Beruflich Dokumente
Kultur Dokumente
Project By
Manila City
August/2014
ii
iii
Executive Summary
The group of Civil Engineering students proposes to design the annex medical
building of the maternity hospital, Mandaluyong City Medical Center (MCMC) Annex II,
as an encased steel composite structure that will have green design innovations. The need
for this structure comes from two sources - the growing number of patients in the
maternity and pediatric division, and the lack of medical facilities in the main building.
The design project aims to meet the requirements imposed by the beneficiary, the
local government of Mandaluyong City, specifically, the City Planning and Development
Office. So, the objectives of the design project are - to introduce encased steel-concrete
composite structure, to provide a green structural design that can maximize the use of
renewable resources and can still withstand natural constraints, to increase the lifespan of
the structure and present an economical design of the building, and lastly, to provide a
healthy and stimulating environment for the patient’s fast recovery and the staff’s
productivity.
The design will be computed using LRFD, and will be evaluated with a computer
simulation, STAAD. And to consider the structure as a green design, innovations such as
solar window films and rain water harvesting system will be utilized. In the estimation of
costs, the group will only focus on the structural part of the project but in the total budget
the architectural and electrical parts will still be included. The team’s outcome would be
a green building that is structurally safe, economical and innovative.
iv
Table of Contents
Title Page i
Approval Page ii
Executive Summary iii
Table of Contents iv
List of Tables and Figures viii
Chapter 1: Introduction 1
Abstract 18
3.1. Introduction 18
3.2. Review of Literature 19
3.3. Methodology 23
3.4 Conclusion and Recommendation 25
4.1.1 Introduction 26
4.1.2 Dead Load 26
4.1.3 Live Load 27
4.1.4 Earthquake Load 27
4.1.5 Total Factored Loads 28
Figures
Figure. 1a. Project Site Location Satellite View 10
Figure. 1b. Vicinity Map 10
Figure. 2. Number of Hospitals by Classification and
Ownership,Philippines, 2009 20
Figure. 3. Flow of the Design Project 24
Figure 4. Project Location Distance from Nearest Active Fault Line 27
Figure 5a. Staad Model 29
Figure 5b. Shear and Moment Diagram 29
Figure 5c. Forces on Beams 30
Figure 5d. Stresses on Beams 30
Figure 6. Beam Composite Section 31
Figure 7. Composite Beam (side view) 31
Figure 8. Beam and Slab Cross-Section 36
Figure 9. Roof Deck Framing Plan Showing Connection No. 1 at Roof Deck 52
Figure 10. Connection of W10x12 beam to Pipe8STD column 52
Figure 11. Roof Deck Framing Plan showing Connection No. 1 at Roof Deck 68
Figure 12. Connection of W10x17 beam to W10x12 girder 68
Figure 13. Retaining Wall 73
Figure 14. Weight of Retaining Wall 77
Figure 15. Pressure on Center of Gravity of The Retaining Wall 81
Figure 16. Weight acting on the toe slab 89
Figure 17. Footing No.1 104
Figure 18. Base Plate Example 112
Figure19a. Design using STAAD Pro 2007 v7i 115
Figure 19b. Designation of Footing Tie Beams 115
Figure 20a. Results from STAAD Pro 2007 v7i: FTB 659 116
Figure 20b. Results from STAAD Pro 2007 v7i: FTB 660 117
Figure 21a. September 2013 Rainfall Forecast from PAG-ASA 118
x
Chapter 1: Introduction
The health care industry or medical industry plays a vital role to a community’s
upbringing and success. It is a sector within the economic system that provides goods and
services that treat patients with curative, preventive, rehabilitative, and palliative
care. The Philippines is a sovereign state in Southeast Asia in the western Pacific Ocean,
remains as one of the countries that have the poorest health conditions in East Asia.
Despite the presence of several modern medical establishments in the capital city of
Metro Manila, we are still lacking the true essence of medical assistance that is: to
expand its range of clinical services offered directly or in collaboration with others to
minimize cost, improve access, and enhance service excellence.
Mandaluyong City, deemed as the "Tiger City" because of its notable number of
shopping malls, entertainment hubs, offices, financial hubs, and hotels, is on its way to
solving the said problems. With a population of 328,699 as of May 1, 2010 (based from
the Republic of the Philippines National Capital Region – District III, NATIONAL
STATISTICS OFFICE), this translates to an average annual population growth rate
(PGR) of 1.67 percent higher than that of the period of 1990 to 2000. This statistics
verifies the need for facility growth in all major departments of the city from education,
food, industrial, economical, environmental and especially their medical industry.
Presently, Mandaluyong has several private and public hospitals & health centers,
namely the privately owned Dr. Victor R. Potenciano Medical Center, and Unciano
General Hospital, and the government hospital Mandaluyong City Medical Center.
Among these three main hospitals, the Mandaluyong City Medical Center (MCMC)
serves as the only general acute public hospital in the city. It is located on Boni Avenue
corner Sto. Rosario St., Brgy. Plainview Mandaluyong, Metro Manila, Philippines and
was built on the 24th day of August 2004.
With their aim to provide total quality, efficient and effective medical care
delivery for their patients, the MCMC, along with the City Planning and Development
Office of Mandaluyong City, has constructed a two-storey maternity hospital along
Martinez St. (C-3 Road), Brgy. Addition Hills, Mandaluyong City. To aid their growing
number of patients in the maternity and pediatric division, the hospital is also planning to
have a four-storey annex building behind the maternity hospital.
2
For one, the facilities of some of the existing public hospitals were in many terms
“lacking”. Their rooms, facilities and services were all in need for a renovation or an
extension. Public hospitals in general should be able to accommodate all of their patients
and to meet the demands of the growing population.
The structural, environmental and economical aspects of a building design are the
norms that are considered in this proposed design project. The structural design norm
prioritizes the design criteria based on the existing structural codes and national hospital
building codes in the Philippines. The codes specifically used in this proposed project are
the National Structural Code of the Philippines (NSCP) and the Manual on Technical
Guidelines for Hospitals and Health Facilities Planning and Design. The requirements of
the beneficiary have also been taken into consideration. One of their requirements is to
transfer some of the facilities of the existing main Maternity Hospital building to the
proposed four-storey Mandaluyong City Medical Center Annex 2 building. The facilities
that they specified are the Kitchen/ Food Preparation Area, Laundry Service, Hospital
Central Record Room, and the Nurse and Doctor Lounge. In addition, the proposed
structural design will be made of composite materials, which is from two or more
components: steel and concrete to maximize the strength and stability of the building.
4
For the environmental design norm, the purpose is to make use of the available
renewable resources within the perimeter of the location. Application of a rainwater
harvester to the proposed design will serve as an alternative water source for industrial
purposes such as flushing and cleaning. Natural light would also be maximized through
wide window panels with solar window films that bounces off UV rays that passes
through the windows.
Lastly, the economical design, for which the priority is to achieve the most cost
effective design for the project. Since it is a government building, the requirement of
having a sustainable and long enduring structure amidst natural constraints should be
attained. Amidst the economical design, the medicinal aspect of the hospital environment
is vital for the patients’ recovery and should be given priority for their comfort and well-
being.
Structural Engineering is the major area of civil engineering used in this project. It
is a field of engineering dealing with the analysis and design of structures that support or
resist loads. In this proposed design of the four-storey Mandaluyong City Medical Center
Annex 2 building, the structural purpose is to create a stable medical building to
accommodate the needs and purposes of both its staff and its patients.
On the other hand, one of the project’s minor areas is geotechnical engineering.
Since it is concerned with the engineering behavior of earth materials, this area is the
basis of the foundation design of the structure that could withstand earthquake loads and
wind loads.
Last but not least, is water resources engineering, which is concerned with the use
and control of water. Since the use of rainwater harvester would be applied on the
building, a proper mode of collection, treatment and distribution for its designated
purpose should be calculated accurately.
accommodate their growing population rate and to provide the best health-care services
possible primarily for the indigent residents of the City Mandaluyong.
This project will provide additional rooms for the staff’s facility such as the
Hospital Central Record Room, Nurse and Doctor’s lounge and locker rooms. In this
annex building an x-ray facility, food preparation area and laundry service would also be
installed. For the patient’s comfort and convenience additional rooms for confinement
would also be supplied.
With the country’s growing medical tourism rate for private facilities, investing in
our local government public medical services has to be faced. Mandaluyong’s constant
strive to provide their local’s needs has already led them to begin constructing new
infrastructures for their city’s general needs. The medical service, which is vital for their
growth, is now prioritized, further supplementing their present facilities with a more
innovative approach embracing green design application and structural ingenuity.
For the design procedure of the four-storey annex medical building with a
composite material for the structural body, the use of structural computer programs such
as STAAD for roofing and frame and footing analysis would be used. Through these
programs the loads that the steel-concrete composite structure would have can be
considered and will also be analyzed. In addition, AutoCAD and Google SketchUp8
programs are used for the drafts and perspective. Such computer programs will be used to
illustrate the framing and design.
Composite construction exists when two different materials are bound together so
strongly that they act together as a single unit from a structural point of view. When this
occurs, it is called composite action. One common example involves steel beams
supporting concrete floor slabs. If the beam is not connected firmly to the slab, then the
slab transfers all of its weight to the beam and the slab contributes nothing to the load
carrying capability of the beam. However, if the slab is connected positively to the beam
with studs, then a portion of the slab can be assumed to act compositely with the beam. In
effect, this composite creates a larger and stronger beam than would be provided by the
steel beam alone. The structural engineer may calculate a transformed section as one step
in analyzing the load carry capability of the composite beam.
outside taps. This shows that the installation of a rainwater harvester can be
performed and will promote an economical advantage because of it uses a renewable
source.
The group will specifically conduct a research study on the related literature in
using Encased Steel Composite for Structural design, Solar Power Application and
Rainwater Harvester. The study will present the need for promoting green building
design and innovation in structural design for hospital buildings. Through this,
optimization of the facilities and services of a public medical center will be promoted and
upgraded to a level that introduces economical design through investing on renewable
resources based production of electricity and water source, as well as equating the
standards of service to the quality of private centers, thus giving the indigent public the
priority and help they need.
The projected operating cost and installation of the sustainable development for
the four-storey annex hospital building would also be given priority. Specifically,
research on cost efficiency, structural stability and applicability of using composite
structure, solar panels and rainwater harvester to the chosen target beneficiaries and
location would be studied.
For the design process, the main reference material for the loadings of the
structure will be the National Structural Code of the Philippines (NSCP) 2010 and the
Manual on Technical Guidelines for Hospitals and Health Facilities Planning and Design
for the hospital building code of the Philippines. For the allowable settlement-geo profile,
the Uniform Building Code (UBC) will be used.
7
The main issue of the public hospitals in our country has already been on the
radar of the World Health Organization for a while. Rising costs of health care in the
Philippines have subjected the slums communities of the capital of Metro Manila to a
deprived state of attaining proper medical care and assistance. Inequalities in access to
quality of health care among Filipino patients are glaring. While a few medical facilities
boast meeting world class standards on quality care, many others suffer from a dire lack
of equipment, facilities, and inadequate staff.
One of the cities in Metro Manila, Mandaluyong City, has been on the verge of
facing this issue by giving priority to medical infrastructure development. In this
perspective, the goal of the project is to maximize the quality, services and appeal of the
building and to create an ambiance suitable for the benefits of the staff and patients of the
hospital.
To apply the concept of green design, making use of the available renewable
resources within the perimeter of the location would be the objective. Application of a
rainwater harvester (an alternative water source for industrial purposes such as flushing
and watering plants), will be introduced. Natural light would also be maximized through
wide window panels with solar window films. This works through allowing the harmful
rays to bounce off of them and thus be repelled. This is done with a technologically
advanced material that is combined with the vinyl surface and since it is a hospital
facility, sanitation is top priority, thus ventilation through the air available in the
environment would be hazardous, making air-conditioning the only option.
Steel beams have long been recognized as one the most economical structural
systems for both multi-storey steel buildings and steel bridges. Buildings and bridges
require a floor slab to provide a surface for occupants and vehicles, respectively.
Concrete and metal decks (composite slab) are the materials of choice for the slab
because their mass and stiffness can be used to reduce deflections and vibrations of the
8
floor system and to provide the required fire protection. The supporting system
underneath the slab, however, is often steel because it offers superior strength-weight and
stiffness-weight ratio, ease of handling, and rapid construction cycles. Since both the
steel and concrete are already present in the structures, it is logical to connect them
together to better utilize their strength and stiffness.
9
The increasing demand for quality medical attention for affected communities
such as the indigent public has been one of the problems that the Philippines is facing.
These families lack the financial capacity to afford the medical attention that they need,
that in common situations only the private medical centers are capable of providing. With
this problem, our group, through the Municipality of Mandaluyong City, intends to take
an action towards the improvement of public hospitals. This proposed design project of a
four-storey annex medical building is a steel-concrete composite structure with green-
building design that maximizes the use of available renewable resources within the
perimeter of the location. The aim of this project is to provide total quality, efficient and
effective medical care delivery for the patients and the staff of the Mandaluyong City
Medical Center. The objective of this project is to create a green building design of the
annex hospital building, which will provide quality and comfort that can accommodate
their growing number of patients. The following rationales are as follows:
narrative description of the deliverables and services required to meet the contract
requirements. It provides the basis on which contractors develop proposals and bids.
In the construction phase, there are three important things to consider – site
logistics and mobilization, management control systems, and quality control. The site
logistics plan for the project utilizes one road on the north side of the site for most of the
site deliveries, as well as the access road for all of the concrete trucks to stage. During
certain times of the week while deliveries and trucks are trying to move around, traffic
around the site will be slowed down which will cause law enforcement in the area to get
involved.
Management control systems would mean that there should be coordination of
activities and meetings within the project team. There are numerous actions a project
team can take to ensure the quality of construction. These actions would include
independent oversight and keeping the permit process separate from the construction
contracting process. Construction oversight would mean that it would be needed to
supervise the performance of subcontractors on site, ensuring that work is performed in a
safe manner and in accordance with contract specifications, local laws and regulatory
requirements. Changes that will be implemented to the construction plan should be first
evaluated by the planning and design team.
The project is located on Boni Avenue corner Sto. Rosario St., Brgy. Plainview
Mandaluyong, Metro Manila, Philippines. Mandaluyong City is bounded on the
northwest by Manila, on the north by San Juan, on the east by Pasig City and Quezon
City and on the south by Makati City. The average elevation of Mandaluyong City,
Philippines is 24 meters.
Mandaluyong City is a highly urbanized city. In light of this, the air quality in this
city is uncomfortable. The city’s water supply comes from a private firm, Manila Water,
making the quality of the water clean and potable. The average temperatures in the year
2012 were recorded to be ranging from 23.9 ˚C (minimum) to 33.6 ˚C (maximum). The
average monthly rainfall of the city would be 18 mm (minimum) in the month of April
and 381.3 mm (maximum) in the month of August. Mandaluyong City is not a part of the
Marikina Valley Fault System and so the area is expected not to experience flooding,
except for times that there would be super typhoons.
The land of the project has already been cleared. There are no trees and grass
around and there are only a few domesticated animals that wander in the area. There are
very few birds in the area because the location of the project which is within the city and
there are less trees. Also, it is assured that there are no wild animals in the area. Overall
the area seems appropriate for the project location. And there is nothing to indicate that it
would be unsafe for people to go to the maternity hospital.
Mandaluyong City is the heart of the “Golden Triangle” (Manila, Makati, and
Quezon City). This city of the leading business and industrial centers in the country
today, the “New Tiger” of Metro Manila, which made an unprecedented giant leap to
progress. This highly urbanized city is characterized by low to medium density
residential subdivisions in the north, heavy industries in the south, commercial activities
in the east, and medium-scale commercial districts in the west.
In the absence of the project in the future, the maternity hospital will not be in its
full function. Also, the area would be vacant, unused and maybe full of garbage due to
the presence of people residing at the back area of the maternity hospital. There will also
still be no trees, or grass that would grow in the location. One part of the area will be
14
surely used as a terminal for the tricycles. In this case, the loss of the project will just add
up to the increasing cause of pollution in metro Manila.
The location of the project is one of the significant impacts of the project. The
proposed site is part of the lot area allotted for the Mandaluyong City Medical
Center (MCMC) Maternity Hospital and since the location has already been cleared
out by the Municipality of Mandaluyong it is already prepared for construction.
The noise during construction would affect the newly constructed and
operating Maternity Hospital. To lessen the impact of the noise to the existing
building, immediate measures would be taken. Ensuring that the machines and
equipment used for the construction is working properly and in good condition
would help in the process. In addition, limiting the working hours to a designated
schedule provides time allowance for both the construction process and the
operation of the maternity hospital.
Air quality is also an issue. Since it is in proximity with the operating maternity
hospital, atmospheric condition must be considered. To lessen the effect to the local
air quality, usage of wind breaks would be erected to minimize dust generation. Also,
using water spray for controlling the dust emitted from the construction process
would be helpful. In addition, water quality is also important. Having a solid waste
management would be the appropriate approach.
With the increasing demand of public services, the project will be of aid in
providing more medical facilities and accommodations for the public. Patients will
have a wider medical service range that will promote in developing better public
hospitals in our country. Changes in employment and income levels would also be an
effect of the project. The employment rate will increase thus supplementing income
to the community. The aesthetic quality of the community will also improve because
of the architectural design of the project.
16
The above mitigation and enhancement measures exemplify standard safety and
operating procedures to ensure the safety and well-being of the laborers and the affected
inhabitants near the perimeter of the construction site. During construction, solid wastes
gathered and produced from the site would be considered harmful and infectious.
Imposing solid waste management regulates the waste effectively. With the noise and
vibration caused by the equipment, administrative control, which incorporates the
17
schedule of working hours and hauling and delivery of materials, would be implemented.
Early hours would be the delivery schedule and construction will only be done during
working hours to avoid conflicts with the people residing near the perimeter.
Since the site area is not along the main road and has an allotted space for
occupying construction equipment, signage and warnings of debris falling and cautions
when passing along the perimeter would be an effective safety procedure. For the health
concern, diminishing dust remnants through water spray would control the situation.
Strict implementation of complete and proper safety gear of the workers would also be
implemented.
During construction, risk and injuries are inevitable. These liabilities often affect
the laborers. In most occasions, the machinery or equipment are the causes of said
injuries because they are malfunctioning or handled improperly. To accommodate these
accidents, a safety area will be allotted to address injuries and providing first aid
medication. Occasional breakage of materials and malfunctioning of the equipment also
occurs during construction. Thus, an allotted fund for any probable machine repair would
also be supplemented, as well as for the replacement of the materials that were damaged.
Fire protection is also important for the duration of the project. Fire alarms and
fire extinguishers would also be distributed at positions where they can be easily acquired
when problem occurs.
3.1 Introduction
Many indigent Filipinos suffer from lack of proper health care services. And thus,
the aim of the local government of Mandaluyong City along with the City Planning and
Development Office of Mandaluyong City, is to provide total quality, efficient and
effective medical care delivery for their patients in MCMC II. To aid their growing
number of patients in the maternity and pediatric division, they have planned to have a
four-storey annex building with a floor area of 288 sq. m. behind the maternity hospital.
In this building, there would be added medical facilities like wards, rooms, x-ray, etc.
The design project proposes a steel-concrete composite structure that uses a green
building design. Concrete is efficient in compression and steel in tension. Concrete also
restrains steel against buckling. Steel on the other hand, brings stability to the structure.
On the other hand, the project also proposes the use of glass panels, solar panels, and a
rain water harvesting system as part of our green building design. Glass panels and solar
panels would be efficient in maximizing the use of sunlight. A rain water harvesting
system would be used for sewerage purposes like flushing toilets.
These topics present a review of several literature, readings and studies asserted
by several people and pioneers in the field of architecture and civil engineering, which
would be helpful to the design project.
RESS
Figure 3. Number of Hospitals by Classification and Ownership, Philippines, 2009
reduce the human impact on global warming. One of these innovations is sustainable
design or green design (Telegen, 2005).
In an article by the Dot Republic (2007), it was said that they were asked to
design and install a water harvesting system to supply rainwater to the main toilet block
using the large roof areas of the buildings within the GreenWood Forest Park. The rain
falling on the roofs of the Great Hall and the Puzzle Barn (total area 370 m 2) is collected
in the gutters and conveyed by 110 mm pipe hidden in overhead sluices, to a WISY 150
vortex filter. The WISY filter removes most of the dirt before the water is passed to two
linked 2.5 m3 tanks which are hidden in a large wooden box on the island between the
toilet block and the Puzzle Barn. These tanks are located about where it says Snowdon
Snacks. The system is expected on average to save 200 m 3 water a year, which is about
20% of the water used for toilet flushing in the main toilet block.
Since the project involves the design of an annex building of a maternity hospital,
this would mean that their water consumption would be very high. To lessen this
consumption, rainfall water would be used for the flushing of toilets in the annex
building. Rainwater harvesting would be appropriate for the design project because
rainfall in Mandaluyong City, ranges from 10.16mm to 403.86 mm. (See the table
below.)
21
3.3 Methodology
3.3.1 Research Design
The study is an Applied Descriptive Design. The process of the study is divided
into three major stages–data gathering, design planning, and economic evaluation. In the
first stage, in order to make the proposal plausible data gathering would be conducted.
The data gathering would be summarized for the review of related literature of the study.
A site visit would be done and a need for consultation of the beneficiary to define the
problems in the project. After the data gathering, the architectural design of the annex
building will be considered. The second stage would be the design planning which
includes structural design and analysis and green design. The structural design would
need the use of the computer program, STAAD. As for the green design, solar panels and
the rainwater catchment system would be introduced. Then, consultation of the
beneficiary would be done to check if the problems stated were addressed. The last stage
of the study would be the economic evaluation. It involves identification of alternatives,
their consequences and their costs. This evaluation would determine whether the project
would be done or not.
The related literature would serve as one of the research instruments for the
design project. The related literature is intended to provide valid data that would help
improve the paper and the design project. This would come from validated studies,
readings, journals, articles, and scientific findings from technical books. Also, this
literature would provide the group economical rates for the materials necessary for the
design project.
Another instrument would be the data that would come from the local government
of Mandaluyong City, particularly, the City Planning and Development Office.
24
The internet and the library would be used to accumulate the literatures. The
group would also interview the engineers and architects of the City Planning and
Development Office of Mandaluyong City assigned to the MCMC Annex II building in
order to know the lot area, soil profile, guidelines in designing a hospital, and other
specifications needed.
Start
Consultation of Background
Beneficiary Study
Green Design
Is the problem No
Revise
addressed?
Yes
Economic Evaluation
End
The safety and security of this structure is highly considered. With the
design concept of using composite as its structure, many of its vital components
are upgraded to a standard that has more strength and capacity. In addition, with
the concrete acting together with the steel component, the combination creates a
stiffer, lighter, less expensive structure which targets our goal: to attain an
economical structure for the government or public facility of Mandaluyong City
that is the Medical Center.
This research highlights a solution to the high-cost construction of
hospitals and reflects a design that is suitable for government use and is
economical and safe. The aesthetic aspect is not compromised with its key
objective of providing a therapeutic ambiance for the patients and workers, and as
well as providing an alternative source of energy for lighting and water use.
26
5. Partition
i. Hollow Concrete Masonry 1.05
ii. Plaster 0.48
6. Shear Wall Thickness of Wall = 400mm 9.6
Total Dead Load Floor 3.95
Wall 1.53
27
Live Load
1. Hospital kPa
i. Dining Rooms 4.8
ii. Wards/Rooms 1.9
2. Storage i. Light 6
The distance of the project location from the nearest active fault line based in the
figure above is beyond 5 kilometers. The following earthquake parameters were
established and presented in the table.
Table 7. Earthquake Parameters
a) Maximum Moment, Mu
Using STAAD Pro 2007 v7i, the maximum moment on the beams and girders were
computed.
Table 8a. Maximum Moment on Beams and Girders at Roof Deck and Fourth Floor
Max Max
Beam Length(m) Moment Beam Length(m) Moment
(kN-m) (kN-m)
R-B1 6 170.856 4-B2 6 170.856
R-B2 6 79.993 4-B4 6 108.817
R-B1 6 108.437 4-B3 6 194.616
R-B1 6 108.437 4-B1 6 140.504
R-B1 6 108.437 4-B1 6 140.504
R-B1 6 108.437 4-B1 6 140.504
Max Max
Girder Length(m) Moment Girder Length(m) Moment
(kN-m) (kN-m)
R-G1 6 29.641 4-G1 6 43.592
R-G2 3 27.312 4-G2 3 40.948
R-G3 6 102.159 4-G3 6 108.012
R-G1 6 63.344 4-G1 6 63.344
R-G2 3 35.567 4-G2 3 35.567
R-G1 6 21.044 4-G4 6 36.988
R-G2 3 16.715 4-G5 3 35.695
R-G4 6 32.88 4-G6 6 54.017
R-G1 6 28.836 4-G7 6 51.758
R-G2 3 12.311 4-G8 3 29.953
R-G1 6 29.911 4-G9 6 41.208
R-G2 3 21.841 4-G10 3 36.462
R-G1 6 27.63 4-G9 6 39.066
R-G1 6 28.051 4-G9 6 39.517
R-G2 3 21.421 4-G10 3 35.452
R-G5 6 51.163 4-G11 6 67.022
R-G6 6 73.265 4-G12 6 115.619
R-G7 6 37.153 4-G13 6 53.723
R-G8 6 37.145 4-G14 6 58.858
R-G6 6 73.199 4-G15 6 147.593
R-G5 6 50.916 4-G16 6 81.58
R-G5 6 51.241 4-G17 6 58.342
R-G6 6 73.287 4-G18 6 95.261
33
Table 8b. Maximum Moment on the Beams and Girders at Third Floor and Second Floor
Max Max
Beam Length(m) Moment Beam Length(m) Moment
(kN-m) (kN-m)
2-B2 6 170.856
3-B2 6 170.856
2-B3 6 112.355
3-B3 6 110.32
2-B2 6 170.856
3-B2 6 170.856
2-B1 6 140.504
3-B1 6 140.504
2-B1 6 140.504
3-B1 6 140.504
2-B1 6 140.504
3-B1 6 140.504
Max
Max Girder Length(m) Moment
Girder Length(m) Moment
(kN-m)
(kN-m)
2-G1 6 62.595
3-G1 6 52.363
2-G2 3 78.414
3-G2 3 58.255
2-G3 6 133.219
3-G3 6 119.858
2-G1 6 87.427
3-G1 6 73.619
2-G2 3 72.862
3-G2 3 52.497
2-G4 6 57.756
3-G4 6 47.539
2-G5 3 68.774
3-G5 3 50.53
2-G6 6 72.724
3-G6 6 62.444
2-G4 6 72.553
3-G4 6 60.616
2-G5 3 64.24
3-G5 3 45.264
2-G7 6 59.892
3-G7 6 49.819
2-G8 3 72.192
3-G8 3 52.815
2-G7 6 56.008
3-G7 6 46.787
2-G7 6 58.097
3-G7 6 48.041
2-G8 3 72.433
3-G8 3 52.272
2-G9 6 66.656
3-G9 6 66.754
2-G10 6 115.263
3-G10 6 116.793
2-G11 6 57.129
3-G11 6 55.251
2-G12 6 59.97
3-G12 6 59.13
2-G10 6 115.81
3-G10 6 115.379
2-G9 6 66.42
3-G9 6 66.48
34
Max
Beam Length(m) Moment
(kN-m)
G-B2 6 192.456
G-B3 6 123.863
G-B2 6 192.456
G-B1 6 192.456
G-B1 6 192.456
G-B1 6 192.456
Max
GIRDER Length(m) Moment
(kN-m)
G-G1 6 75.284
G-G2 3 106.568
G-G3 6 157.697
G-G1 6 106.671
G-G2 3 95.476
G-G4 6 68.31
G-G5 3 83.746
G-G6 6 85.32
G-G4 6 86.735
G-G5 3 78.795
G-G7 6 74.674
G-G8 3 93.059
G-G7 6 70.07
G-G7 6 71.898
G-G8 3 95.212
G-G9 6 72.796
G-G10 6 129.199
G-G11 6 62.568
G-G12 6 78.184
G-G10 6 129.152
35
G-G9 6 72.636
G-G13 6 72.857
G-G14 6 129.279
G-G15 6 129.751
G-G15 6 129.972
G-G14 6 129.384
G-G13 6 72.686
Moment Actual,
Where
∑ kips
{ ⁄
{ ⁄
Where
NOTE: See NSCP 2010 509.3.2.c Strength of Composite Beams with Formed Steel
Deck
Moment Actual,
Check adequacy:
Where
(AISC Part 3 Table 3-21 (p). 3-207)
⁄
41
4.2.2.1 Summary
Table 11. Summary of Composite Section and No. of Studs
No. Of
Beam Section tf(in) 0.25tf 0.25tf
stud
R-B1 W16x26 5.5 1.375 0.75 46
R-B2 W12x14 3.97 0.9925 0.75 26
R-B1 W12x19 4.01 1.0025 0.75 34
R-B1 W12x19 4.01 1.0025 0.75 34
R-B1 W12x19 4.01 1.0025 0.75 34
R-B1 W12x19 4.01 1.0025 0.75 34
No. Of
Girder Section tf(in) 0.25tf 0.25tf
stud
R-G1 W10x12 3.96 0.99 0.75 22
R-G2 W10x12 3.96 0.99 0.75 22
R-G3 W12x19 4.01 1.0025 0.75 34
R-G1 W10x15 4 1 0.75 26
R-G2 W10x12 3.96 0.99 0.75 22
R-G1 W10x12 3.96 0.99 0.75 22
R-G2 W10x12 3.96 0.99 0.75 22
R-G4 W10x12 3.96 0.99 0.75 22
R-G1 W10x12 3.96 0.99 0.75 22
R-G2 W10x12 3.96 0.99 0.75 22
R-G1 W10x12 3.96 0.99 0.75 22
R-G2 W10x12 3.96 0.99 0.75 22
R-G1 W10x12 3.96 0.99 0.75 22
R-G1 W10x12 3.96 0.99 0.75 22
R-G2 W10x12 3.96 0.99 0.75 22
R-G5 W10x12 3.96 0.99 0.75 22
R-G6 W10x15 4 1 0.75 26
R-G7 W10x12 3.96 0.99 0.75 22
R-G8 W10x12 3.96 0.99 0.75 22
R-G6 W10x15 4 1 0.75 26
R-G5 W10x12 3.96 0.99 0.75 22
R-G5 W10x12 3.96 0.99 0.75 22
R-G6 W10x15 4 1 0.75 26
R-G9 W10x17 4.01 1.0025 0.75 30
R-G9 W10x17 4.01 1.0025 0.75 30
R-G6 W10x17 4.01 1.0025 0.75 30
R-G5 W10x12 3.96 0.99 0.75 22
42
No. Of
Beam Section tf(in) 0.25tf d(stud)
stud
4-B2 W16x26 5.5 1.375 0.75 46
4-B4 W12x19 4.01 1.0025 0.75 34
4-B3 W33x118 11.5 2.875 0.75 52
4-B1 W10x22 5.75 1.4375 0.75 38
4-B1 W10x22 5.75 1.4375 0.75 38
4-B1 W10x22 5.75 1.4375 0.75 38
No. Of
Girder Section tf(in) 0.25tf d(stud)
stud
No. Of
Beam Section tf(in) 0.25tf d(stud)
stud
No. Of
Beam Section tf(in) 0.25tf d(stud)
stud
2-B2 W16x26 5.5 1.375 0.75 46
2-B3 W12x19 4.01 1.0025 0.75 34
2-B2 W16x26 5.5 1.375 0.75 46
2-B1 W10x22 5.75 1.4375 0.75 38
2-B1 W10x22 5.75 1.4375 0.75 38
2-B1 W10x22 5.75 1.4375 0.75 38
No. Of
Girder Section tf(in) 0.25tf d(stud)
stud
2-G1 W10x15 4 1 0.75 26
2-G2 W10x15 4 1 0.75 26
2-G3 W10x22 5.75 1.4375 0.75 38
2-G1 W10x17 4.01 1.0025 0.75 30
2-G2 W10x15 4 1 0.75 26
2-G4 W10x12 3.96 0.99 0.75 22
2-G5 W10x15 4 1 0.75 26
2-G6 W10x15 4 1 0.75 26
2-G4 W10x15 4 1 0.75 26
2-G5 W10x15 4 1 0.75 26
2-G7 W10x12 3.96 0.99 0.75 22
2-G8 W10x15 4 1 0.75 26
2-G7 W10x12 3.96 0.99 0.75 22
2-G7 W10x12 3.96 0.99 0.75 22
2-G8 W10x15 4 1 0.75 26
2-G9 W10x15 4 1 0.75 26
2-G10 W12x19 4.01 1.0025 0.75 34
2-G11 W10x12 3.96 0.99 0.75 22
2-G12 W10x12 3.96 0.99 0.75 22
2-G10 W12x19 4.01 1.0025 0.75 34
2-G9 W10x15 4 1 0.75 26
2-G13 W10x12 3.96 0.99 0.75 22
2-G14 W12x16 3.99 0.9975 0.75 28
2-G15 W12x16 3.99 0.9975 0.75 28
2-G15 W12x16 3.99 0.9975 0.75 28
2-G14 W12x16 3.99 0.9975 0.75 28
2-G13 W10x12 3.96 0.99 0.75 22
45
No. Of
Beam Section tf(in) 0.25tf d(stud)
stud
No. Of
Girder Section tf(in) 0.25tf d(stud)
stud
Using STAAD Pro 2007 v7i, the maximum moment and axial force loaded on the column were
computed. The values calculated per floor are shown below.
Max Max
Max Max Max Axial
Axial Shear Max Shear
Column Length(m) Moment Moment Force
Force Force Force (kip)
(kN-m) (kip-ft) (kip)
(kN) (kN)
4-C1 3 235.37 207.48 105.80 173.60 46.64 23.79
= 0.5(3)
= 1.5 m ≈ 4.94 ft
= 0.5(3)
= 1.5 m ≈ 4.94 ft
47
= 0.5(3)
= 1.5 m ≈ 4.94 ft
= 0.5(4)
= 2 m ≈ 6.58 ft
= 0.5(3)
= 1.5 m ≈ 4.94 ft
Determine the required composite column size from AISC Table 4-17
For 1-C1
HSS 18.000x
[ ]
[ ]
48
The same procedure of determining the required composite column size applies to other columns
per floor. See sample table below.
49
4.2.3.1 Summary
Pipe
Column Pipe Section Diameter
(kip-ft) (kip) (kip)
(in)
4-C1 HSS 18.000x 18 1440 450 95.5
4-C2 HSS 18.000x 18 1440 450 95.5
3-C1 HSS 18.000x 18 1440 450 95.5
3-C2 HSS 18.000x 18 1440 450 95.5
2-C1 HSS 18.000x 18 1440 450 95.5
2-C2 HSS 18.000x 18 1440 450 95.5
1-C1 HSS 18.000x 18 1440 450 95.5
1-C2 HSS 18.000x 18 1440 450 95.5
B-C1 HSS 18.000x 18 1440 450 95.5
B-C2 HSS 18.000x 18 1440 450 95.5
Governing pipe section for C1 & C2:
HSS 18.000x
Fy Fu D(in) t(in)
HSS 18.000x 46 ksi 62 ksi 18 0.465
√
50
Therefore, use
of steel section
( )
Connection No. 1
Figure 9. Roof Deck Framing Plan Showing Connection No. 1 (RD-A1) at Roof Deck
HSS 18.000x
Strength:
Ductility: =
Slenderness: √ √
Obtain the available single plate connection strength from Manual Table 10-9
Table 18. AISC Manual Table 10-9a Single Plate Connections
55
Use
From table,
Thus,
Calculate the available beam web bearing strength from Manual Table 10-1
Table 20. AISC Manual Table 10-1 Double Angle Connections
4.2.4.1.2 Summary
Table 21a. Summary of Girder to Column Single Plate Connection at Roof Deck
Weld
Force Single Plate No. of
No. Beam Column Bolt Size
(kN) Size Bolts
(in.)
W10x12 HSS 4.133 ¾ in. 2 3/16
RD-A1
W10x12 18.000x 50.551 ¾ in. 2 3/16
W10x12 15.646 ¾ in. 2 3/16
HSS
RD-B1 W10x15 72.594 ¾ in. 2 3/16
18.000x
W10x12 18.137 ¾ in. 2 3/16
W12x19 88.636 ¾ in. 2 3/16
HSS
RD-C1 W10x12 43.981 ¾ in. 2 3/16
18.000x
W10x12 29.128 ¾ in. 2 3/16
W10x12 29.958 ¾ in. 2 3/16
HSS
RD-D1 W10x12 44.033 ¾ in. 2 3/16
18.000x
W10x12 89.291 ¾ in. 2 3/16
W10x12 18.889 ¾ in. 2 3/16
HSS
RD-E1 W10x17 72.616 ¾ in. 2 3/16
18.000x
W10x12 29.910 ¾ in. 2 3/16
W10x12 HSS 50.653 ¾ in. 2 3/16
RD-F1
W10x12 18.000x 19.674 ¾ in. 2 3/16
W10x12 6.426 ¾ in. 2 3/16
HSS
RD-A2 W10x12 50.222 ¾ in. 2 3/16
18.000x
W10x12 50.244 ¾ in. 2 3/16
W10x12 8.709 ¾ in. 2 3/16
W10x15 HSS 71.929 ¾ in. 2 3/16
RD-B2
W10x12 18.000x 6.426 ¾ in. 2 3/16
W10x15 71.989 ¾ in. 2 3/16
W10x12 25.477 ¾ in. 2 3/16
W10x12 HSS 71.557 ¾ in. 2 3/16
RD-C2
W10x12 18.000x 15.647 ¾ in. 2 3/16
W10x12 39.957 ¾ in. 2 3/16
59
Table 21b. Summary of Girder to Column Single Plate Connection at Fourth Floor
Weld
Force Single Plate Bol No. of
No. Beam Column Size
(kN) Size t Bolts
(in.)
W10x12 HSS 30.371 ¾ in. 2 3/16
4-A1
W10x12 18.000x 81.229 ¾ in. 2 3/16
W10x12 29.349 ¾ in. 2 3/16
HSS
4-B1 W10x22 146.254 ¾ in. 3 1/4
18.000x
W10x12 29.396 ¾ in. 2 3/16
W10x12 81.053 ¾ in. 2 3/16
HSS
4-C1 W10x12 53.270 ¾ in. 2 3/16
18.000x
W10x15 43.828 ¾ in. 2 3/16
W10x15 23.004 ¾ in. 2 3/16
HSS
4-D1 W10x12 52.293 ¾ in. 2 3/16
18.000x
W10x12 81.835 ¾ in. 2 3/16
W10x12 28.079 ¾ in. 2 3/16
HSS
4-E1 W16x26 114.476 ¾ in. 2 3/16
18.000x
W10x12 23.004 ¾ in. 2 3/16
W10x17 HSS 66.309 ¾ in. 2 3/16
4-F1
W10x12 18.000x 28.989 ¾ in. 2 3/16
W10x12 26.389 ¾ in. 2 3/16
HSS
4-A2 W10x12 18.000x
57.353 ¾ in. 2 3/16
W10x15 80.879 ¾ in. 2 3/16
W10x12 25.640 ¾ in. 2 3/16
W12x16 HSS 93.089 ¾ in. 2 3/16
4-B2
W10x12 18.000x 24.007 ¾ in. 2 3/16
W10x22 44.914 ¾ in. 2 3/16
W10x12 45.828 ¾ in. 2 3/16
W12x16 HSS 92.754 ¾ in. 2 3/16
4-C2
W10x12 18.000x 36.088 ¾ in. 2 3/16
W10x12 73.335 ¾ in. 2 3/16
W10x12 HSS 26.466 ¾ in. 2 3/16
4-D2
W12x16 18.000x 92.865 ¾ in. 2 3/16
61
Table 21c. Summary of Girder to Column Single Plate Connection at Third Floor
Weld
Force Single Plate No. of
No. Beam Column Bolt Size
(kN) Size Bolts
(in.)
W10x12 HSS 41.557 ¾ in. 2 3/16
3-A1
W10x12 18.000x 66.209 ¾ in. 2 3/16
W10x12 23.651 ¾ in. 2 3/16
HSS
3-B1 W12x16 114.396 ¾ in. 2 3/16
18.000x
W10x12 40.768 ¾ in. 2 3/16
W10x12 92.561 ¾ in. 2 3/16
HSS
3-C1 W10x12 53.374 ¾ in. 2 3/16
18.000x
W10x12 47.758 ¾ in. 2 3/16
W10x12 44.533 ¾ in. 2 3/16
HSS
3-D1 W10x12 52.13 ¾ in. 2 3/16
18.000x
W10x12 93.321 ¾ in. 2 3/16
W10x12 30.888 ¾ in. 2 3/16
HSS
3-E1 W12x16 114.927 ¾ in. 2 3/16
18.000x
W10x12 45.817 ¾ in. 2 3/16
W10x17 HSS 66.3 ¾ in. 2 3/16
3-F1
W10x12 18.000x 31.697 ¾ in. 2 3/16
W10x12 36.406 ¾ in. 2 3/16
HSS
3-A2 W10x12 18.000x
57.368 ¾ in. 2 3/16
W10x12 65.938 ¾ in. 2 3/16
W10x12 26.958 ¾ in. 2 3/16
W12x16 HSS 93.136 ¾ in. 2 3/16
3-B2
W10x12 18.000x 34.386 ¾ in. 2 3/16
W12x16 113.412 ¾ in. 2 3/16
W10x12 48.966 ¾ in. 2 3/16
W10x12 HSS 92.827 ¾ in. 2 3/16
3-C2
W10x12 18.000x 39.265 ¾ in. 2 3/16
W10x12 73.623 ¾ in. 2 3/16
W10x12 HSS 40.28 ¾ in. 2 3/16
3-D2
W12x16 18.000x 92.931 ¾ in. 2 3/16
63
Table 21d. Summary of Girder Column Single Plate Connection at Second Floor
Weld
Force Single Plate No. of
No. Beam Column Bolt Size
(kN) Size Bolts
(in.)
W10x12 54.902 ¾ in. 2 3/16
2-A1 HSS 18.000x
W10x12 66.209 ¾ in. 2 3/16
W10x12 33.183 ¾ in. 2 3/16
2-B1 W12x16 HSS 18.000x 114.386 ¾ in. 2 3/16
W10x12 54.497 ¾ in. 2 3/16
W10x12 97.161 ¾ in. 2 3/16
2-C1 W10x12 HSS 18.000x 53.374 ¾ in. 2 3/16
W10x12 53.837 ¾ in. 2 3/16
W10x12 58.293 ¾ in. 2 3/16
2-D1 W10x12 HSS 18.000x 52.13 ¾ in. 2 3/16
W10x12 97.796 ¾ in. 2 3/16
W10x12 34.23 ¾ in. 2 3/16
2-E1 W12x16 HSS 18.000x 114.927 ¾ in. 2 3/16
W10x12 59.37 ¾ in. 2 3/16
W10x17 66.3 ¾ in. 2 3/16
2-F1 HSS 18.000x
W10x12 34.806 ¾ in. 2 3/16
W10x12 48.927 ¾ in. 2 3/16
2-A2 W10x12 HSS 18.000x 57.368 ¾ in. 2 3/16
W10x12 65.938 ¾ in. 2 3/16
W10x12 29.28 ¾ in. 2 3/16
W12x16 93.136 ¾ in. 2 3/16
2-B2 HSS 18.000x
W10x12 47.497 ¾ in. 2 3/16
W12x16 113.412 ¾ in. 2 3/16
W10x12 52.802 ¾ in. 2 3/16
W10x12 92.827 ¾ in. 2 3/16
2-C2 HSS 18.000x
W10x12 44.04 ¾ in. 2 3/16
W10x12 73.623 ¾ in. 2 3/16
W10x12 49.202 ¾ in. 2 3/16
2-D2 HSS 18.000x
W12x16 92.931 ¾ in. 2 3/16
65
Table 21e. Summary of Beam to Column Single Plate Connection at Ground Floor
Weld
Force Single Plate No. of
No. Beam Column Bolt Size
(KN) Size Bolts
(in.)
W10x12 HSS 69.491 ¾ in. 2 3/16
GF-A1
W10x15 18.000x 72.488 ¾ in. 2 3/16
W10x12 37.414 ¾ in. 2 3/16
HSS
GF-B1 W10x22 128.587 ¾ in. 2 3/16
18.000x
W10x12 70.697 ¾ in. 2 3/16
W10x12 109.901 ¾ in. 2 3/16
HSS
GF-C1 W10x15 58.392 ¾ in. 2 3/16
18.000x
W10x15 62.391 ¾ in. 2 3/16
W10x12 76.195 ¾ in. 2 3/16
HSS
GF-D1 W12x14 56.419 ¾ in. 2 3/16
18.000x
W10x12 109.998 ¾ in. 2 3/16
W10x12 39.237 ¾ in. 2 3/16
HSS
GF-E1 W10x22 128.603 ¾ in. 2 3/16
18.000x
W10x12 77.299 ¾ in. 2 3/16
W10x15 HSS 72.541 ¾ in. 2 3/16
GF-F1
W10x12 18.000x 39.077 ¾ in. 2 3/16
W10x12 57.548 ¾ in. 2 3/16
HSS
GF-A2 W10x12 18.000x
72.323 ¾ in. 2 3/16
W10x15 72.34 ¾ in. 2 3/16
W12x14 31.845 ¾ in. 2 3/16
W10x22 HSS 127.944 ¾ in. 2 3/16
GF-B2
W10x15 18.000x 58.846 ¾ in. 2 3/16
W10x22 128.587 ¾ in. 2 3/16
W10x17 59.194 ¾ in. 2 3/16
W10x12 HSS 127.748 ¾ in. 2 3/16
GF-C2
W12x14 18.000x 50.512 ¾ in. 2 3/16
W10x15 92.36 ¾ in. 2 3/16
W12x14 HSS 59.416 ¾ in. 2 3/16
GF-D2
W10x22 18.000x 127.22 ¾ in. 2 3/16
67
Connection No. 1
1 8
4 5
3
2 9
6
3
3 7 10
3
Figure 11. Roof Deck Framing Plan showing Connection No. 1 at Roof Deck
Using LRFD
Obtain the available single plate connection strength from Manual Table 10-9
Use
n = 3,
70
4.2.4.2.1 Summary
C=0
t = 0.40 m
Earth Pressure
Forces:
75
Maximum Moment:
( ( ) ( ))
( ( )( ))
( ( )( ))
Thickness:
Say
Say t = 300 mm
W4
W2
W3
W1
O
W5
Computation:
Weight:
Centroid:
( ) ( )
78
( )
( )
79
( )
( ) ( )
( )
( )
Then,
( )
Passive Pressure
80
81
72.355
40.3680
27.840 24.95
Pressure 1 (rectangle)
Presuure 2 (Triangle)
82
Forces
Moment
( ) ( )
( ) ( )
( ( )( ))
( ( )( ))
Area of steel
Vertical bars
Let
84
Spacing
Horizontal Bars
Let
Number of bars
Spacing of bars
Number of bars
85
Spacing of bars
Design of Heel
( ) ( )
( )
Development length
√
86
Spacing of bars
( )
( )
Width
Depth
87
Area of steel
88
Spacing
89
1.25
49.5427
W1
W2
35.0136
( ) ( )
( )
√
90
Number of bars
91
Area of steel
Spacing
92
Ultimate
Initial
Column Total Axial Factored Soil
No. Dimension,
Pipe Ø Load, P Load, Pult Pressure,
B
qult
in mm kN kN kPa
1 8.63 2000 680.813 701.131 89.88859
2 8.63 3000 901.800 914.395 87.9226
3 8.63 3000 760.001 779.237 89.56747
4 8.63 3000 1024.723 1044.93 89.31026
5 8.63 3000 979.952 978.384 87.35571
6 8.63 2000 386.338 395.962 89.99136
7 8.63 3000 1142.853 1189.263 90.09568
8 10.8 5000 1507.816 1540.944 88.05394
9 10.8 5000 1815.571 1849.692 86.23273
10 10.8 4000 2287.509 2329.022 86.90381
11 10.8 5000 1553.002 1571.412 87.30067
12 8.63 3000 656.798 684.727 91.29693
13 8.63 3000 607.327 655.203 94.95696
14 8.63 3000 849.168 902.793 90.2793
15 8.63 3000 834.835 888.430 93.51895
16 8.63 3000 1159.633 1228.934 91.03215
17 8.63 3000 823.561 875.743 91.22323
18 8.63 2000 326.096 358.384 94.31158
Concrete strength,
Steel strength,
Depth of Footing
Design Computation
Pipe
104
Thickness,
( )
Size of Footing
imum
One-Way Shear
√ = 1230.7 kN
Two-Way Shear
√ = 1705.9 kN
Number of bars
106
Distribution of bars
Development Length
Spacing
4.2.7.3 Summary
Table 27. Summary of Footings
mm kPa m kPa mm mm
1 600 88.2 3.9 89.88859 495 515
2 600 88.2 2.6 87.9226 495 515
3 600 88.2 2.9 89.56747 495 515
4 600 88.2 3.9 89.31026 495 515
5 600 88.2 2.8 87.35571 495 515
6 400 89.6 2.2 89.99136 295 315
7 700 87.5 4.4 90.09568 595 615
8 800 86.8 2.5 88.05394 695 715
9 800 86.8 3.3 86.23273 695 715
10 900 86.1 6.7 86.90381 795 815
11 800 86.8 3 87.30067 695 715
12 500 88.9 2.5 91.29693 395 415
13 500 88.9 2.3 94.95696 395 415
14 600 88.2 2.5 90.2793 495 515
15 600 88.2 1.9 93.51895 495 515
16 700 87.5 4.5 91.03215 595 615
17 600 88.2 3.2 91.22323 495 515
18 400 89.6 1.9 94.31158 295 315
One-Way Shear
No. xshort ØVc qult Vult
kN kPa kN
1 0.902869 1230.694 89.88859 142.9847
2 1.202869 1262.25 87.9226 248.9506
3 1.352869 946.6875 89.56747 230.5114
4 1.402869 1230.694 89.31026 316.2197
5 1.302869 1262.25 87.35571 282.2878
6 0.902869 413.7375 89.99136 120.3464
7 1.402869 1668.975 90.09568 320.2561
8 1.128445 3101.438 88.05394 267.1659
9 1.528445 2879.906 86.23273 467.1566
10 1.878445 3395.644 86.90381 630.8419
11 1.378445 2658.375 87.30067 357.9913
12 1.152869 755.4375 91.29693 207.5732
108
Two-Way Shear
for
No. xshort Vult ØVc Qult Mult Remarks
circular
m m kN kN kN kN-m
1 0.689263 0.902869 658.4265 1705.925 89.88859 142.8856 compliant
No. xshort Mu Ru As N
kN-m Mpa mm2 bars
1 1.852869 308.5985 0.646408 0.002387 0.005091 0.033779 0.005091 5243.636 17
across
across
N center center Minimum
No. outer Ld
band band Ld
strip
width
bars bars mm mm
1.95 21.69492 22 5 827.8686
1 346 ok
1.538462 26 26 4 1127.869
2 346 ok
Since the base plate is resting on full area of the concrete support,
113
√ √
√
114
4.2.8.1 Summary
With the use of STAAD Pro 2007 v7i, the reinforcement bars needed for the footing tie
beams were computed. The structure of the building is shown below.
Considering two footing tie beams as examples from the blue group, the results are
shown below:
Figure 20a. Results from STAAD Pro 2007 v7i: FTB 659
117
Figure 20b. Results from STAAD Pro 2007 v7i: FTB 660
118
http://kidlat.pagasa.dost.gov.ph/cab/cab.htm
Sample Computation:
Number of Tanks
Maximum of 7 tanks can be used in the collection of rainwater but since the tanks should
only occupy a certain area in the basement due to parking purposes, 4 tanks will be
placed, instead. A sample rainwater tank is given below:
To achieve the appropriate design for the project the correct data analysis of the
soil investigation should be performed. Soil investigation is important to determine the
soil condition of the project location which is important in designing and constructing the
foundation of the structure. It also provides an evaluation of the general sustainability and
economical design that should be considered for the benefit of the project. It also allows a
distinct precaution of what may occur during construction and the effects of it to nearby
properties and locations.
In accordance with the soil investigation report, the proceedings performed were
as follows: soil borings at the locations of structure, geotechnical laboratory testing and
geotechnical engineering report. The investigation was conducted in accordance with the
procedures recommended by the American Society for Testing and Materials (ASTM).
Field tests and laboratory Tests were conducted. Subsurface conditions at the site were
explored by drilling three test borings. The test used during the subsurface investigation
is the Standard Penetration Test (SPT) carried out in accordance with ASTM D1586 in
the test hole. The test involves driving standard split-spoom sampler into the bottom of a
borehole with repeated blows of a 63.5-kg hammer dropped 450 mm. The penetration
resistance is recorded as the number of hammer blows required to achieve a penetration
of 300 mm after the initial penetration of 150 mm. If the penetration depth is less than
300 mm and the blows count is more than 50, or if the sampler fails to advance during 10
consecutive blows, then the value is considered as “Refusal”. In addition, the laboratory
test served to determine index values for identification and correlation, further refining
the geological model of the site.
For discussion purposes in our research paper, we prioritized the important phases
of soil investigation that should be used. And these are the following: Phase 1: Analysis
of the provided information with regard to the site location, the site plan, the type of
structure to be used, the loading conditions to be used, the geotechnical report provided
of the site, and the topographic map of the site. In accordance with the given geotechnical
report, we were able to distinguish the type of soil the location has and how we could
142
comply with the appropriate design for its foundation. The target is to take into account
the lab equipments that the hospital would likely to have which would highly affect the
design investigation.
Phase 2: Visitation of the site location. The general outlook of the project location
is important to be able to gauge the probable results of the design that we will conduct.
The current condition upon perceiving the site would give us an evaluation of how the
construction will be performed. To comply with this action, the whole group visited the
site and had a video of the whole location. The actual site is only behind the current
Mandaluyong Maternity Hospital, along the borders of the lot, residences where present,
and at the right side separated by a street is a school. There is also an animal shelter and a
police station at the left side. Upon taking all of this into account, it is mandatory to take
it into consideration the proximity of the possible affected areas during construction. We
were able to visualize the procedure and the design that should be done.
And lastly Phase 3: Detailed soil investigation of the site. The geographical
structure of the site, groundwater condition, and the soil sample should be determined.
These components would be used to obtain the necessary results for the situ test. Since
the planning department of the Mandaluyong local government has already provided us
with a full report of the geotechnical investigation. The data for our design procedure was
already handed to us. And we were able to make use of it to start with the design analysis.
For the summary of the procedures done on the site, the following processes will
be conducted: First is site preparation. Site preparation involves staking out of the site.
The site location would be surveyed and marked out for the location’s boundary lines.
The topographical heights of the site would also be determined. It is followed by clearing
of the site. Obstruction on the location would then be removed, allowing space for the
equipments, materials and machinery that is to be used for the construction. Then for the
last step for the site preparation would be excavation. This is for the foundation
construction and design.
Second is the construction. Substructure components are then built for the
beginnings of the whole structure. This includes the footing that is to be built for the
foundation of the building. Superstructures that are in relation with the substructure
would also then be built. These are the slab on grade, the beams and the columns and for
our case there would also be a retaining wall. After these procedures the water and sewer
line would then be constructed on the ground level, as well as the inspection for any
causes of future disruption on the structure.
For this project, we used isolated footing. The structure rises 4 m from the ground
and 12 m from the second level to the roof deck, having a 3 m height per level.
According to the soil report that was given to us by the City Planning and Development
Office of Mandaluyong City, the soil in the area has a net allowable soil bearing capacity
of 150 Kpa for 2 meters deep bore hole. In detail, compressible soils such as clays, the
borings should penetrate either 1.5 to 2 times the least dimensions of the foundation or
until the stress increment due to the foundation loads is less than 10 %, whichever is
143
greater. Borings should penetrate at least 1 meter into the rock. In very stiff clays, borings
should penetrate 5 meters to 7 meters to prove that the thickness of the strata is enough
and adequate.
For the design, we used the 28th day compressive strength of concrete of 25 MPa,
yield strength of reinforcing steel of 275 MPa, an allowable soil bearing capacity of 150
kPa, a diameter of steel reinforcing bar of 20 mm, and a minimum concrete cover of 75
mm. According to the National Structural Code of the Philippines which states that if the
concrete is casted against and permanently exposed to earth, a concrete cover of 75 mm
should be used.
For the punching shear of the footings, concrete specifications such as its strength,
ratio of flexural reinforcement, type of anchorage of the reinforcement, and the type of
shear reinforcement were considered. The concrete strength showed a vital effect to the
punching shear strength while the influence of the ratio of flexural reinforcement only
slightly affects it. The type of anchorage has no influence on it. The use of inclined bent-
up bars as shear reinforcement gave higher punching shear strengths than the use of
stirrups. The resistance to the transverse effects of concentrated forces acting on concrete
slabs is an essential problem in design of column footings, flat plates and bridge slabs.
The design methods should be based on physical models, which in a relevant way
describe the behaviour of the structure and consider the mechanical properties of the
materials. For the beam shear, the resistance to the transverse effects of concentrated
forces acting on concrete slabs is an essential problem in design of column footings, flat
plates and bridge slabs. The design methods should be based on physical models, which
in a relevant way describe the behaviour of the structure.
144
The Earth seems to be unique among the other known celestial bodies. It has
water, which covers three-fourths of its surface and constitutes 60-70 wt % of the living
world. Water regenerates and is redistributed through evaporation, making it seem
endlessly renewable.
Actually, only 1% of the world's water is usable to us. About 97% is salty sea
water, and 2% is frozen in glaciers and polar ice caps. Thus that 1% of the world's
water supply is a precious commodity necessary for our survival. A growing world
population, unrelenting urbanization, increasing scarcity of good quality water
resources and rising fertilizer prices are the driving forces behind the accelerating
upward trend in the use of wastewater, excreta and grey water for agriculture and
aquaculture.
Around 1 billion people globally do not have access to improved water supply
sources whereas 2.4 billion people do not have access to any type of improved
sanitation facility. About 2 million people die every year due to diarrhoeal diseases,
most of them are children less than 5 years of age. The most affected are the
populations in developing countries, living in extreme conditions of poverty, normally
peri-urban dwellers or rural inhabitants.
The rainwater collected from the roof deck of the hospital is transferred to
a storage tank at the basement of the building by connecting down-pipes to the
gutter. It is then pumped through a system of basic water treatment and storage.
Filtered rainwater can be either connected directly to supply distribution line or
kept in a holding tank that stores the water for intended use.
The average annual rainfall in Mandaluyong is 164.7825 mm. It is during between the
months of June and October that the system can collect a large amount of rain water. The
tank has a 2 meter-diameter and has a capacity of 5400 Liters. The lowest volume of
water that can be collected is 2.34 cubic meters (February) and the highest volume can be
up to 93.05 cubic meters (July). Maximum of 7 tanks can be used in the collection of
rainwater but since the tanks should only occupy a certain area in the basement due to
parking purposes, 4 tanks will be placed, instead.
The water collected by a rain water harvesting system that is then treated, can be
used to wash laundry and dishes, to bathe with and to use in toilets. The group has only
146
shown in this paper a rough design of the rain harvesting system’s tank and schematic
diagram. Thus, the water produced by the said proposed system is not properly treated
and if it is not purified, then it is not potable.
If the water is not tested for quality, it can be a dangerous source of both chemical
pollutants as well as coli form and other bacteria, and can be a serious health hazard to
staff as well as the patients. To maintain cleanliness and safety of water consumption,
hospital engineering services must test the quality of water obtained from the source
initially and at fixed annually for chemical and bacterial content and to ascertain the
treatment required to render it fit for human consumption.
Further, it must again be tested periodically at the user’s end (different departments and
wards) to confirm the adequacy of treatment and portability of water. A record of the
test reports and treatment given should be maintained.
147
(Minimum Design Dead Loads) in Section 204 of the National Structural Code of the
Philippines 2010. In accordance with the National Structural Code of the Philippines
2010, live loads are those loads produced by the use and occupancy of the building or
other structure and do not include dead load, construction load, or environmental loads
such as wind load, earthquake load and fluid load. Based on the values indicated under
Table 205-1 (Minimum Uniform and Concentrated Live Loads) in Section 205 of the
National Structural Code of the Philippines. Lastly, earthquake load is the application of
an earthquake-generated agitation to a structure. It happens at contact surfaces of a
structure either with the ground, or with adjacent structures, or with gravity waves from
tsunami. In structural design, it is important to consider earthquake provisions. For these
ensure the safety of the occupants and the structure itself. National Structural Code of the
Philippines, Section 208 and Uniform Building Code 1992 are the basis for computing
the earthquake loads.
In reference with the National Structural Code of the Philippines 2010, it is stated
that buildings, towers and other vertical structures and all portions thereof shall be
designed to resist the load combinations specified in Section 203.3 or 203.4 and the
special seismic load combinations of Section 203.5. For the design process it should be
considered that the most critical effect can occur when one or more of the contributing
loads are not acting and all applicable loads shall be considered in accordance with the
specified load combinations. Basic load combinations values indicated under Section
203.3.1 and the alternate basic load combinations under Section 203.4.2 of the National
Structural Code of the Philippines 2010 are used for the strength design computations.
The design project uses a steel-concrete composite structure. Composite action is
developed when two load carrying structural members are integrally connected and
deflect as a single unit. Concrete is stronger in compression than in tension, and steel is
susceptible to buckling in compression. By the composite action between the two, their
respective advantages can be utilized to the fullest extent.
For the beam design, steel beams were used. It is made composite by using shear
connectors, composite metal decking and concrete thus needing acting moments for its
computation. From the STAAD model, the load and specifications are used to compute
for the frame analysis of the structure where the acting moments are computed by the
program needed for the composite steel beam design. In the case of a composite beam the
action of the steel beam and the slab is similar to that of a monolithic Tee beam.
On the other hand, the column design used for the structure is a concrete filled
column. Concrete-Filled Steel Tubes (CFTs) are composite member consisting of a steel
tube filled with concrete. The CFT structural member has a number of distinct advantages
over an equivalent steel, reinforced concrete, or steel-reinforced concrete member. The
orientation of the steel and concrete in the cross section optimizes the strength and
stiffness of the section. The steel lies at the outer perimeter where it performs most
effectively in tension and in resisting bending moment. Also, the stiffness of the CFT is
greatly enhanced because the steel, which has a much greater modulus of elasticity than
the concrete, is situated farthest from the centroid, where it makes the greatest
contribution to the moment of inertia. The concrete forms an ideal core to withstand the
compressive loading in typical applications, and it delays and often prevents local
149
buckling of the steel. Additionally, it has been shown that the steel tube confines the
concrete core, which increases the compressive strength for circular CFTs. Therefore, it
is most advantageous to use CFTs for the columns subjected to the large compressive
loading. In contrast to reinforced concrete columns with transverse reinforcement, the
steel tube also prevents spalling of the concrete and minimizes congestion of
reinforcement in the connection region, particularly for seismic design.
Connections of structural members are extremely important as they could be the
weak link in any structural system. Composite connections resist moment by generating a
couple between their tension and compression components. The mechanics are
essentially the same as those for bare steel moment connections, with the slab
reinforcement acting like an additional row of bolts in an extended end plate. In order to
achieve their full potential, the reinforcing bars must be properly anchored, and be
capable of accommodating significant strain before fracture. For this research, the design
of the single plate connection between a PIPE8STD column to a W10x12 girder web is to
support a beam end reaction of 346.38 MPa The top flange of the beam is considered to
be uncoped. 3/4 –in diameter ASTM A325-N bolts in standard holes and 70 ksi electrode
welds are also used.
The design moments of the beams and columns computation for the four-storey
medical center using encased steel-concrete composite structure are generated using
STAAD Pro 2007 v7i. Then, the STAAD results were transferred to Microsoft Excel for
computation and design of the specifications and dimensions of the beams, footing,
column and connections using manual analysis.
150
Beam
Section Span Shear Connector
Designation
R-B1 W16x26 6000 46 – 19.05mm Ø @ 120mm
R-B2 W12x14 6000 26 – 19.05mm Ø @ 240mm
R-G1 W10x12 6000 22 – 19.05mm Ø @ 280mm
R-G2 W10x12 3000 22 – 19.05mm Ø @ 140mm
R-G3 W12x19 6000 34 – 19.05mm Ø @ 160mm
R-G4 W10x12 6000 22 – 19.05mm Ø @ 280mm
R-G5 W10x12 6000 22 – 19.05mm Ø @ 280mm
R-G6 W10x15 6000 26 – 19.05mm Ø @ 240mm
R-G7 W10x12 6000 22 – 19.05mm Ø @ 280mm
R-G8 W10x12 6000 22 – 19.05mm Ø @ 280mm
R-G9 W10x17 6000 30 – 19.05mm Ø @ 180mm
Beam
Section Span Shear Connector
Designation
4-B2 W16x26 6000 46 – 19.05mm Ø @ 120mm
4-B4 W12x19 6000 34 – 19.05mm Ø @ 160mm
4-B3 W33x118 6000 52 – 19.05mm Ø @ 95mm
4-B1 W10x22 6000 38 – 19.05mm Ø @ 140mm
4-G1 W10x12 6000 22 – 19.05mm Ø @ 260mm
4-G2 W10x12 3000 22 – 19.05mm Ø @ 120mm
4-G3 W12x19 6000 34 – 19.05mm Ø @ 160mm
4-G4 W10x12 6000 22 – 19.05mm Ø @ 260mm
4-G5 W10x12 3000 22 – 19.05mm Ø @ 160mm
4-G6 W10x12 6000 22 – 19.05mm Ø @ 260mm
4-G7 W10x12 6000 22 – 19.05mm Ø @ 260mm
4-G8 W10x12 3000 22 – 19.05mm Ø @ 160mm
4-G9 W10x12 6000 22 – 19.05mm Ø @ 260mm
4-G10 W10x12 3000 22 – 19.05mm Ø @ 160mm
4-G11 W10x15 6000 26 – 19.05mm Ø @ 210mm
4-G12 W10x22 6000 38 – 19.05mm Ø @ 140mm
4-G13 W10x12 6000 22 – 19.05mm Ø @ 260mm
4-G14 W10x12 6000 22 – 19.05mm Ø @ 260mm
4-G15 W16x26 6000 46 – 19.05mm Ø @ 120mm
4-G16 W10x17 6000 30 – 19.05mm Ø @ 180mm
4-G17 W10x12 6000 22 – 19.05mm Ø @ 260mm
4-G18 W12x16 6000 28 – 19.05mm Ø @ 200mm
165
Beam
Section Span Shear Connector
Designation
3, 2-B2 W16x26 6000 46 – 19.05mm Ø @ 120mm
3, 2-B3 W12x19 6000 34 – 19.05mm Ø @ 160mm
3, 2-B2 W16x26 6000 46 – 19.05mm Ø @ 120mm
3, 2-B1 W10x22 6000 38 – 19.05mm Ø @ 140mm
3, 2-G1 W10x12 6000 22 – 19.05mm Ø @ 260mm
3, 2-G2 W10x12 3000 22 – 19.05mm Ø @ 120mm
3, 2-G3 W10x22 6000 38 – 19.05mm Ø @ 140mm
3, 2-G4 W10x12 6000 22 – 19.05mm Ø @ 260mm
3, 2-G5 W10x12 3000 22 – 19.05mm Ø @ 120mm
3, 2-G6 W10x15 6000 26 – 19.05mm Ø @ 210mm
3, 2-G7 W10x12 6000 22 – 19.05mm Ø @ 260mm
3, 2-G8 W10x12 3000 22 – 19.05mm Ø @ 120mm
3, 2-G9 W10x15 6000 22 – 19.05mm Ø @ 260mm
3, 2-G10 W12x16 6000 34 – 19.05mm Ø @ 160mm
3, 2-G11 W10x12 6000 22 – 19.05mm Ø @ 260mm
3, 2-G12 W10x12 6000 22 – 19.05mm Ø @ 260mm
3, 2-G13 W10x12 6000 22 – 19.05mm Ø @ 260mm
3, 2-G14 W12x16 6000 28 – 19.05mm Ø @ 200mm
3, 2-G15 W12x16 6000 28 – 19.05mm Ø @ 200mm
Beam
Section Span Shear Connector
Designation
G-B2 W33x118 6000 52 – 19.05mm Ø @ 95mm
G-B3 W10x22 6000 38 – 19.05mm Ø @ 140mm
G-B1 W33x118 6000 52 – 19.05mm Ø @ 95mm
G-G1 W10x15 6000 26 – 19.05mm Ø @ 210mm
G-G2 W10x22 6000 38 – 19.05mm Ø @ 140mm
G-G3 W16x26 3000 46 – 19.05mm Ø @ 120mm
G-G4 W10x15 6000 26 – 19.05mm Ø @ 210mm
G-G5 W12x14 6000 26 – 19.05mm Ø @ 210mm
G-G6 W10x17 3000 30 – 19.05mm Ø @ 80mm
G-G7 W10x15 6000 26 – 19.05mm Ø @ 210mm
G-G8 W12x16 6000 28 – 19.05mm Ø @ 200mm
G-G9 W10x15 3000 26 – 19.05mm Ø @ 210mm
G-G10 W10x22 6000 38 – 19.05mm Ø @ 140mm
166
Shear Connector
9
Beam
Girder
168
Vertical
Column Mark Type Size Spiral Ties
Reinforcement
C-1 HSS 18.000x 450mm 6- 16mm 12mm @75mm
C-2 HSS 18.000x 450mm 6- 16mm 12mm @75mm
Dx
BAR Y
COLUMN
(SEE SCHEDULE)
Dy
BAR X
173
COLUMN
d
(SEE SCHEDULE)
N.G.L
H
BAR Y
BAR X
t
174
In addition, the building is not just structurally safe but also eco-friendly and
aesthetically innovative. Solar window films and rainwater harvesting system were
incorporated to create a green innovative design. The solar window films both allow
natural day lighting and reduce heat into the building. By this, it keeps the area cool
enough for the patients and the staff. As for the rainwater harvesting system, it is
designed to be cylindrical in shape and to collect an average volume of 3796 Liters of
rain per month. This amount of volume is just enough to water plants and flush every
toilet in the building. Also, the purpose of these two green designs is not only to lessen
the hospital’s cost in electricity and water but to help conserve renewable resources, as
well.
177
Chapter 9: Recommendation
With the data presented in this project, it is evident that the design focuses mainly
in architectural and structural. Thus, the researchers would like to recommend having a
design of mechanical, electrical, plumbing and fire protection of the building and also its
budget estimate since it is no longer their field of expertise. It is also recommended to
have a professional civil engineer to the design the shear wall and the bracings for
columns at the ground floor and basement.
The innovation of this project includes the use of rainwater harvester but, does not
have a detailed design of the cistern. Hence, the researchers recommend having thorough
plan of the water storage tank and also, the treatment needed for the water to be used for
industrial purposes such as flushing and cleaning. The researchers also put forward to
design the pump to be used for the distribution of water in the cistern. To have a much
lower cost of construction materials and operation of the medical center, the group
recommends having a further study of alternative materials and to introduce LED light,
water-efficient toilet and others.
178
We would also like to acknowledge Engr. Comandao and Arch. Joseph Perfecto
Rea of the City Planning and Development of Mandaluyong City Government, the
beneficiary of this project, for their kindness and their hospitality especially in
accommodating us amidst their busy schedule.
Finally, we would like to thank our friends and family who never gets tired to
understand us in times of distress and to lend a hand willingly in times of need, asking
nothing in return. Your love and support surpasses all our hardships and for that we are
truly grateful.
179
American Institute of Steel Construction, Inc. Steel Construction Manual. 13th Edition.
2005
Arbi, G. S. and Pragasen, P., Study of optimum tilt angles for solar panels in different
latitudes for urban applications. Solar Energy Volume 86, Issue 6,: Elsevier Ltd, 2012
Christian, K.D.J. and Shatynski S.R,Thin film passive solar windows produced by
reactive evaporation of In-Sn. Thin Solid Films Volume 108, Issue 3: Elsevier Ltd. 1983
Cheng-Chih C., Jian-Ming Li, C.C. Weng. Experimental Behaviour and Strength of
Concrete-Encased Composite Beam–Columns with T-shaped Steel Section Under Cyclic
Loading. Department of Civil Engineering, National Chiao Tung University, Hsinchu,
30010, Taiwan: Elsevier Ltd, 2005
Cláudia A., Maria L. L., Ferdinando F., and Marino B. Users’ views of hospital
environmental quality: Validation of the Perceived Hospital Environment Quality
Indicators (PHEQI). Centre for Psychological Research & Social Intervention (CIS):
Elsevier Ltd., 2011
180
Dalke, H.Colour and lighting in hospital design. Colour Design Research Centre, London
South Bank University, Borough Road, London SE1 OAA, UK: Elsevier Ltd, 2005
Ellobody, E. and Young, B., Performance of axially restrained concrete encased steel
composite columns at elevated temperatures. Engineering Structures Volume 33, Issue 1:
Elsevier Ltd, 2011
Foque, R., and Lammineur, M. Introducing Human Scale in Hospital Design. Elsevier
Science Ltd: Printed in Great Britain, 1995
Monjur, M., and Yisong, Z. Healthcare providers’ perception of design factors related to
physical environments in hospitals, Building Energy Research Group, School of Civil
and Building Engineering, Loughborough University, Loughborough LE11 3TU, United
Kingdom: Elsevier Ltd, 2012
Mwenge, J.M., Rockström, J., Akpofure, E., and Dimes, J.. Rainwater harvesting to
enhance water productivity of rainfed agriculture in the semi-arid Zimbabwe, Physics
and Chemistry of the Earth, Parts A/B/CVolume 32, Issues 15–18, Mainstreaming
Integrated Water Resources Management in the Development Process, 2007
Rao, SKM. Designing Hospital for better Infection Control : an Experience. Department
of Hospital Administration, Armed Forces Medical College, Pune: MJAFI, 2004
Slonim, M.A. Transient processes in different types of solar cell panels. Experimental
investigation. Solar Energy Materials and Solar Cells Volume 90, Issue 15 : XIV
International Materials Research Congress, 2006
Weng, C.C and Yen, S.I. Comparisons of concrete-encased composite column strength
provisions of ACI code and AISC specification, Engineering Structures Volume 24, Issue
1: Elsevier Ltd, 2011
Wilson, A.P.R. and Ridgway, G.L. Reducing Hospital-Acquired Infection by Design: The
New University College London Hospital A.P.. University College London Hospitals,
London, UK: Published by Elsevier Ltd, 2005
Yin, R., Xu, P., and Shen, P.. Case study: Energy savings from solar window film in two
commercial buildings in Shanghai. Energy and Buildings Volume 45: Elsevier, 2012