PRESUPUESTO BASE VALORIZACION MENSUAL 01

AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL DEL MES AVANCA ACUMULADO ACTUAL SALDO ACTUAL
PARTIDA UND MET. C. UNITARIO PARCIAL Metrado Monto % Metrado Monto % Metrado Monto % Metrado Monto %
Obras Provisionales Glb. 1 15,000.00 15000 0 0 0 0.7 10500 70% 0.7 10500 70% 0.3 4500 30%
Excavaciones m3 1220.72 30.00 36621.6 0 0 0 924.788 27743.64 75.76% 924.788 27743.64 75.76% 295.932 8877.964 24.24%
Pavimentos de Concreto m2 15259 40.00 610360 0 0 0 7629.5 305180 50.00% 7629.5 305180 50.00% 7629.5 305180 50.00%
Juntas de Dilatacion ml 2034.533 5.00 10172.6667 0 0 0 0 0 0.00% 0 0 0.00% 2034.533 10172.667 100.00%
COSTO DIRECTO S/. 672154.267 0 343423.6364 343423.636 328730.63
GASTOS GENERALES Y UTILIDADES 25% 168038.567 0 85855.90909 85855.9091 82182.6576
PRESUPUESTO SUB TOTAL (S. IGV) S/. 840192.833 0 0% 429279.5455 51.09% 429279.545 51.09% 410913.288 48.91%

VALORIZACION MENSUAL 02

AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL DEL MES AVANCA ACUMULADO ACTUAL SALDO ACTUAL
PARTIDA UND MET. C. UNITARIO PARCIAL Metrado Monto % Metrado Monto % Metrado Monto % Metrado Monto %
Obras Provisionales Glb. 1 15,000.00 15000 0.7 10500 70.00% 0.3 4500 30% 1 15000 100.00%
Excavaciones m3 1220.72 30.00 36621.6 924.788 27743.64 75.76% 295.932121 8877.963636 24% 1220.72 36621.6 100.00%
Pavimentos de Concreto m2 15259 40.00 610360 7629.5 305180 50.00% 7629.5 305180 50% 15259 610360 100.00%
Juntas de Dilatacion ml 2034.533 5.00 10172.6667 0 0 0.00% 2034.53333 10172.66667 100% 2034.533 10172.6667 100.00%
COSTO DIRECTO S/. 672154.267 343423.636 328730.6303 672154.267
GASTOS GENERALES Y UTILIDADES 25% 168038.567 85855.9091 82182.65758 168038.567
PRESUPUESTO SUB TOTAL (S. IGV) S/. 840192.833 429279.545 51.09% 410913.2879 48.91% 840192.833 100.00%
840192.833

Avance fisico programado 46%

Avance fisico de obra 51% AP < Af

POR LO TANTO LA OBRA ESTA ADELANTADA