Daily report In-charge Manager P.M.

■ Project : The Central Area Of Tay Ho Tay New Town Project

Date 23-February-2018

Morning 17oC~25oC, Cloudy Afternoon 17oC~25oC, Cloudy

Completion Yesterday Plan Today Completion status


APARTMENT WORK (FOUNDATION + STRUCTURE + FINISHING WORK) Description Contract Q'ty Before Q'ty Today Total Completed (%)
1. PHAN VU 1. PHAN VU
- Tet holiday leave - Set up machine before drilling test piles Installing pile 853.00 2.00 0.00 2.00
1. H9
2. WK 2. WK
- Tet holiday leave - Making plan levels Excavate soil and make plan levels

Manpower Machinery & Equipment Material

Item Unit Accum. Today Total Item Unit Accum. Today Total Item Unit Accum. Today Total

1. PHAN VU
Site Manager Ps 0.0 1.0 1.0 Excavator EA 0.0 1.0 1.0
Engineer Ps 0.0 1.0 1.0 Base machine EA 0.0 1.0 1.0
Safety Engineer Ps 0.0 0.0 0.0 Crane EA 0.0 1.0 1.0
Survey Engineer Ps 0.0 1.0 1.0 Mixing cement Machine EA 0.0 1.0 0.0
Pile Machine Driver Ps 0.0 1.0 1.0 Welding Machine EA 0.0 1.0 1.0
Crane Driver Ps 0.0 1.0 1.0 Generator EA 0.0 1.0 1.0
Backhoe Operator Ps 0.0 1.0 1.0 Survey Machine EA 0.0 1.0 1.0
Mixing cement Worker Ps 0.0 1.0 1.0 Pumping EA 0.0 0.0 0.0
H9 Welding Worker Ps 0.0 0.0 0.0 Truck EA 0.0 0.0 0.0
General worker Ps 0.0 0.0 0.0
SUB-TOTAL Ps 0.0 7.0 7.0 Total machine EA 0.0 7.0 7.0
2. WK
Site Manager Ps 0.0 1.0 1.0 Excavator EA 0.0 2.0 2.0
Engineer Ps 0.0 2.0 2.0 Truck EA 0.0 0.0 0.0
Backhoe Operator Ps 0.0 2.0 2.0
Truck Driver Ps 0.0 0.0 0.0
General worker Ps 0.0 0.0 0.0
SUB-TOTAL Ps 0.0 5.0 5.0 Total machine EA 0.0 2.0 2.0
TOTAL OF SUBON Ps 0.0 12.0 12.0 EA 0.0 9.0 9.0
No. Ref. code Meeting agenda Time Result

Other to be informed (Accident , site event , site visitor , Inspection by Authority , Quality problem , etc )

Engineer's Comment

Supervisor's Comment

Prepared by : Contractor Checked by : Supervisor


Daily report In-charge Manager P.M.

■ Project : The Central Area Of Tay Ho Tay New Town Project

Date 24-February-2018

Morning 17oC~25oC, Cloudy Afternoon 17oC~25oC, Cloudy

Completion Yesterday Plan Today Completion status


APARTMENT WORK (FOUNDATION + STRUCTURE + FINISHING WORK) Description Before Q'ty Today Total Completed (%)
1. PHAN VU 1. PHAN VU
- Set up machine before drilling test piles - Set up machine before drilling test piles Installing pile 2.00 0.00 2.00
1. H9
2. WK 2. WK
- Making plan levels - Making plan levels Excavate soil and make plan levels

Manpower Machinery & Equipment Material

Item Unit Accum. Today Total Item Unit Accum. Today Total Item Unit Accum. Today Total

1. PHAN VU
Site Manager Ps 1.0 1.0 2.0 Excavator EA 1.0 1.0 2.0
Engineer Ps 1.0 0.0 1.0 Base machine EA 1.0 1.0 2.0
Safety Engineer Ps 0.0 0.0 0.0 Crane EA 1.0 1.0 2.0
Survey Engineer Ps 1.0 1.0 2.0 Mixing cement Machine EA 1.0 1.0 2.0
Pile Machine Driver Ps 1.0 1.0 2.0 Welding Machine EA 1.0 1.0 2.0
Crane Driver Ps 1.0 1.0 2.0 Generator EA 1.0 1.0 2.0
Backhoe Operator Ps 1.0 1.0 2.0 Survey Machine EA 1.0 1.0 2.0
Mixing cement Worker Ps 1.0 0.0 1.0 Pumping EA 0.0 0.0 0.0
H9 Welding Worker Ps 0.0 1.0 1.0 Truck EA 0.0 0.0 0.0
General worker Ps 0.0 0.0 0.0
SUB-TOTAL Ps 7.0 6.0 13.0 Total machine EA 7.0 7.0 14.0
2. WK
Site Manager Ps 1.0 0.0 1.0 Excavator EA 2.0 2.0 4.0
Engineer Ps 2.0 2.0 4.0 Truck EA 0.0 0.0 0.0
Backhoe Operator Ps 2.0 1.0 3.0
Truck Driver Ps 0.0 0.0 0.0
General worker Ps 0.0 1.0 1.0
SUB-TOTAL Ps 5.0 4.0 9.0 Total machine EA 2.0 2.0 4.0
TOTAL OF SUBON Ps 12.0 10.0 22.0 EA 9.0 9.0 18.0
No. Ref. code Meeting agenda Time Result

Other to be informed (Accident , site event , site visitor , Inspection by Authority , Quality problem , etc )

Engineer's Comment

Supervisor's Comment

Prepared by : Contractor Checked by : Supervisor


Daily report In-charge Manager P.M.

■ Project : The Central Area Of Tay Ho Tay New Town Project

Date 25-February-2018

Morning 17oC~25oC, Cloudy Afternoon 17oC~25oC, Cloudy

Completion Yesterday Plan Today Completion status


APARTMENT WORK (FOUNDATION + STRUCTURE + FINISHING WORK) Description Before Q'ty Today Total
1. PHAN VU 1. PHAN VU Installing pile D700 1.00 0.00 1.00
- Set up machine before drilling test piles - Set up machine before drilling test piles Installing pile D800 2.00 1.00 3.00
1. H9
2. WK 2. WK Excavate soil and make plan levels 0.00 0.00 0.00
- Making plan levels - Making plan levels

Manpower Machinery & Equipment Material

Item Unit Accum. Today Total Item Unit Accum. Today Total Item Quality Accum. Today Total

1. PHAN VU
Site Manager Ps 2.0 1.0 3.0 Excavator EA 2.0 1.0 3.0 PHC D700: L1= 14m 322.00 3.0 0.0 3.0
Engineer Ps 1.0 0.0 1.0 Base machine EA 2.0 1.0 3.0 PHC D700: L2= 15m 322.00 3.0 0.0 3.0
Safety Engineer Ps 0.0 0.0 0.0 Crane EA 2.0 1.0 3.0 PHC D700: L3= 10.2m 4.00 3.0 0.0 3.0
Survey Engineer Ps 2.0 1.0 3.0 Mixing cement Machine EA 2.0 1.0 3.0 PHC D700: L3=8.5m 50.00 0.0 0.0 0.0
Pile Machine Driver Ps 2.0 1.0 3.0 Welding Machine EA 2.0 1.0 3.0 PHC D800: L1= 13.5m 531.00 5.0 0.0 5.0
Crane Driver Ps 2.0 1.0 3.0 Generator EA 2.0 1.0 3.0 PHC D800: L2= 15m 531.00 5.0 0.0 5.0
Backhoe Operator Ps 2.0 1.0 3.0 Survey Machine EA 2.0 1.0 3.0 PHC D800: L3= 10.4m 5.00 5.0 0.0 5.0
Mixing cement Worker Ps 1.0 1.0 2.0 Pumping EA 0.0 0.0 0.0
H9 Welding Worker Ps 1.0 1.0 2.0 Truck EA 0.0 0.0 0.0
General worker Ps 0.0 0.0 0.0
SUB-TOTAL Ps 13.0 7.0 20.0 Total machine EA 14.0 7.0 21.0
2. WK
Site Manager Ps 1.0 0.0 1.0 Excavator EA 4.0 2.0 6.0
Engineer Ps 4.0 2.0 6.0 Truck EA 0.0 0.0 0.0
Backhoe Operator Ps 3.0 1.0 4.0
Truck Driver Ps 0.0 0.0 0.0
General worker Ps 1.0 1.0 2.0
SUB-TOTAL Ps 9.0 4.0 13.0 Total machine EA 4.0 2.0 6.0
TOTAL OF SUBON Ps 22.0 11.0 33.0 EA 18.0 9.0 27.0
No. Ref. code Meeting agenda Time Result

Other to be informed (Accident , site event , site visitor , Inspection by Authority , Quality problem , etc )

Engineer's Comment

Supervisor's Comment

Prepared by : Contractor Checked by : Supervisor


DAILY REPORT
■ Project : The Central Area Of Tay Ho Tay New Town Project, APT (H9-CT1)

Date 26-February-2018

Weather (Morning) 17oC~25oC, Cloudy Weather (Afternoon) 17oC~25oC, Cloudy


Completion Yesterday Plan Today Work Volume
Work Company Manpower Manpower Total Previous Total Perc.
Work Details Work Details Item Unit Today
No. No. Planned Accumulative Completed (%)
- Set up machine before drilling test piles - Set up machine before drilling test piles
- Installing pile D700 - Installing pile D700 Pile D700 ea 853.00 0.00 0.00 0.00 0%
- Installing pile D800 - Installing pile D800 Pile D800 ea 0.00 1.00 1.00

1. PHAN
Pile 27
VU

- Making plan levels - Making plan levels 0.00 0.00 0.00


- Excavate soil and make plan levels - Excavate soil and make plan levels m3

Civil 2.WK 17
Manpower Machinery & Equipment Material
Work Company Previous Total Previous Total Total Previous Total Perc.
Type Today Type Today Item Unit Today
Accumulative Accumulative Accumulative Accumulative Planned Accumulative Accumulative (%)
Site Manager 0.0 1.0 1.0
0. Manager 0.0 3.0 3.0
Main DAEWOO Engineer 0.0 3.0 3.0
VINA Safety Engineer 0.0 0.0 0.0
SUB-TOTAL 0.0 7.0 7.0 SUB-TOTAL 0.0 0.0 0.0
Site Manager 3.0 1.0 4.0 Excavator 3.0 1.0 4.0 PHC D700: L1= 14m 322.00 3.0 0.0 3.0
Engineer 1.0 0.0 1.0 Base machine 0.0 PHC D700: L2= 15m 322.00 3.0 0.0 3.0
Safety Engineer 0.0 0.0 0.0 Crane 0.0 PHC D700: L3= 10.2m 4.00 3.0 0.0 3.0
Survey Engineer 3.0 1.0 4.0 Mixing cement Machin 0.0 PHC D700: L3=8.5m 50.00 0.0 0.0 0.0
Pile Machine Driver 3.0 1.0 4.0 Welding Machine 0.0 PHC D800: L1= 13.5m 531.00 5.0 0.0 5.0
1. PHAN Crane Driver 3.0 1.0 4.0 Generator 0.0 PHC D800: L2= 15m 531.00 5.0 0.0 5.0
Pile
VU
Backhoe Operator 3.0 1.0 4.0 Survey Machine 0.0 PHC D800: L3= 10.4m 5.00 5.0 0.0 5.0
Mixing cement Worker 2.0 1.0 3.0 Pumping 0.0
Welding Worker 2.0 1.0 3.0 Truck 0.0
General worker 0.0 0.0 0.0
SUB-TOTAL 20.0 7.0 27.0 SUB-TOTAL 21.0 7.0 0.0
Site Manager 1.0 0.0 1.0 Excavator 6.0 2.0 8.0
Engineer 6.0 2.0 8.0 Truck 0.0 0.0
Backhoe Operator 4.0 1.0 5.0 0.0 0.0
Civil 2. WK
Truck Driver 0.0 0.0 0.0 0.0 0.0
General worker 2.0 1.0 3.0 0.0 0.0
SUB-TOTAL 13.0 4.0 17.0 SUB-TOTAL 6.0 2.0 8.0
TOTAL OF
TOTAL OF
TOTAL NO 33.0 11.0 44.0 EQUIPMEN 27.0 9.0 8.0
MANPOWER
T
No. Ref. code Meeting agenda Time Result

Other to be informed (Accident , site event , site visitor , Inspection by Authority , Quality problem , etc )

Engineer's Comment

Supervisor's Comment

Prepared by : Contractor Checked by : Supervisor