Lecture 6
Engineering Management
Bidding Procedures I
Owners should advertise the availability and distribution of bidding documents as far in advance as possible,
but no later than 30 days prior to bid document issue. An advertisement should contain a short description of
the project, including bid date, time, approximate contract amount, approximate size, project location,
licensing requirements, plus bid and performance and payment bond requirements. It also should state the
date of document availability, location of documents, and deposit and refund information.
An Employer invites sealed bids from eligible Contractors who meet the following criteria:
Interested eligible candidates may obtain further information from and inspect the Bid documents at the
Procurement Office, during normal working hours (08:30 – 15:30 local time on Mondays to Fridays except
during lunch time from 13:00 to 14:00 hours and public holidays.).
1Extracted from a construction of water kiosks and extension of water pipelines bid
1
L. Ogutu June 2019 Engineering Management II
June 2019
A complete set of Bid documents may be obtained by interested candidates upon payment of non-refundable
fee.
Completed Bid documents are to be enclosed in plain sealed envelopes marked with Bid reference number and
be deposited in the Tender Box at the Employer’s office by a set date.
Prices quoted should be inclusive of all taxes; and must be in Kenya Shillings. They shall remain valid for a
period of ninety (90) days from the closing date of the Bid.
Bids will be opened immediately thereafter in the presence of the Candidates or their representatives who
choose to attend
costs of visiting the site shall be the Bidder’s own responsibility. A site visit confirmation form shall form part
of this bid document.
a. General Conditions
The Conditions of Contract set out the core terms of the contract between the parties. In doing
so, the Conditions of Contract set forth the rights, obligations and responsibilities of the parties
arising in connection with the design and construction of the works. The Conditions of Contract
also prescribe procedures for the management of the project.
This contract document will define the obligations and rights on how to execute the project.
b. Specifications
Specifications add intelligence to the construction drawings; specify common standards,
deviations accepted, materials accepted and the required testing for all materials. Usually,
specifications are composed by referencing construction standards and codes. The specification
sets out the technical requirements of the works, and how those works are to be executed.
c. Bill of Quantities
Bill of Quantities is formed by the list of diverse trades, and materials included that form part of
the construction. Sometimes this document is not required by the contracting officer.
d. Drawings
All set of drawings that form part of the job to be performed. These drawings are usually the
latest drawings and must be received by the contractor prior to the date of commencement. It
must include all drawings from consultants, and will constitute the entire project being
contracted.
e. Letter of Acceptance
The Letter of Acceptance as the “letter of formal acceptance, signed by the Employer, of the
Letter of Tender, including any annexed memoranda comprising agreements between and
signed by both Parties”.
The Employer shall respond in writing to any request for clarification which he receives earlier
than seven (7) days prior to the deadline for the submission of Bids.
Written copies of the Employer’s response (including the query but without identifying the
source of the inquiry) shall be sent to all prospective Bidders who have purchased the Bid
documents. Clarifications shall be done within three (3) days of receipt.
4
L. Ogutu June 2019 Engineering Management II
June 2019
or
b) In the case of a successful Bidder, if he fails
(i) To sign the Agreement,
or
(ii) To furnish the necessary Performance Security
c) If a bidder does not accept the correction of his Bid price pursuant to requirements of
this bid.
The Employer shall prepare minutes of the Bid opening including the information disclosed to
those present.
Bids not opened and read out at Bid opening shall not be considered further for evaluation,
irrespective of the circumstances.
After the public opening of Bids, information relating to the examination, clarification,
evaluation and comparisons of Bids and recommendations concerning the award of Contract
shall not be disclosed to Bidders or other persons not officially concerned with such process
unless the award of Contract is announced.
4.0 EVALUATION OF BIDS
Preliminary Evaluation
Detailed Evaluation
Technical Evaluation
Financial Evaluation
Awards
The Bid is complete and does not deviate from the scope,
Any computational errors have been made,
Required sureties have been furnished,
The documents have been properly signed,
The Bid is valid till required period,
The Bid prices are firm during currency of contract if it is a fixed price bid,
Completion period offered is within specified limits,
The Bidder/Manufacturer is eligible to bid and possesses the requisite experience,
Is the bid accompanied by the required securities i.e. the amount is adequate as Standard
Procedure for Evaluation of Bids for Procurement of Works?
6
L. Ogutu June 2019 Engineering Management II
June 2019
Bids that contain major deviations from the requirements in the instruction to bidders shall be
considered invalid.
e. Corrections for errors, discounts, and other modifications: corrections for arithmetical or
computational errors, as well as for discrepancies between total bid prices and extended unit bid
prices, between stated total prices and actual summations, between prices in figures and in
words, and other errors/discrepancies, shall use the methodology described in the Instructions
to Bidders. Discounts and other modifications in the bid amounts shall be reflected in the
evaluation of bids.
f. Modifications and Discounts:
Bidders are allowed to submit, prior to bid opening, modifications to their original bid. The
impact of modifications should be fully reflected in the examination and evaluation of the bids.
These modifications may include either increases or discounts to the bid amounts that reflect
last-minute business decisions.
a. If there is a discrepancy between the unit price and the total price that is obtained by
multiplying the unit price and quantity, the unit price shall prevail and the total price shall be
corrected, unless in the opinion of the Employer there is an obvious misplacement of the
7
L. Ogutu June 2019 Engineering Management II
June 2019
decimal point in the unit price, in which case the total price as quoted shall govern and the unit
price shall be corrected;
b. If there is an error in a total corresponding to the addition or subtraction of subtotals, the
subtotals shall prevail and the total shall be corrected; and
c. If there is a discrepancy between words and figures, the amount in words shall prevail, unless
the amount expressed in words is related to an arithmetic error, in which case the amount in
figures shall prevail subject to (a) and (b) above
Bidders shall be requested to accept correction of arithmetical errors. Failure to accept the correction, shall
result in the rejection of the Bid
4.2.9 Employer’s Right to Accept Any Bid, and to Reject Any or All Bids
The Employer reserves the right to accept or reject any bid, and to annul the bidding process and reject all
bids at any time prior to contract award, without thereby incurring any liability to Bidders. In case of
annulment, all bids submitted and specifically, bid securities, shall be promptly returned to the Bidders
8
L. Ogutu June 2019 Engineering Management II
June 2019
In the event the Procuring entity terminates the Contract in whole or in part, it may procure, upon such
terms and in such manner as it deems appropriate, equipment similar to those undelivered, and the Bidder
shall be liable to the Procuring entity for any excess costs for such similar goods.
Either Party may terminate the contract for any reason provided that such termination is communicated to
the other Party by way of a notice and provided that such a notice is given three calendar months from the
date of receipt of the notice to the date of the termination.
9
L. Ogutu June 2019 Engineering Management II
June 2019
10
L. Ogutu June 2019 Engineering Management II
June 2019
To:
This is to notify that the contract/s stated below under the above mentioned tender have been awarded to
you.
(FULL PARTICULARS)
SIGNED FOR ACCOUNTING OFFICER
11
L. Ogutu June 2019 Engineering Management II
June 2019
WHEREAS ………………………………………..(hereinafter called “the Tenderer”) has submitted his tender dated
………………………… for the construction of ……………………………………………………………………… ……………………
(name of Contract)
KNOW ALL PEOPLE by these presents that WE ……………………… having our registered office at
………………(hereinafter called “the Bank”), are bound unto ……………………………(hereinafter called “the
Employer”) in the sum of Kshs.……………………… for which payment well and truly to be made to the said
Employer, the Bank binds itself, its successors and assigns by these presents sealed with the Common Seal of
the said Bank this ……………. Day of ………20…………
1. If after tender opening the tenderer withdraws his tender during the period of tender validity
specified in the instructions to tenderers
Or
2. If the tenderer, having been notified of the acceptance of his tender by the Employer during the
period of tender validity:
a. fails or refuses to execute the form of Agreement in accordance with the Instructions to
Tenderers, if required; or
b. fails or refuses to furnish the Performance Security, in accordance with the Instructions to
Tenderers;
We undertake to pay to the Employer up to the above amount upon receipt of his first written demand,
without the Employer having to substantiate his demand, provided that in his demand the Employer will note
that the amount claimed by him is due to him, owing to the occurrence of one or both of the two conditions,
specifying the occurred condition or conditions.
This guarantee will remain in force up to and including thirty (30) days after the period of tender validity, and
any demand in respect thereof should reach the Bank not later than the said date.
___________________________ ______________________________
[date [ [signature of the Bank]
___________________________ ______________________________
[witness] [seal]
12
L. Ogutu June 2019 Engineering Management II
June 2019
Dear Sir,
AND WHEREAS it has been stipulated by you in the said Contract that the Contractor shall furnish you with a
Bank Guarantee by a recognised bank for the sum specified therein as security for compliance with his
obligations in accordance with the Contract;
AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee:
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you, on behalf of the
Contractor, up to a total of Kshs. ________________ (amount of Guarantee in figures) Kenya
Shillings__________________________________________ (amount of Guarantee in words), and we
undertake to pay you, upon your first written demand and without cavil or argument, any sum or sums
within the limits of Kenya Shillings _________________________ (amount of Guarantee in words) as
aforesaid without your needing to prove or to show grounds or reasons for your demand for the sum
specified therein.
We hereby waive the necessity of your demanding the said debt from the Contractor before presenting us
with the demand.
We further agree that no change, addition or other modification of the terms of the Contract or of the Works
to be performed thereunder or of any of the Contract documents which may be made between you and the
Contractor shall in any way release us from any liability under this Guarantee, and we hereby waive notice of
any change, addition, or modification.
This guarantee shall be valid until the date of issue of the Certificate of Completion.
13
L. Ogutu June 2019 Engineering Management II