Beruflich Dokumente
Kultur Dokumente
AUTO-BAKE SERPENTINE™
218-PAN CONVECTION HEATED OVEN
FREE-TRAY LTS BAKING LINE
SUNCREST LINE # 7
Philippines
J/N 5128
SERIAL NO: 793 LTS218 02 13
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 1
_______________________________________________________________________________
TABLE OF CONTENTS
SECTION 1 ...................................................................................................................................... 5
1.1 Definition of Symbols ..................................................................................................... 6
1.2 General Safety Checks ................................................................................................. 7
1.3 Lock-Out Procedure ...................................................................................................... 8
SECTION 2 GENERAL DESCRIPTION OVERVIEW .................................................................. 10
2.1 System Process .......................................................................................................... 11
2.2 Oven Infeed Module – 4m (including Free-Tray Loading System) .............................. 14
2.3 Serpentine™ Gas-Fired Convection Heated Oven - 218 Pans ................................... 14
2.4 Product Inspection Station – 2.5m............................................................................... 17
2.5 Oven Drive Unit c/w Vertical Pan Transfer System (VPTS) ........................................ 17
2.5.1 Mechanical Overload System ..................................................................................... 17
2.5.2 Chain Tensioning System ........................................................................................... 18
2.6 Serpentine™ MK 126-8/9 Ambient Coolers – 207/232 Pans ...................................... 18
2.7 Cooler-Mounted Drive & Chain Take-Up System ........................................................ 19
2.8 Outfeed Module – 3m c/w Drive Unit & Main Chain Take-Up ..................................... 20
2.9 Automatic Lubrication System (Chain & Carrier Bearings).......................................... 20
2.10 Robotic Product Depanning System – Dual Head....................................................... 21
2.11 Conveyor Circuit System (CCS) .................................................................................. 21
2.12 Pan Washer & Dryer - Colussi .................................................................................... 21
2.13 Pan Greaser - Dubor ................................................................................................... 21
2.14 Steam Generator – Simons Boilers ............................................................................. 22
2.15 Electrical Control Cabinet (MCC) & HMI (Touch Screen Control) ............................... 22
2.16 ATTACHMENTS ......................................................................................................... 22
Production Line Drawing ............................................................................................. 22
Services Information ................................................................................................... 22
Tray/Product Drawings ............................................................................................... 22
Line and Factory Layout ............................................................................................. 22
Colussi Pan Washer & Dyer Operating Instructions Manual ...................................... 22
Dubor Pan Greaser Operating Instructions Manual .................................................... 22
Simons Steam Generator (Boiler) Operating Instructions Manual .............................. 22
SECTION 3 OVEN INFEED MODULE ........................................................................................ 23
3.1 Oven Infeed Module .................................................................................................... 24
SECTION 4 GAS-FIRED CONVECTION-218 PAN BAKING OVEN ........................................... 27
4.1 Description of Heating System .................................................................................... 29
4.2 Gas Train ..................................................................................................................... 30
4.3 Detailed Purge Process ............................................................................................... 31
4.3.1 PLC-Automated Purge Sequence ............................................................................... 31
4.4 Burner Start-Up Sequencing ....................................................................................... 32
4.5 Temperature Control ................................................................................................... 32
4.6 Oven Exhaust System ................................................................................................. 34
4.7 Pan Too-High Sensor .................................................................................................. 35
4.8 Oven Cleaning – Annual Schedule ............................................................................. 35
4.9 ATTACHMENTS ......................................................................................................... 37
AeroVent Fan Operation & Maintenance Instructions................................................. 37
Eclipse Burner Manuals (Design and Installation) ...................................................... 37
Eclipse Air Heat Burners – Model AH ......................................................................... 37
Eclipse Butterfly Valves and Belimo Servo Motors ..................................................... 37
Burner Fan Manual – Moro ......................................................................................... 37
Krom Schroder Pressure Switches ............................................................................. 37
Siemens LFL Series – Burner Flame Safeguard Control............................................ 37
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 2
_______________________________________________________________________________
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 3
_______________________________________________________________________________
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 4
_______________________________________________________________________________
SECTION 1
SAFETY NOTICE
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 5
_______________________________________________________________________________
Important Message
Maintenance Personnel
Electrician
General Operator
Extreme danger
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 6
_______________________________________________________________________________
• Ensure all operators, maintenance and sanitation personnel read these instructions
carefully and fully understand the contents before working on the Auto-Bake line.
• Ensure all operators are fully trained on the particular Auto-Bake equipment they are
responsible for, and that they are fully aware of emergency stop locations and the
correct start up procedure for the system.
• Ensure all guards are in place before starting equipment and ensure that safety
interlocks, where installed, are operative. Never remove a guard without first isolating
all power to the machine. Ensure all emergency stops, lanyards and safety interlocks
are in good working condition and will stop the line when activated.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 7
_______________________________________________________________________________
• Ensure start-up alarm is in good working condition and clearly audible from all
operating stations on the Auto-Bake line.
• Ensure motor overload systems are in good working condition and that sensitivity
settings are checked regularly by qualified engineering personnel.
• Prior to starting up the conveyor system, check and remove any objects that may
have been placed & left on the machine, and ensure all pans and grills are correctly
replaced in their carriers following routine cleaning or maintenance operations.
Please note the following lock-out procedure, which is to be followed prior to entering the
chain path area of an operational machine:
• Identify with your supervisor the area of the machine in which you will be working.
• Identify the drive that powers that specific area of the machine, and identify the
electrical isolator for that drive.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 8
_______________________________________________________________________________
• Ask your supervisor to isolate the drive by turning the electrical isolator to the ‘off’
position.
• Place compliant ‘red electrical lockout clasp’ through the isolator switch handle and
close the clasp.
• Place your personal, engraved padlock through one of the holes in the clasp and
close the padlock.
• Ask your supervisor to try and start the machine. Failure to start confirms the lock-out
has been successful.
• Once you have completed your task, and do not intend going back into the machine,
remove your padlocks. Advise your supervisor that you have finished and that you do
not intend going back into the machine.
• Once all locks are removed, the supervisor may switch on the isolator in readiness
for machine start-up.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 9
_______________________________________________________________________________
SECTION 2
GENERAL DESCRIPTION
OVERVIEW
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 10
_______________________________________________________________________________
Auto-Bake’s Free-Tray system feeds product-deposited pans continuously into the oven
infeed module, transferring each pan at line speed onto a converging vacant host carrier as
it journeys around the Auto-Bake closed-loop chain circuit. A system of conveyors is
incorporated to transport trays ejected at the oven outfeed module all the way back to the
oven infeed module, with trays passing various process stations en-route.
Starting at the beginning of the process, space along the conveyor circuit is provided for
operators to manually insert paper liners into recently cleaned empty pans, and/or to
accommodate an ancillary Paper Cup Denester (supplied by others where incorporated). If
product is deposited directly into pan cavities, a roll in/out pan greaser caters for this, and is
located immediately upstream of the Depositor station. The Depositor (supplied by others)
fills empty pan cavities or paper cups with product batter as the empty pans pass through
the station.
Pans enter the segmented 6-zone convection oven at low-level and travel along each
horizontal run in the first segment winding upwards along the Serpentine™ chain path to the
uppermost horizontal run. Pans enter the second segment of the oven at top level and travel
horizontally to the extreme outfeed end, whereupon they wind downwards this time along the
Serpentine™ chain path to the lowest horizontal run of the second segment, before exiting
the oven at the opposite end to which they entered.
Pans progress into the upper, then lower, Ambient Coolers (8-run & 9-run respectively),
entering at hi-level after passing the Product Inspection Station, Oven Drive Unit and
Overhead Pan Transfer System en-route. The pans riding in their host carriers traverse
downwards along the Serpentine™ chain path, where naturally rising hot air ensures each
subsequent horizontal run continues to be cooler than the one immediately above it. In
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 11
_______________________________________________________________________________
addition to natural convection, a series of fans assist in the removal of flash-heat from the
product and from the metal transport elements.
Upon exiting the Ambient Coolers at low-level, carriers & pans continue into the Outfeed
Module whereupon the pans are separated and ejected onto the first of 11 system
conveyors (nominated C1-C11), C1 being the 5m Injector conveyor located immediately
downstream of the Outfeed Module, and C-11 being the 90º conveyor feeding newly-
deposited pans back into the Oven Infeed Module.
Product can be filled on demand by an ancillary Injector (by others) which straddles C1.
Products baked directly in the pan cavities (as opposed to paper cups) are partially liberated
from the baking cavities by a purpose built pre-release manifold located immediately
downstream of the Injector mounted to C1. The pre-release manifold is fitted with
strategically located nozzles that blast hi-pressure air between the outer perimeter of each
individual product and the cavity in which it was baked. Pans now containing ‘loosened’
product are subsequently transferred via C2 & C3 to the Robotic Product Depanning
System, where product is transferred onto one of two take-away conveyors (by others).
Empty pans are transported from the robot enclosure via C4, then to the entrance of the in-
line Colussi Pan Washer via C5. Pans enter the washer tunnel (right way up) and emerge
clean & dry as they proceed onto C6, which is 15m long. Water in the Colussi washer is
heated by steam injected into the tank’s heat-exchangers. A 350 Kw Simons Boiler supplied
by Auto-Bake generates the necessary steam. Operators can stand either side of C6 at a
comfortable distance apart when manually inserting paper cups into pan cavities. A future
Paper Cup Denester can be accommodated downstream on C7, which also caters for two
additional equipment stations, including a Pan Greaser (Dubor) & Batter Depositor
(Suncrest). Two stainless steel slat-belts incorporating equally pitched welded dog plates
positively propel & locate the pans as they pass under each process stations.
C8 is a straight conveyor that declines approximately 200mm over its length joining onto a
90º conveyor, C9. C10 is a short straight conveyor bridging the two 90º conveyors (C9 &
C11), and is ideal for loading/unloading pans in to/out of the system when product changes
are being undertaken. Several conveyors including C10 have pivoting lift-over side guides
for centralising the shorter croissant trays when loading. These loading guides simply pivot
back out of the way when the longer Fudgee Bar & Ring Cake pans are in production.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 12
_______________________________________________________________________________
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 13
_______________________________________________________________________________
NOTE:
Please refer respective operation and maintenance manuals
for all ancillary equipment not supplied by Auto-Bake
• Full perimeter safety cage to protect operators from moving mechanical transmission
components such as chains & sprockets. This cage can only be assessed when the
Auto-Bake line has been powered-down. This is achieved without electrical interlocks but
rather by a series of mechanical locks & keys.
• An industrial PLC integrated HMI (Touch Screen) control unit designed to enable easy
operator interface of oven and auxiliary controls. The HMI screen is mounted to a fixed
post located at the RH side of this module.
Construction
The Infeed module is manufactured from heavy gauge RHS and angle sections. Welded to
these are heavy-duty 12mm (1/2”) mild steel side plates, which are in turn strengthened by
angle and plate cross members. The Infeed section is fully protected by a zinc rich epoxy
coating. Guards, doors, panels & covers are manufactured from stainless steel sheets.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 14
_______________________________________________________________________________
the uppermost run of the first section of the oven in horizontal runs, transferring radially
around sprockets at each end of each horizontal level. Crossing a separating bulkhead over
to the second Serpentine™ section of the oven, carriers and their pillion baking pans then
proceed downwards to the lowest horizontal run in the second section, with carriers once
again transfer radially about each sprocket set located at the end of each horizontal run.
Fully baked product in pans exit the oven at the opposite end to which the pans entered,
emerging into the Product Inspection Station.
Cold air is pulled through each burner’s flame by the respective zone blower and heated to a
specific temperature as controlled via the size of the flame (the burner’s turn-down position).
The heated air is then pushed by the blower into diffuser plenums (plena) located above and
below each horizontal pass in each section of the oven. Each burner provides heating for 4
rows of plena (constituting that particular burner’s heating-zone). Each plenum has a row of
slits above and below where the heated air escapes and enters the oven baking chamber.
The percentage of air delivered from the top slits relative to the bottom slits of each plenum
is adjustable by PLC controlled actuators, hence enabling top & bottom heat profiles to be
selected at the HMI and saved to a specific recipe.
Oven Bearings
The sprocket assemblies in the oven incorporate heavy-duty bearings that are pre-lubricated
with special high temperature grease.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 15
_______________________________________________________________________________
Only the recommended grease should be used for the bearings! The bearings have
been charged with grease at the Auto-Bake factory, and only the same grease should
be used. Do not mix greases or utilize any other make of grease!
Please refer to the lubrication schedule for details on the greases to be used. The oven
bearings use Barrierta L55/2 manufactured by Klüber. Each sprocket assembly has a
readily accessible greasing point allowing for periodic maintenance. The oven bearings are
protected against ingress of foreign material by ‘Nilos’ ring seals. All other bearings external
to the oven are standard clearance, pre-packed with specific food-safe grease, including in
some cases, Barrierta L55/2 where bearings are still relatively hot within close proximity of
the oven. (Refer to drawing at the rear of this section showing oven bearing greasing points.)
Environment
Flues are required to extract moisture from the baking environment and to extract products
of combustion. Flues are not supplied by Auto-Bake.
Please note that flues will require cleaning on a periodic basis to remove any fat or
similar build up on the wall of the flues. Such build up, unless removed, may present
a fire danger.
Oven Doors
All side doors are hinged, such that the interior of the oven is accessible for periodic
inspection, maintenance and cleaning. A window on either side of the oven allows for visual
product inspection during baking. Oven door panels are manufactured from No 4 polished
stainless steel.
Construction
The oven is constructed from welded heavy gauge RHS and angle sections. Members are
protected against corrosion by a zinc rich epoxy coating and lined with low heat transfer
insulation material, such as ‘Superwool’ or similar. Guards, doors, panels & covers are
manufactured from stainless steel sheets.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 16
_______________________________________________________________________________
Construction
The Product Inspection Station is manufactured from heavy-gauge RHS steel members
welded to 12mm thick steel side-plates. Members are protected against corrosion by a zinc
rich epoxy coating. Guards and covers are manufactured from stainless steel sheets.
2.5 Oven Drive Unit c/w Vertical Pan Transfer System (VPTS)
Duty
The Drive Unit provides carrier transport chain propulsion via a speed-variable 3-phase
electric motor. Where multiple drive units are incorporated, the oven drive is the master and
all other drives are slaves to the oven drive. Synchronised motors are used which are
‘homed’ on start-up with the aid of linear encoders. These encoders are mounted to the
chain tensioner slides located downstream of the slave drive(s). Power and torque are
transmitted via a reduction hollow shaft gearbox coupled directly to the electric motor. The
drive unit is fitted with an on-board mechanical overload system as described below, which
is designed to protect the transport system chain & carriers. Line speeds can be individually
set (and saved to recipe) at the HMI touch screen.
The Vertical Pan Transfer System (VPTS) comprises sets of standard LTS sprockets &
guides in conjunction with vertical elevator rails that guide the pan carriers directly to the
upper-most run of the Ambient cooler, whilst maintaining the carriers in a level plane during
the vertical ascent.
A mechanical overload limit switch is fitted to the drive unit. In normal running conditions this
switch is in the ‘depressed’ position, held by a torque arm mounted to the gearbox housing.
As reaction torque builds up due to increased load on the conveyor chain, the motor/gearbox
assembly will pivot allowing the limit switch to slowly release from its fully depressed state. If
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 17
_______________________________________________________________________________
sufficient load is encountered, the limit switch will trip stopping the entire production line in
the process. The sensitivity of the overload system is controlled via a programmable
pressure regulator, which is pre-set by Auto-Bake to control precise air pressure servicing
the overload air cylinder. The overload air cylinder applies force to the torque arm such that
it provides resistance to the natural reaction of the pivoting gearbox as load is encountered.
By increasing this resistance (by increasing air pressure), the effort required to trip the
overload limit switch also increases. The system is hence more sensitive to mechanical
overload when the overload cylinder air supply pressure is set as low as possible, without
incurring nuisance stoppages.
As is common with all chain-driven mechanisms, loose carrier transport chain is generated
immediately downstream of each drive unit. As such, all drive units incorporate a dedicated
dynamic chain tensioning system which in most cases is located as near as possible
downstream to the propulsion unit it serves. The LHS & RHS carrier transport chains are
engaged with tensioning sprockets mounted to slide plates. Each slide plate is connected to
a dedicated air cylinder plumbed in parallel and controlled by a common pressure regulator.
An air pressure switch is pre-set to a minimum value, as deemed appropriate to safely drive
all pneumatic-controlled devises on board. When air pressure drops below this value the line
is programmed to stop and a corresponding alarm will be annunciated on the HMI.
Construction
The Drive Modules are manufactured from heavy gauge RHS and angle sections. Welded to
these are heavy-duty 12mm (1/2”) mild steel side plates that are in turn strengthened by
angle and plate cross members as required. Members are protected against corrosion by a
zinc rich epoxy coating. Guards and covers are manufactured from stainless steel sheets.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 18
_______________________________________________________________________________
incorporates 8 horizontal passes whilst the lower unit incorporates one additional pass to
continue product flow towards the outfeed end of the Auto-Bake line. Trays emerge from the
lower cooler at the lowest horizontal pass whereupon they enter into the Outfeed Module.
Each Mk 126 Ambient Cooler module is fitted with side-mounted fans that pull ambient air
across the path of product as it travels along the horizontal runs, thus exhausting flash heat
to the side of the machine away from the product zone. This process assists depanning by
allowing the product to cool sufficiently for handling purposes. The Ambient Cooler dwell
time is nominally calculated based on an accepted ratio with the oven dwell time, which can
vary depending on whether a refrigerated cooler is incorporated downstream, and in some
cases, on special instructions from customers. In this case the exact ratio is 218:439 (oven
pans: cooler pans), or 200% cooling relative to baking.
Ambient Coolers can be enclosed within an insulated room (supplied by others) or open to
the factory, depending on conditions and customer requirements.
Construction
Ambient Cooler modules are manufactured from welded heavy gauge RHS and angle
sections. Members are protected against corrosion by a zinc rich epoxy coating. Guards and
covers are manufactured from stainless steel sheets.
The chain tensioning system resides at the opposite end of the cooler (infeed end) taking up
slack chain generated on the downstream side of the propulsion unit. This chain tensioning
system is similar in design and operation as described previously in the Oven Drive section.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 19
_______________________________________________________________________________
2.8 Outfeed Module – 3m c/w Drive Unit & Main Chain Take-Up
Duty
Baked product exiting the cooler is conveyed to the Outfeed section where the tray transfer
system is located. The tray transfer mechanism pushes the trays from the carriers and onto
the take-away conveyor. The empty carrier frames then return to the infeed to receive fresh
trays and product.
The Outfeed Module Drive Unit provides additional conveyor chain propulsion via a speed-
variable 3-phase electric motor with identical performance specification to that of the Oven
Drive. Power and torque are transmitted via a reduction hollow shaft gearbox coupled
directly to the electric motor. The Drive Unit is fitted with an on-board mechanical overload
system as described previously in the Oven Drive section.
The main [carrier transport] chain tensioning system also resides in the Outfeed Module.
This chain tensioning system is similar in design and operation as described previously in
the Oven Drive section except the take-up slides may have additional travel capacity (usually
500mm linearly), which enables one complete tray-pitch of chain to be removed as/when
these slides approach limit of travel.
Construction
The Outfeed Module is manufactured from heavy gauge RHS and angle sections, which
form the base-frames. Welded to these are heavy-duty 12mm (1/2”) mild steel side plates
that are in turn strengthened by angle and plate cross members. The Outfeed Module is fully
protected by metallic coating. Guards and covers are manufactured in No 4 polished
stainless steel.
Duty
An automatic chain and carrier bearing lubrication system manufactured by Dropsa is
installed at the front end of the infeed module (Please refer applicable section in this
manual). Recommended lubricant is KLUBERFOOD NH1 CH 2-220 made by Klüber.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 20
_______________________________________________________________________________
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 21
_______________________________________________________________________________
Duty
The MCC is located adjacent to the Infeed Module. This cabinet contains all the contactors,
variable speed drives, relays, switchgear and a PLC which controls the line functions. A HMI
touch screen interface is located on one of the main cabinet doors, which displays real-time
comprehensive data regarding the system’s status and allows operators to control all
necessary line functions. There is provision to store the product parameters (menu) such as
bake time, oven zone temperatures, chain lubrication frequency, etc. in the PLC memory to
allow for quick changeover between production runs without having to re-program for each
product. Once programmed, the production line operator is only required to select a product
menu which will in turn set all parameters automatically. A VPN link allows for remote
diagnostic assistance of the main PLC, if required.
2.16 ATTACHMENTS
Production Line Drawing
Services Information
Tray/Product Drawings
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 22
_______________________________________________________________________________
SECTION 3
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 23
_______________________________________________________________________________
Trays carrying deposited product are transferred horizontally from upstream conveyor (C11)
into the Infeed Module, maintained on the machine centreline by fixed tray guides (for Ring
Cake & Fudgee Bar pans), or retractable tray guides (for Croissant pans). Trays are
presented wide edge leading onto two rows of flat-top conveyor belts which are set at the
same working height as C11. The Infeed Module flat-top conveyor belts continually circulate
when the line is running at a constant line-speed ratio, by way of mechanically gearing
coupled directly to the carrier transport chain idler sprockets located at the oven end of
this module.
Each loaded tray travels along the infeed section riding on top of the flat-top conveyor belts a
distance of some 1.5 metres approximately, whereupon they are prevented from progressing
any further by way of two pneumatically operated pivoting gates. These gates are
controlled via the PLC to swing upwards at a strategic moment in time; blocking the path of
each tray in sequence until the Auto-Bake carrier to be merged with is at the correct relative
position.
As the trays continue to feed into the infeed section from upstream processing, accumulating
behind the tray being held back by the pivoting gates, it will be necessary to create a ‘gap’
between each subsequently released tray. This gap is required to ensure the pivoting gates
can swing up freely and detain the next tray without hitting the preceding tray released.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 24
_______________________________________________________________________________
Since all trays are propelled by the flat-top conveyor belts, which are travelling at a constant
speed, detaining the next tray is accomplished by injecting brake pins upwards from
underneath the trays at just the right height as to thwart the tray’s forward momentum. These
pins are connected to pneumatic cylinders controlled via the PLC and are retracted when a
sufficient gap has been created. At the appropriate time the pivoting gates will swing
downwards again out of the trays path, allowing the liberated tray to continue on its way
riding on the flat-top conveyor belts, which continuously slide beneath the tray unabated by
gate operation.
The speed of the flat-top conveyor belts has been mechanically geared to run approximately
25% faster than the average line speed, taking into account all known product types
nominated by the customer. Whilst this actual percentage ratio will change slightly as
different line speeds are called for, the flat-top conveyor belts will always be travelling faster
than the linear line speed due to the fixed mechanical linkage employed.
The faster speed of the flat-top conveyor belts is required to ensure the released tray can
accelerate along the remaining length of the infeed section fast enough to shunt up behind
two rows of tray pusher dogs, that are pushing the preceding tray forward towards the
oven. It is essential the tray in transfer reaches the preceding pair of pusher dogs in plenty of
time before the next pair of pusher dogs coming around on the pusher dog chain-circuit
block off passage. There are two pusher dog chain-circuits, each mechanically driven by
the same carrier transport chain idler sprockets as the flat-top conveyor belts. However,
unlike the flat top conveyor belts, the dog chain-circuits are geared to run at exactly the
same linear speed as the Auto-Bake carrier transport chain.
Tray support is transferred from the flat-top conveyor belts onto two cantilevered tray slide
arms some distance downstream of where the trays first shunts up against the back of the
pusher dogs. The ‘dead-bed’ working surface of the tray slide arms is fixed about 2mm
below the flat top belts so that the trays are unimpeded whilst travelling over these slides
when riding on the flat-top conveyor belts. As the horizontal travel limit of the flat-top
conveyor belts is reached, the leading edge of the tray in transfer will slowly ‘ride off’ these
belts and rest on the dead-bed surface of the slide arms, said 2mm below, slowing down in
the process since traction from the flat-top conveyor belts has now become impeded. By this
time the entire tray in transfer is forward on the slide arms, well beyond the centreline of the
rear tray pusher dog chain sprockets.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 25
_______________________________________________________________________________
The slowing down affect caused by the front of the tray now riding on the dead-bed slide
arms enables the next set of pusher dogs (attached to the pusher dog chain-circuit) to catch
and shunt up behind the slowed-down tray. The subject tray is then pushed forward towards
the oven by the pair of chain dogs travelling at the same linear speed as the Auto-Bake
carrier transport system. As this set of pusher dogs reach the end of their horizontal travel
and rotate radially about their respective drive sprockets, the tray they are pushing is shoved
to a final resting point just in time to be transported away by the next passing carrier in the
circuit.
At all times the transferred trays remain horizontal and are supported on the slide arms right
up to the point the carriers are at Top Dead Centre of the Infeed Module’s carrier transport
chain idler sprockets, hence there is no perceivable interruption to the horizontal trajectory of
the trays during the entire transfer process. As the carrier proceeds into the oven it drags the
captured tray with it, sliding the tray gently from the tips of the tray slide arms, from whence
the tray will be wholly supported in the carrier frame.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 26
_______________________________________________________________________________
SECTION 4
GAS-FIRED
CONVECTION-218 PAN
BAKING OVEN
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 27
_______________________________________________________________________________
Prelude
The oven utilises the Auto-Bake Serpentine™ continuous conveying system incorporating
two identical sections divided by an insulated bulkhead. This is often referred to as a ‘back to
back’ oven. The only difference between the two sections of this oven is that the pans travel
from the bottom to the top of the oven in the first section and from top to bottom of the oven
in the second section. Some of the following images depict a typical single-section oven,
which can be taken to represent any of the two sections in this ‘back to back’ oven. Each
section is identical in all manner of operation other than the vertical direction in which the
trays travel.
Overview
Pans with deposited product are conveyed in carriers from the Infeed Module into the oven,
through 6 zones of heating (3 zones per section) such that the product on exiting the oven is
fully baked to specification. Carriers & pans enter at the bottom of the oven’s first section
and are conveyed in horizontal passes along the length of the oven, transferring vertically
around sprockets at the end of each level to move to the next horizontal run above. Having
completed the full circuit through the first section of the baking chamber, pans are conveyed
from the end of the top level through the internal bulkhead wall into the second section of the
oven. From here pans wind downwards to the bottom run in the second section, in the exact
same manner as they did in the first section, exiting the oven from the opposite end to which
they entered.
The oven essentially consists of 2 Serpentine™ system modules, mounted back to back as
described in the above prelude. The oven has capacity to accommodate a total of 218
carriers at any given time. Each of the two segregated sections of the oven incorporates a
separate heating system comprising 3 gas burners, 3 combustion chambers, 3 turbulence
fans, 3 sets of air ducting, and, 12 diffuser plates, capable of directing discharged hot air
from the top or bottom (of each plate) in varying proportions. These diffuser plates cover the
vast majority of the area above and below the travelling baking pans, and are referred to as
heating plena (plural of plenum). Each of the two oven modules is configured with 3 heating
zones, therefore 6 heating zones in the entire oven. Temperature in each heating zone can
be controlled to a different set point, and each zone of plena can be biased top to bottom in
terms of hot air discharged (in either direction from 0-100%). Each heating zone is divided
equally, i.e. 4 rows of plena per zone.
These features combine to provide flexibility in the baking profile, as is often required where
a customer’s product portfolio is considerable.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 28
_______________________________________________________________________________
The operation of each zone’s gas burner is identical. Prior to start-up of the gas burners,
each oven baking chamber must be purged. The time period for the purge cycle is
determined by the size of the oven and the exhaust fan speed. During the purge cycle the
extraction fan will operate at full speed to maximize the evacuation of air (with potential un-
combusted gas) from the oven chamber. The turbulence fans also operate at maximum
speed to assist with mixing the air within the oven chamber. After the purge cycle has been
completed, the extraction and turbulence fan speeds can be adjusted between 40% and
100% to achieve the desired baking performance. If at any point during the purge cycle the
pressure differential switches fail to detect air flow (an inverter/fan motor fault, for example),
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 29
_______________________________________________________________________________
the purge cycle is programmed to start again from the beginning of the cycle, as a safety
precaution.
Re-circulated air is extracted from the oven chamber in each zone by each zone’s
turbulence (recirculation) fan. These fans are powered by variable speed AC drives allowing
for volumetric airflow adjustment. The air is drawn through the combustion chamber where it
is heated by a gas burner; the burner is directly-fired into the combustion chamber and heats
the re-circulating air. Safe operation of these fans is verified by a differential air pressure
switch connected across the inlet and outlet ducting (of each fan), which prove sufficient air
flow is detected at any given time.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 30
_______________________________________________________________________________
Every fan in the heating system (including oven extraction, oven turbulence and gas-fired
burner) is equipped with a dedicated differential pressure switch to prove that each particular
fan is pulling sufficient airflow when called upon to do so. The differential pressures are
taken between the intake side and discharge side of each fan. Before commencing each
purge cycle the PLC must first check all pressure differential switches throughout the entire
system are operating correctly, insomuch they signal the PLC as soon as a ‘no-flow’
situation has been detected. To do this, each time an attempt to start the burners is initiated
the PLC shuts down all oven fans & closes all extraction dampers. If operating correctly,
each pressure differential switch will then send a ‘no flow’ signal to the PLC which upon
receiving, confirms the purge sequence is safe to commence.
(Note: All extraction dampers are permitted to move from their fully-opened position at this
time)
Once the Purge Process is complete the PLC will send a ‘Burner Run Signal’ (which can be
seen on the Burner Status Popup on the Touch screen). Only at this time can the extraction
fans and turbulence fans revert to their programmed set point.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 31
_______________________________________________________________________________
When the ‘Oven Chamber Purged’ relay is latched and the ‘Burner Run Signal’ is on (i.e.
K101/201/301 are all closed), and, both the Min Gas Pressure & Max Gas Pressure switches
are healthy, each burner will be started by an individual Burner Flame Safeguard Controller
(a.k.a. burner controller or LFL). There is a dedicated burner controller for each burner in the
oven.
• Check burner fan, applicable turbulence fan, and common extraction fan pressure
switches all indicate ‘air flow’.
• After 3 seconds, the Start Gas (Pilot Gas) valves are energised
• After a further 3 seconds, the spark is turned off and Flame Rods monitor the start
gas flame. If no flame is detected, the burner controller “locks out” and requires a
manual reset – in this case, the entire sequence is started again
• Once Pilot Flame has operated satisfactorily without spark for 5 seconds, the Main
Gas valves are energised
• Following 3 seconds of Main Gas valve open, the Start Gas (Pilot) valves are closed
• The main flame is checked by the flame rod for 5 seconds and providing the flame is
stable, the burner control is released to modulation.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 32
_______________________________________________________________________________
regulates the air temperature within 2ºC of the set-point. A second thermocouple is mounted
at the exit of each combustion chamber and is connected to a temperature control relay that
functions as an over-temperature relay. This serves to shut down the burner if a temperature
in excess of 400ºC is detected.
The top/bottom divider position is adjustable to vary the ratio of heat supplied to the top and
bottom as required by the baking process. Electric actuators are fitted to control and adjust
the position of the top/bottom heat dividers.
Within the oven the air temperature of each level of the Serpentine conveying system is
monitored with a temperature probe connected to the PLC I/O modules. These probes are
intended to measure the actual air temperature of the baking chamber at each level, to
provide feedback for analysis only.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 33
_______________________________________________________________________________
• Burner output
• Turbulence fan speed
• Delivery air temperature
• Delivery damper position
• Zone temperature
• Exhaust fan speed % or exhaust damper position %
Moisture extracted from the product during the baking process is converted to steam. If
allowed to build up inside the baking chamber the steam would continue to raise the
humidity level within the oven and subsequently slow down the moisture extraction rate
necessary to complete baking within a defined period of time.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 34
_______________________________________________________________________________
Residual moisture levels in baked-off product would also be affected if excessive steam
within the baking chamber were not vented. The baker can control residual moisture level
and optimize bake times by manually setting the exhaust damper position on the HMI,
displayed as a percentage of its fully open position i.e. 100% means the damper is fully
open.
The purpose of the sensor is to stop the oven conveyor when a pan is not positioned
correctly on the carrier, or has been damaged to some degree. There is a possibility of a jam
in the oven circuit if such a pan is allowed to pass into the oven beyond this point.
1. Remove pans from carriers and cycle empty carriers into the oven such that the
entire oven is void of pans. Note: If oven is in particularly poor state and requires
aggressive scraping to remove product build-up on heater plates/plena, then
additional space can be provided by removing enough carriers from the chain circuit
to accommodate a full vacant row inside the oven. If this is done, start the line and
move the vacant section of chain to the uppermost row in the oven. Lock-off
drives on each occasion after incrementing gap, before re-commencing oven
cleaning! Carry out cleaning operation as described below, incrementing gap to the
next row below, as each subsequent row has been completed.
2. Cover all electrical switches, sensors, thermal couples, and viewing door ventilation
apertures such that all electrical components are completely watertight.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 35
_______________________________________________________________________________
3. Open oven doors. Starting from the top of the oven and working down, loosen burnt
material that has spilt onto the heater plates/plena with suitable hand held scrapers.
Use extended handle or pole for scraping middle section of plenum if unable to reach
with hand held scrapers. Thoroughly clean framework including sprocket columns,
sprockets, thermal plates of any stubborn product residue, dust, paper cases,
greases and oils etc.
4. Brush product residue from the heater plates/plena allowing it to fall down below
where it can be collected and disposed of more readily. Remove residue that has
collected on ledges or oven frames, using industrial vacuum cleaners where
necessary.
5. Working from the top level down, use compressed air to remove smaller loosened
product, making sure all oven doors are open to allow airborne product to escape
oven.
6. Scrape and remove grease & residue from chain rails and sprocket areas.
8. Working from the top level down, use town-pressure hot/warm water hose to wash
out oven internally, making sure all scraped residue and cleaning agent has been
thoroughly flushed away. DO NOT spray directly at viewing doors!
10. Replace all carriers if removed, and replace all baking pans, ensuring any damaged
units are not put back into the baking circuit.
12. Ensure all personnel are clear of the line. Unlock drives and commence start-up
procedure.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 36
_______________________________________________________________________________
4.9 ATTACHMENTS
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 37
_______________________________________________________________________________
SECTION 5
DRIVE SYSTEMS
for
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 38
_______________________________________________________________________________
• Master Drive Module. Main drive of the system located directly after the oven
inspection module (in most cases), and master to the two remaining Drive Modules.
• Secondary Drive Module. Slave to the Master Drive Module, usually located within
the Outfeed Module.
• Auxiliary Drive Module. Slave to the Master Drive Module, located in the Upper
Ambient Cooler Module in this case.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 39
_______________________________________________________________________________
The Drive units provide power from the shaft-mounted motor/gearbox via a common Drive
Cross-Shaft. Output torque is dispatched equally via Drive Sprocket Assemblies mounted
directly to the Drive Cross Shaft, propelling the Carrier Transport Conveyor Chains
incorporated on each side of the machine. The transport chain used in the system is 50.8mm
(2”) pitch roller type fitted with extended chain pins every 11 links to suit the width of baking
trays used on this machine (nominally 500mm), hence referred to as 558.8mm (22”) ‘tray’
pitch chain. Hardened-stainless steel ferules incorporated in the carrier end-assemblies
engage with these extended chain pins. When setting up the carrier transport conveyor
chain alignment, adjustable drive sprockets that can be rotated slightly and locked in position
are used to achieve accurate pin alignment from one side of the system to the other. The
main conveyor chain tensioning, overload & pneumatic control systems are described later
in this section.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 40
_______________________________________________________________________________
The Motor/Gearbox unit fitted on all three Drive Modules is identified as follows:
SEW Helical Bevel Gearmotor, 70.46/FINITE Ratio – 3.0Kw Motor - 3Ph 220V 60Hz
Part No. KA87DRE100LC4/ES7C/V-147 (Mounting Position M2)
Shaft Position B, C/W Forced Cooling Vent 220V single phase 60Hz - Speed 1455/21
Terminal Box Position 270º - Encoders Supplied & fitted by SEW
Drive # 1 is always denoted as the Master Drive and Drive # 2 (and Drive #3 where
incorporated) is denoted the Slave Drive(s). All drives are fitted with encoder feedback
motors. Drive #1 is also fitted with a linear transducer mounted to one of its take-up slides.
Here, the transducer sends information back to the PLC to slow down or speed up the next
downstream drive (Drive #2), as initiated whenever the take-up slide roams beyond a pre-
determined range within its travel limits, hence maintaining drive speed synchronisation on
an average basis. Where a third Drive Module is incorporated, a second linear transducer is
mounted to one of the take-up slides on Drive #2, where it fulfils the same duty as the first
transducer in governing speed synchronisation, this time between Drives 2 & 3.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 41
_______________________________________________________________________________
The overload cylinder is mounted in such a way as to provide resistance to the natural
pivoting action of the gearbox when reacting to varying chain loads. Sufficient resistance is
maintained by applying the correct air pressure to the cylinder to hold the overload limit
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 42
_______________________________________________________________________________
switch in the closed position. In the event that the gearbox is subjected to unusually high
chain loads, the gearbox will pivot against the resistance offered by the air cylinder/s,
allowing the overload limit switch to be released from its normal operating position. The
overload limit switch is normally depressed against the overload bracket and when fully
released will trip, causing the conveyor system to stop instantaneously. The sensitivity of
the overload system on each drive module is dependent on the air pressure applied to the
respective overload cylinder. The pressure setting for each drive module is determined
during commissioning when full production loads are established.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 43
_______________________________________________________________________________
In this instance, the overload system is probably reacting to chain surge as a consequence
of extremely dry chain, thus giving maintenance personnel prior warning the chain is in need
of lubrication. A quick check by maintenance to ensure the chain is free from any mechanical
obstruction should be undertaken. If all is well, the chain lubrication system reservoir should
be checked and filled, and the chain lubrication system manually engaged. Generally the line
will run with minor nuisance trips until such time the chain lubrication takes hold, however,
should the chain be excessively dry at this time, it may be necessary for the overload
pressure setting to be increased, ever so slightly, in order to propel the line. Only at this time
should maintenance personnel access the necessary password protected fields and make
the adjustments to the pressure setting.
The pressure setting for the Overload Sensitivity Regulator should be as low as
possible; it should enable the line to start-up and run smoothly, but will stop the line at the
slightest interference outside of normal operating conditions. The load encountered during
normal operating conditions governs the optimum pressure settings. System load will vary
during the start up and run out phases of production runs, and will also vary from one
product to another depending on selected line speed, product and pan weight. Therefore
the optimum pressure settings will involve a learning curve, erring at all times on the side of
safety.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 44
_______________________________________________________________________________
It is better to incur a nuisance trip, say once per day, rather than run the system under
protected. As such, it may be necessary to change post-commissioning settings should a
previously untested product be brought into service, or other circumstances change affecting
normal operation (such as line speed changes for example). Should this be the case, please
contact Auto-Bake before attempting to make any changes to the post-commissioning
pressure setting.
Typical cause may be dry conveyor chain due to inadequate lubrication (as used in above
example), or, chain take-up pressure set too high or too low. Should neither be the case,
please check for possible chain path obstruction. If no obstruction is found, check sprocket
bearings for noisy operation and replace suspect parts immediately. There should be no
need to alter the setting after commissioning except where a new ‘untested’ product or line
speed has been introduced into service.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 45
_______________________________________________________________________________
The Main Chain Take-Up system is situated on the ‘slack’ side of the nominated drive unit
and comprises a Chain Take-Up Cylinder mounted on each side of the machine. Each of
these cylinders is connected to their respective side Take-Up Slide assembly, which consists
of a slide plate and pair of slide rails. Tension Sprockets, which form part of the Tension
Slide assembly, engage with the conveyor chain. The Tension Slide assembly also ensures
that chain pin alignment is maintained.
There are two take-up cylinders per take-up system, (one per side of m/c). These connect in
parallel to a pressure-regulated air supply. The pressure setting is determined during
commissioning when full production loads are established. The customer’s maintenance
department should record the correct pressure setting and conduct daily checks to ensure
that the setting is maintained.
The pressure settings for the Chain Take-Up regulator should be as low as possible. It
should be set so that chain slack is ‘just’ eliminated. Excessive chain tension is
unnecessary and will result in accelerated wear of transmission components and
could cause the mechanical overload system to engage unnecessarily. The optimum
pressure setting may therefore involve some learning curve, erring at all times on the
side of safety.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 46
_______________________________________________________________________________
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 47
_______________________________________________________________________________
activated, the fault ‘Low Air Pressure’ will register on the HMI touch screen, as too, an
audible alarm will also be triggered.
5.10 ATTACHMENTS
Motor Gearbox Catalogues
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 48
_______________________________________________________________________________
SECTION 6
CONVEYOR SPROCKET
SYSTEM
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 49
_______________________________________________________________________________
Each oven sprocket assembly has a readily accessible greasing point located at the end of
each sprocket shaft that allows for periodic lubrication of the oven bearings.
The ball bearings fitted to all sprocket assemblies other than those in the oven are of the
more common type with standard clearance designation. These are pre-lubricated with
grease and sealed, therefore requiring no further maintenance during their expected
lifecycle.
The bearing housings for the oven-sprockets are the same design as those for the cooler-
sprockets, also their removal and replacement from the machine is performed in the same
manner. After relaxing the conveyor chain tension fully, the bearing housing c/w bearings
can be removed without disturbing the idler-sprockets/shafts, i.e. the sprocket can be left
engaged with the conveyor-chain.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 50
_______________________________________________________________________________
1. Fully relax the static tension of the chain on the sprocket to be removed by rotating
the sprocket in both directions to create maximum chain slack. Use a suitable lever to
rotate the sprocket in question as not to damage the parts.
2. Should the chain want to ‘run’ back, use a heavy duty ‘C’ clamp or similar ‘safe’
clamping device to prevent this occurring. Take care not to over-clamp the chain and
risk damaging it, or other components. If the clamp does not fit or clamp correctly,
discard it and obtain one that will.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 51
_______________________________________________________________________________
IMPORTANT:
The relationship between the steel chain sprocket and the alumin’m
levelling sprocket is very important; if the position of the carrier
bearing support tooth valley on the alumin’m levelling sprocket is out
of alignment with the corresponding tooth valley on the chain
sprocket (i.e. corresponding sprocket teeth are not synchronously
timed @ TDC), the carrier bearings will not engage in the levelling
sprocket correctly. This can lead to component damage. This degree
of care similarly applies to cross-shafts and all other timing
assemblies throughout the machine.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 52
_______________________________________________________________________________
1 Timing between the chain sprocket teeth and alumin’m levelling sprocket teeth can be
adjusted by sliding out the central idler timing gear from its stub shaft. This enables the
alumin’m levelling sprocket to freewheel.
2 Engage Auto-Bake supplied timing jig between the chain sprocket & alumin’m levelling
sprocket set, adopting either of the applicable methods shown below (depending if chain
connected).
3 The timing jig locator cylinder will ride upwards on the side of the levelling sprocket tooth
if timing is incorrect, as shown in below left image. When timing is correct, the timing jig
locator cylinder will sit snugly between the teeth of the levelling sprocket as shown in
below right image.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 53
_______________________________________________________________________________
4 Select any tooth valley of the alumin’m levelling sprocket initially, drop timing jig locator
cylinder into this valley as shown below and hold down firmly, then attempt to slide
central idler timing gear back onto stub shaft and engage with mating gears. If the
central idler timing gear fails to slide easily [with equidistant backlash] between mating
gears, i.e. ‘best fit’, remove central idler timing gear, raise timing jig locator cylinder
away from tooth valley and rotate alumin’m sprocket 1 tooth (in any direction). Drop
timing jig locator cylinder into new valley and hold firm, then attempt once again to slide
central idler timing gear back onto stub shaft. Repeat this process for all 14 teeth of the
alumin’m levelling sprocket (if necessary) to establish ‘best fit’.
All timing gear assemblies are set and locked at time of installation and commissioning. It is
important that these settings are not altered by anyone who does not have a full knowledge
and understanding of their application in the system.
If it is intended to remove the steel idler-sprocket and/or the alumin’m levelling sprocket from
the machine, then all cams and guides that may impede this operation will need to be
removed beforehand. Chain sprockets can be removed by moving them inwards whilst the
chain is still engaged, until such point the chain can be slipped off the sprocket.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 54
_______________________________________________________________________________
IMPORTANT:
The radial alignment between opposing chain sprockets geared to
cross-shafts is very important. Cross-shafts serve two purposes.
Firstly, by virtue of their regular spacing throughout a typical line they
ensure transport carriers are square to the machine’s longitudinal axis
as they negotiate 180º sprocket rotations. Secondly, irregular or
localised chain stretch on one side of the machine (relative to the
other side) will be ‘contained’ between upstream and downstream
cross-shaft assemblies geared to respective chain sprockets. This
results in the ‘un-stretched’ side chain pulling more of the carrier load
than the ‘stretched’ side chain (between two consecutive sets of
cross-shafts), hence tending to auto-correct unevenly stretched chain
over time.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 55
_______________________________________________________________________________
1 If possible, stop the machine when the extended chain pins are at TDC (or as near as
possible to TDC), riding on the sprocket set connected to the cross-shaft being checked.
2 Measure distance from the machine column to either the extended chain pins (if on/near
TDC), or, the actual chain sprocket tooth nearest to, but not yet passed, TDC. If
checking via extended chain pins, please ensure these pins are in pristine condition and
are not bent in any way.
3 If pins/sprocket tooth are misaligned by more than 10mm please schedule a rectification
service in near future.
In context of the following procedures the ‘Cross-Shaft Assembly’ includes all transmission
components connecting the chain sprocket on one side of the machine to the chain sprocket
on the opposite side of the machine (it does not therefore include alumin’m levelling
sprockets and levelling sprocket timing gears). There are several conditions to consider
before attempting to re-set cross-shaft alignment, and, depending on which condition is most
applicable, a different procedure may be required. These conditions are identified as follows:
• Condition #1 – Original ‘Cross-Shaft Assembly’ still exists (with all original transmission
components) and has been disassembled for routine servicing (e.g. changing bearings
by way of controlled line stop where all timing mark are aligned - per below image), and,
all transmission components are in good working condition (i.e. minimal additional
backlash has developed since new).
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 56
_______________________________________________________________________________
• Condition #2 – Original ‘Cross-Shaft Assembly’ still exists (with all original transmission
components), but upon checking cross-shaft alignment as per previously described
‘checking’ procedure, deduced extended chain pins were out of alignment by more than
10mm due to wear & tear (excessive backlash).
1 There is no need to disengage transport chain from the steel idler sprockets for routine
servicing of cross-shaft assemblies (unless the steel sprockets are in need of being
replaced, in which case Condition #3 would apply). Carriers can be removed either side
of the cross-shaft assembly being serviced if so required to improve access.
3 It may be necessary to leave one or both sides cross-shaft assembly intermediate timing
gears (red/blue dimpled gears) disengaged initially if timing marks are difficult to align.
This allows corresponding LH & RH steel chain sprockets to rotate (slightly)
independently of each other. If so, go to step 4. If intermediate timing gears can be
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 57
_______________________________________________________________________________
aligned with original timing marks and engaged with mating gears without needing to
proceed to step 4, please proceed to step 5.
4 Rotate LH steel chain sprockets and/or LH cross-shaft ‘flat’ with lever/adjustable wrench
as described in below images to align mating timing gears so that the LH intermediate
timing gear can be engaged, ensuring all original timing marks are correctly aligned.
Repeat when assembling RH intermediate timing gear.
5 Engage intermediate timing gears so that the original timing marks (dimples) all line up
as indicated below.
6 Replace intermediate cross-shaft timing gear retainer plates and fasten securely.
7 Check all is in readiness to re-start the line, when safe to do so, run the line for several
minutes to allow the new cross-shaft setting to bed-in, then stop and check extended
chain pin alignment as previously described. Do this several times to ensure timing is
consistently held.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 58
_______________________________________________________________________________
1 To remove the intermediate cross-shaft timing gear it will first be necessary to neutralise
loading on the timing teeth by rotating either the applicable chain sprocket or cross-
shaft. This can be done as depicted in below images.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 59
_______________________________________________________________________________
4 Replace intermediate cross-shaft timing gear retainer plate and fasten securely.
5 Check all is in readiness to re-start the line, when safe to do so, run the line for several
minutes to allow the new cross-shaft setting to bed-in, then stop and check extended
chain pin alignment as previously described. Do this several times to ensure timing is
consistently held.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 60
_______________________________________________________________________________
1 If possible, stop the machine when the extended chain pins are at TDC (or as near as
possible to TDC), riding on the sprocket set connected to the cross-shaft being serviced.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 61
_______________________________________________________________________________
4 Ensure carrier transport chain is engaged with all chain sprockets on both sides of the
machine; then reinstate air-supply to the chain take-up cylinders, ensuring chain is
tensioned normally.
5 Rotate applicable ‘Cross-Shaft Assembly’ chain sprocket (on same side of machine that
has been fitted with new transmission components) until the extended chain pins on
each side of the machine are aligned to within +/- 1mm of each other, (as measured per
checking procedure described previously). Since full chain tension is applied it will be
necessary to use either a lever (similarly as described in previous procedures, depicted
in below image) or pull the chain with suitable Come-A-Long. Once extended chain pins
are aligned correctly, clamp chains to rails or wedge chain sprockets to prevent chain
pin alignment slipping whilst new ‘Nordberg’ dowel holes are drilled into the new
components.
6 Using Auto-Bake supplied drilling jig, re-drill new ‘Nordberg’ dowel holes into shaft &
timing gear. If original shaft remains, rotate drilling jig so that new holes are approx 90º
to original holes. Likewise if timing gear is original, position new holes 90º to original
holes in timing gear.
Position drilling jig such that new holes are drilled approx 90º to original holes, then tighten retainer bolt &
drill holes
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 62
_______________________________________________________________________________
7 Bolt Auto-Bake supplied ‘Nordberg Dowel Insertion Jig’ to the timing gear shaft as
shown below, being careful to position the hollowed sides such that the newly drilled
dowel holes are exposed. This jig pulls together and holds firmly the cross-shaft & timing
gear assembly, allowing the ¼” dowel pins to be knocked into the new dowel holes
without pushing the shaft away. Use suitable pin punch or Auto-Bake supplied ‘Dowel
Pin Punch’ to knock pins into newly drilled dowel holes.
Nordberg Dowel Insertion Jig Dowel Pin Punch Insert dowel into hollowed end
Drive dowel pins in as far as possible using the special hollowed-out ‘Dowel Pin Punch’, then knock pin in fully
(until flush with gear) with conventional pin punch.
8 Replace intermediate cross-shaft timing gear retainer plate and fasten securely.
9 Check all is in readiness to re-start the line, when safe to do so, run the line for several
minutes to allow the new cross-shaft setting to bed-in, then stop and check extended
chain pin alignment as previously described. Do this several times to ensure timing is
consistently held.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 63
_______________________________________________________________________________
6.11 ATTACHMENTS
Position of bearing housings and sprocket assemblies
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 64
_______________________________________________________________________________
SECTION 7
LINE LUBRICATION
VERY IMPORTANT
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 65
_______________________________________________________________________________
Open Gears in Oven HOTEMP 2000 Apply with oil can once per month
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 66
_______________________________________________________________________________
Equally important is the oil type used for lubrication of the Main Conveying Chains.
The use of incorrect oil can result in ineffective lubrication. This can damage the
oven components and generate dangerous fumes and/or smoke if the oil burns.
• Chains wearing more on one side of the machine than the other, causing the pans to
skew out of square.
• Possible chain-link or chain-pin breakage.
• Increased continuous loading on the chain system (Note: this can also make it difficult to
set correct overload protection).
An air circuit controls the lubricator. Turning off the air supply isolating valve to the lubricator
will manually stop it. The lubricator is controlled by the PLC from where it can be
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 67
_______________________________________________________________________________
programmed (on/off cycles) via an electro-pneumatic solenoid valve. The on/off and pump
cycle duration, and dosage time, are controlled electronically via the HMI touch screen.
Typical Lubrication System - Dropsa units depicted located front end Infeed Module
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 68
_______________________________________________________________________________
Targeting Carrier Transport Chain Elements Typical chain oiling nozzles – 4 in total
Once in the oven, the oil administered onto the chain links runs down between the chain
plates and onto the chain pin, where it provides vital lubrication between the pin and bush
interface. The atomized spray pattern ensures adequate lubrication also reaches the working
surfaces of the chain roller, in particular the bore of the roller and the mating external surface
of the chain bush.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 69
_______________________________________________________________________________
There is a dedicated dividing valve for each spray nozzle, each metering a precise volume of
oil into respective feeder tubes, as/when the oil pump is energized. Between each pump
stroke there are individual pulses of atomized air introduced into the divider valve mixing
chamber, each pulse coinciding with the passing of every carrier. A shaft encoder driven by
the infeed chain sprockets enables very accurate targeting of the spray nozzles. There are
four spray nozzles per side, one dedicated for each carrier bearing, (8 in total per chain
circuit).
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 70
_______________________________________________________________________________
The cubic capacity of the lubricating oil reservoir is 6 litres (approx 2 US gallon). Each
reservoir is fitted with a low level sensor, which provides an analogue signal. The low
level switch can be hardwired back to an available PLC I/O block enabling a suitable
message to be displayed on the user interface touch screen. There is one reservoir
for each circuit.
Care should be taken to ensure that only clean, new oil is used in the system to
prevent damage to the pump system or clogging of the fine nozzles. Routine daily
checks by the maintenance personnel should ensure that the oil level in the reservoir
is adequate and a visual check of the deposit point of the lubricant shot to ensure that
all is functioning correctly. This takes only minutes to do.
Industry experience shows never to fully trust any automated lubricating system.
Always check! Never underestimate the importance of correct lubrication in any
continuous automated system especially when an oven is involved.
It is important that the changes made to the oiler at the touch screen are checked
through to each formulation, i.e. the changes made only affect the specific product
which is selected.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 71
_______________________________________________________________________________
7.7 ATTACHMENTS
MSDS KLUBERFOOD NH1 CH 2-220
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 72
_______________________________________________________________________________
SECTION 8
OUTFEED MODULE
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 73
_______________________________________________________________________________
The OLP assembly is integral with the secondary drive unit, incorporating a crank wheel for
propulsion that is driven directly by a transmission chain connected to one of the carrier
transport chain idler sprockets within the Outfeed Module. A series of crank arms and slide
arrangements connect to a pair of Pusher Arms, which in turn bolt to the actual Pusher
Bar. The Pusher Bar is a channel section member with a UHMW-PE strip inserted to prevent
metal to metal contact with the trays.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 74
_______________________________________________________________________________
Because the Off-Load Pusher assembly is mechanically linked to the carrier transport chain
circuit, the Pusher Bar movement is synchronized with the carriers. The timing chain ensures
the pusher movement always complete the pan off-load cycle and is retracted before the
next descending free-tray carrier passes through the Depanning Zone, irrespective of line
speed.
The separated pan is pushed away from the Auto-Bake line onto conveyor (C1), which is
located in-line immediately downstream of the Outfeed Module. This transfer conveyor
moves trays away from the Auto-Bake line and under the Injection Unit (manufactured by
Comas). When the pusher bar is fully extended the pan is fully on-board this conveyor. The
extended position of the pusher arm is detected by an inductive sensor, which is mounted
within the right hand side of the outfeed/drive module.
Empty carriers travel back towards the oven infeed module passing under the lower Ambient
Cooler en-route.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 75
_______________________________________________________________________________
SECTION 9
CONVEYOR CIRCUIT
SYSTEM
(CCS)
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 76
_______________________________________________________________________________
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 77
_______________________________________________________________________________
Conveyor C2
Conveyor C3
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 78
_______________________________________________________________________________
Conveyor C4
9.1.5 Function of Conveyor C5
Conveyor C5 is a straight Slat-Belt conveyor approx 9.2m in length that delivers pans wide-
edge leading from C4 conveyor to the entrance tunnel of the Colussi in-line tray washer. This
conveyor is driven by a Gearmotor which also drives C4 conveyor via mechanical linkages.
C5 is not equipped with brakes or gates. All standard length pans (Ring Cake & Fudge Bar)
are automatically fed directly into the Colussi washer on C5 centreline. When shorter
Croissant trays are to be washed & dried, these are manually loaded onto C5 at the
immediate entrance of the Colussi Washer, and then manually removed from the system as
soon as the clean trays emerge from the washer. When manually loading the Croissant trays
onto C5, the trays are not loaded on the conveyor’s centreline, instead they are biased to the
left side, resting against the left side tray guide rail. This enables the shorter Croissant pans
to pass safely through the Colussi Washer riding on only the central and left side transport
chains.
Conveyor C5
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 79
_______________________________________________________________________________
Conveyor C6
9.1.7 Function of Conveyor C7
Conveyor C7 is a straight stainless steel ‘dogged’ Slat-Belt conveyor approx 7.8m in length
that positively conveys pans wide-edge leading from C6 to C8 via three ancillary equipment
workstations. Here, a Dubor Pan Greaser occupies Work Station #1, and the customer’s
own Depositor occupies Work Station #3. Work Station #2 is available for future ancillary
equipment, such as a Paper Cup Denester. Each work station has adjustable side guides to
ensure centreline accuracy of trays whilst travelling under respective ancillary machines. The
conveyor is not fitted with tray brakes or gates. It is propelled by mechanical linkages
connected to next downstream conveyor (C8).
Conveyor C7
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 80
_______________________________________________________________________________
Conveyor C8
9.1.9 Function of Conveyor C9
Conveyor C9 is the third in line of four 90º transfer conveyors incorporated into the CCS and
uses the same belting and pan guide arrangement as described for C2. It delivers pans
wide-edge leading from the decline conveyor (C8) to the straight conveyor (C10), which
provides propulsion to this conveyor via connecting mechanical linkages. C9 is not equipped
with brakes or gates.
Conveyor C9
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 81
_______________________________________________________________________________
Conveyor C10
9.1.11 Function of Conveyor C11
Conveyor C11 is the last in line of four 90º transfer conveyors incorporated into the CCS and
uses the same belting and pan guide arrangement as described for C2. It delivers pans
wide-edge leading from conveyor C10 to the Infeed Module. C11 is the only 90º transfer
conveyor with its own dedicated drive gear motor; in all other aspects it is identical to the
other three 90º conveyors.
Conveyor C11
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 82
_______________________________________________________________________________
As the pans pass under the diffuser tubes a jet of air penetrates between the product and
the cavity wall, tearing bondage & propelling the product upwards away from the captive
cavity. A special hold-down plate prevents the now hovering product from escaping; allowing
the product to fall gently back into the cavity it was baked in once the effect of the air blast
abates. The product, whilst now sitting in the same cavity, is no longer ‘bonded’ to this
cavity; it is loose and ready to be depanned.
An adjustable support frame located at each end of the pre-release manifold enables the
manifold to be lowered easily (without tools) during Ring Cake production, and then raised
back up again out of the way when Ring Cake production has been completed.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 83
_______________________________________________________________________________
Typical construction – inner & outer tubes, diffuser tubes, air blast nozzles &
hold-down plate
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 84
_______________________________________________________________________________
The Auto-Bake line is equipped with a Robotic Product Depanning System (a.k.a. Pick and
Place, or, P&P) located downstream of the Outfeed Module within the Conveyor Circuit
System (CCS). The P&P has been developed especially for handling products that are
baked on the Auto-Bake Level Tray System (LTS) series ovens. This particular system is
referred to as a dual-head system as there are two individual needle heads attached to the
robot tool head, servicing two pans simultaneously at a time. The P&P system consists of
the following main elements:
The essential principal of the P&P system is to pick product out of the baking pans and
deliver this product to the downstream conveyor for further processing. This task is
accomplished by positioning the needle head in correct alignment directly over the particular
pan where product is to be removed. At a signal from the controlling PLC, the robot tool arm
supporting the needle head descends to a precise depth allowing the ‘retracted’ needles to
hover just above the top surface of the product in each cavity. At the appropriate time, the
needles are extended and penetrate deep into the baked product. The ‘curved’ trajectory of
each needle impales the product in such a way that the product remains ‘captured’ by the
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 85
_______________________________________________________________________________
needle as the robot tool arm pulls away. The needle head with its payload of product firmly in
its grasp moves to a new position above the take-away conveyor. The needles retract
liberating the product on demand. Upon release, the needle head returns to the pick-up point
once again in readiness for the next cycle.
The Auto Bake P&P system requires little day-to-day attention, apart from routine
cleaning of the needle heads. Small pneumatic cylinders operate needle actuation. The air-
supply to these cylinders passes through a combined pressure-regulator and filter-unit. The
air-pressure should not be set excessively high and the filter-unit bowl must be drained
routinely.
Refer to the separate manual for, Daily, Weekly and Monthly, ‘Operation, Care and
Maintenance’ of the ABB IRB 6640 ROBOT unit.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 86
_______________________________________________________________________________
SECTION 10
GENERIC PREVENTATIVE
MAINTENANCE
SCHEDULE
for
AUTO-BAKE SUPPLIED EQUIPMENT (only)
PLEASE REFER RELEVANT OEM MANUALS FOR EQUIPMENT NOT
MANUFACTURED OR SUPPLIED BY AUTO-BAKE
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 87
_______________________________________________________________________________
Chain &
Carrier
Bearing
Lube
System
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 88
_______________________________________________________________________________
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 89
_______________________________________________________________________________
Product
Depanning
Systems Check operation & condition of product Replace/repair components if defective.
where depanning heads, control mechanisms,
incorporated needles/vacuum cups, robot (per OEM
instructions), etc.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 90
_______________________________________________________________________________
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 91
_______________________________________________________________________________
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 92
_______________________________________________________________________________
Oven
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 93
_______________________________________________________________________________
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 94
_______________________________________________________________________________
Tighten if loose.
Visually check all Level Tray Guides are
securely fastened.
Carriers should be parallel to each other
and be squarely aligned at each cross-
General
Inspect carriers at every cross-shaft sprocket shaft sprocket turn throughout the
turn to ensure they are reasonably square to machine. Corresponding chain pins on
the machine. each side of the cross-shaft should be
aligned to within 5mm (or better). If
alignment is out by more than 5mm,
check condition of cross-shaft &
couplings, and replace as required.
Flange &
Plummer Refer Generic Lubrication Schedule.
Bearings Lubricate flange/plummer bearings
throughout
Refer to gearbox manufacturer’s
Drive
information for correct level and
Unit(s)
Check all gearbox oil levels. periodic changing of oil.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 95
_______________________________________________________________________________
SECTION 11
GENERIC SANITATION
SCHEDULE
for
AUTO-BAKE SUPPLIED EQUIPMENT (only)
PLEASE REFER RELEVANT OEM MANUALS FOR EQUIPMENT NOT
MANUFACTURED OR SUPPLIED BY AUTO-BAKE
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 96
_______________________________________________________________________________
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 97
_______________________________________________________________________________
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 98
_______________________________________________________________________________
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 99
_______________________________________________________________________________
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 100
_______________________________________________________________________________
SECTION 12
TROUBLE SHOOTING
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 101
_______________________________________________________________________________
1. If replacing missing carriers, chain pins must be checked for straightness. Any bent pins must be
replaced. When replacing chain pins, always replace same on both sides of the line, regardless
of whether the other side is damaged or not. Potential risk of jamming the line can result
if/when carriers are installed on bent pins!
2. Make sure all PM’s are completed. Auto-Bake ovens operate more reliably and efficiently
when well-maintained!
3. Make sure operators do not mistreat the machine in any way. Heavy-handed loading of trays onto
carriers, for example, can result in damage to carrier bearings. If unchecked, these bearings can
come apart and lose the tiny ball bearings. A single carrier bearing ‘ball’ can jam the Auto-
Bake machine if lodged between the chain and a sprocket tooth!
4. If the line happens to stop on mechanical overload, do not allow operators to restart the line
without a first having a qualified maintenance technician check out the root cause. If this is not
adhered to, it is recipe for disaster! The mechanics should do a quick ‘once-over’ of the line
before trying to restart. If no obvious cause for the stoppage is found, then, (and only then),
should the line be reset and restarted. If the line stops once more on overload, then there is very
likely a mechanical obstruction somewhere on the chain circuit. Never bypass overload
switches! If the line trips there is usually a very good reason for so doing. Not finding the root-
cause will spell trouble in the long run if ignored.
5. If a mechanical obstruction occurs, the timing on the sprockets must be checked in the general
area of the obstruction. No exceptions! Also, please check chain pin alignment in the same
vicinity.
6. If a mechanical obstruction occurs, please check all carriers in the general vicinity are straight and
not damaged in any way. It may not be the carrier(s) at the epicentre of the obstruction that
caused the fault. Likewise, it may not be the carrier(s) at the epicentre of the obstruction that are
damaged. A damaged carrier may have ‘caused’ the initial obstruction by first damaging
components in the area, then moving on unscathed for possibly several serpentine rows, before
the damaged it inflicted to the components previously causes subsequent carrier(s) to jam. Be
aware of this, it is a trap for young players!
7. Have maintenance technicians ‘walk the line’, once or twice a shift, remove covers and listen for
strange noises.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 102
_______________________________________________________________________________
8. Allocate sufficient maintenance time to ensure the well-being of the Auto-Bake line generally. The
tasks can be broken down into small activities, for example, ‘check the oven this week’, ‘check the
drive next week’ and so forth.
9. Grease all bearings according to the PM’s, schedule tasks to actually go looking for loose bolts,
worn parts, timing errors, debris contamination, etc. The basic parts of the machine are the same
throughout the machine. Look for things that do not look right!
10. Fix the problem ‘as soon as possible’. Leaving chain misalignment or incorrectly timed sprockets
for ‘another day’, as an example, increases the opportunities for bending carriers or causing
damage elsewhere throughout the chain circuit.
11. Acquire a training setup from Auto-Bake, which consists of a set of LTS sprockets mounted in a
bench frame. This will allow training of maintenance technicians ‘off-line’ on how to time LTS
sprockets properly and how to change out bearings housed within these sprocket assemblies.
TROUBLE SHOOTING CHAIN PATH
PROBLEM POSSIBLE CAUSE POSSIBLE SOLUTION
Machine won't start. ‘E’ stop circuit is tripped. Check all safety switches and
re-set if necessary.
Many carriers damaged in the Mechanical overload set too Adjust to setting at time of
event of a mechanical jam. high. commissioning.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 103
_______________________________________________________________________________
Carriers not square to line. Chain pins out of alignment. Re-set cross-shaft in that area.
Carriers not located beneath Position of ancillary. Measure and check position.
ancillary equipment correctly.
Carriers not level in vertical Vertical guides not adjusted Re-set guides to have 1-1.5mm
transfer modules. correctly. clearance on both carrier
bearing and chain.
Carriers not level around turn Timing incorrect between Re-set timing: Refer Section 6
over sprocket. gears. attachment.
Carriers have bent ferrules Timing incorrect between Re-set timing: Refer Section 6
(horizontally). gears. attachment.
Carriers have bent ferrules Personnel walking on carriers Instruct personnel not to walk
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 104
_______________________________________________________________________________
TROUBLESHOOTING - PRODUCT
Depositing equipment not Signal from Auto-Bake. Check corresponding relay in
working.
Junction Box 1
Check isolator.
Damage to top of product. Turbulence tube fallen. Re-fit and tighten fittings & grub
screw. Screw one side only to
allow for expansion.
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 105
_______________________________________________________________________________
SECTION 13
SPARE PARTS
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 106
_______________________________________________________________________________
SECTION 14
ANCILIARY EQUIPMENT
14.1 ATTACHMENTS
Comas Injector
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 107
_______________________________________________________________________________
SECTION 15
HMI TOUCHSCREEN
15.1 ATTACHMENTS
Touchscreen Operations Manual
LTS OPERATIONS & MAINTENANCE MANUAL - SUNCREST LINE #7 - W/O 5128 - JULY 2013 108