Contractor applies for Taking-Over

Certificate (S.CI. 10.1) Tests on Completion


- complete (CI. 9)
L I I
14 days max.

Contractor considers Works

w-
-
complete
Max.
1 28 days T
Engineer agrees Works complete Engineer fails to act
L

Works are substantially


Engineer issues Engineer rejects in accordance with
Taking-Over Certificate application with Contract
(S.CI. 10.1) reasons (S.CI. 10.1)

Taking-Over Certificate
Contractor completes Works deemed to have been
and issues further application issued (S.CI. 10.1)

I Engineer issues Taking-Over Certificate except


for minor outstanding work and defects
I
Contractor completes Contractor fails to complete
outstanding work outstanding work and defects.
and defects Employer acts as S.CI. 11.4

Fig. 6. Procedures at Completion of Works