22-Jun-20126% 23%
23-Jun-2012 8% 25%
24-Jun-2012 12% 27%
abcd Power Energy Systems Indonesia

25-Jun-2012 15% 31%


26-Jun-2012 19% 33%
27-Jun-2012 24%
28-Jun-2012 28%
29-Jun-2012 33%
30-Jun-2012 38%
1-Jul-2012 44%
2-Jul-2012 50%
3-Jul-2012 55%

Progress Plan (%)


4-Jul-2012 60%
Days 5-Jul-2012 65%
1.S-Curve

4 of 5
6-Jul-2012 70%
7-Jul-2012 76%
8-Jul-2012 81%
9-Jul-2012 85%
ESP#1 Rehabilitation S-Curve

10-Jul-2012 88%
Actual Progress(%)

11-Jul-2012 91%
12-Jul-2012 93%
13-Jul-2012 95%
14-Jul-2012 97%
15-Jul-2012 99%
16-Jul-2012 100%
17-Jul-2012 100%
18-Jul-2012 100%
19-Jul-2012 100%
20-Jul-2012
21-Jul-2012
abcd Power Energy Systems Indonesia
PT PJB UP Paiton
ESP#1 Rehabilitation
5.Photograp

Picture-1
Install drive house bottom

Picture-2
Night shift activities

Picture-3
Remove existing MIGI rapping at GD

26 June 2012 5 of 5