Final Copy

PRE-ARRANGED JOBS
W e e k N o. 26
(June 26, 2017 - July 02, 2017)
Print Date & Time: 06-22-17 10:01 AM

To All Requesting Offices:

Please take note of the following guidelines:

1. Pre-arranged circuit interruption must be limited to once in fifteen (15) days. Momentary interruptions not
exceeding thirty (30) minutes are not counted.

2. Request for interruption with customers affected shall not exceed five (5) hour duration. Any request
exceeding five hours shall require the approval of Requesting Office's Distribution Head.

3. Observe on-time submission of original copy of RPJ (3 copies). Deadline for submission is every 4:00 PM of
Monday for jobs covering Monday to Sunday of a next succeeding week. Late submission would mean resetting
of the job for another week. Sending copy of RPJ through fax will only serve as an advance notice to OPU but it
is not a means of beating the deadline. It is therefore suggested that requesting party shall prepare their RPJ
earlier and submit to OPU on time. No original copy of RPJ would mean non-inclusion of job in the final PAJ
summary.

4. For jobs falling under the category of 'hazardous' request, Requesting Office shall see to it that RPJ are in the
custody of Operations Planning not beyond 1400H of the day immediately before the interruption. For those
falling under the category of 'urgent' request, RPJ should be submitted at least three (3) days before the
interruption. RPJ submitted beyond these time frames will be reset in order to meet the said time frame. This is
to provide us sufficient time to analyze and prepare a job summary for the said job and for Call Center to make
proper advisory if there are affected customers. For purposes of clarification, 'urgent' and 'hazardous' request is
defined below:

'Hazardous' conditions are any abnormalities on line or equipment that may endanger life or property and has to
be corrected within forty eight (48) hours

'Urgent' conditions are those abnormalities that need to be corrected or management initiated projects which
need to be executed within seven (7) days

5. Advanced copy is available every Tuesday and the final copy every Thursday. The final copy includes the
corrections/revisions and additional jobs (in blue fonts) covered by the pre-arranged job week. For more
inquiries, contact us at locals 6457 and 6772. However, Operations Planning will not entertain inquiries if the
subject of the inquiry is only the schedule of the job. It is our intent that all requesting parties should read and
verify their schedules through this Pre-Arranged Job Summary.

6. Heads with access to e-mail should provide copy of Job Summary to all supervisors directly involved to
countercheck their schedule with the Pre-Arranged Job Summary as well as the accuracy of the Job Summary
involving their job. Operations Planning will not be liable for cancellation of jobs on the date of interruption
due to inaccurate request or for failure to verify the schedule in the Final copy of the Pre-Arranged Job
Summary.

7. For all PAJs which will affect the station service transformer, the requesting party shall specifically indicate
it in their submitted RPJs.

8. This PAJ summary does not include Additional PAJs which may be accommodated and scheduled within the
same week. Instead, Lotus Notes Advisories will be sent to involved offices regarding these additional PAJs.

9. Any caution request by performing crew relative to a PAJ shall be made to Delta by the former before the
start of the job.

10. Any scheduled job maybe cancelled or modified as needed and involved offices will be properly advised.

1
Final Copy

Monday, June 26, 2017 - Tuesday, June 27, 2017

Job # 1 0800H - 0600H Code : 17-015561/016015


a) De-energize: 1. Balintawak 115kV bus no. 2
2. Balintawak 300MVA bank no. 1 and associated GCBs
3. Balintawak-Sta. Mesa 115kV line 63E-61F - 0001H to 0300H
4. Balintawak-Bagbaguin 115kV line 64E-62YZ - 0301H to 0600H
b) Reason: 1. Replacement of GCB 63E8 and its corresponding D.S. 63E7/9 as part of the project "Uprating of
115kV GCBs at Balintawak substation" W.O.#P1602000375
2. Wiring of 63E8 alarms, control and protection.
3. Functional testing of 63E8 alarms, control and protection.
4. Line stability test (63E8 vs 63E4) and bus stability test (63E8 vs 64E8)
c) Clearance: E.A.S. Dimapilis/D.J.B. Regalado
d) Performing Crew: PSP PSAS/North O&M, Substation North O&M/Construction, Testing
e) Customer Affected: NONE
f) Notes: 1. Unload Meycauayan, Marilao & Saog substations then shift Diliman banks 2 & 3 to Sector 2 as N-1
contingency for item a.4.
2. NGCP was advised.

Job # 2 2300H - 0600H Code : 17-015958


a) De-energize: Dolores-Manggahan-Marikina 115kV line 65XM-61ZM-6 4VG
b) Reason: Correction of several overheating line components along Dolores-Manggahan-Marikina 115kV line
(EAM WO 100269039496):
1. Pole no. G13-59T along L. Wood St., Dolores, Taytay, Rizal
2. Pole no. H10-142T along Ortigas Ave. Extn., Pasig City
3. Pole no. K10-6T along J.P. Rizal St., Marikina City
4. Pole no. K9-169T along Marcos Highway, Marikina City
c) Clearance: L.N.D.L. Medina
d) Performing Crew: STL Central O&M
e) Customer Affected: 2300H to 0600H
Midland Steel
f) Notes: 1. Shift loads of Manggahan s/s to adjoining ckts. prior to interruption.
2. Midland Steel will be affected.
3. NGCP was advised.

Tuesday, June 27, 2017

Job # 3 0001H - 0500H Code : 17-015966


a) De-energize: 1. Portion of LISP 34.5 kV ckt. 412ZQ, bounded by LISP substation, normally open LBS
412ZQ13 and opened "hot" temporary LBS on pole #DF4-0101- NO CUSTOMER
2. Portion of LISP 34.5kV ckt. 413ZQ, bounded by opened temporary LBS on pole #DF3-
0180, opened "hot" LBS 413ZQ11 and disconnected "hot" 3 -20 kV jumpers on pole #DF3-
0182 – NO CUSTOMER
b) Reason: 1. Replacement of 7 spans of 3-phase bare ACSR wires with covered conductors; size 336 MCM of
ckt. 413ZQ
2. Installation of tandem pole (15-meter concrete) on pole #DF3-0182 to accommodate
recommended wire conversion
3. Replacement of aging insulators on ckts. 413ZQ and 412ZQ (4 and 7 poles respectively)
Related to Planned MA: P1702049774
c) Clearance: L.S. Badayos
d) Performing Crew: Sta. Rosa Construction II
e) Customer Affected: NONE
f) Notes: 1. Install caution tags on LISP ckts. 410ZQ, 413ZQ, 416ZQ and Carmelray ckts. 416WQ & 426WQ.
2. Shift unaffected portions of LISP ckts. 412ZQ & 413ZQ to adjoining ckts. prior to interruption.
3. Observe proper procedure in "hot" disconnection of abovementioned jumpers.

Job # 4 0830H - 1330H Code : 17-015763


a) De-energize: Portion of North Port 34.5kV ckt. 403H, bounded by opened “hot” LBS 47H13R, opened
RCLR 403Hr3 (K3-2540) and disconnected 3-34.5kV jumpers on pole # K3-0031-T along
Ugbo cor. Jacinto Sts., Tondo, Manila.

2
Final Copy

b) Reason: Replacement of rotted wood pole (K3-1015) and re-conductoring of 3-spans to 3#336.4 MCM TW
ACSR from pole no. K3-1015 to K3-0031-T along Velasquez St. corner Ugbo St., Tondo, Manila
under 2017 Planned MA P1701003116.
c) Clearance: W.C.P. Amaca
d) Performing Crew: Manila Construction 2, Manila Maintenance
e) Customer Affected: 0830H-0900H then again 1300H-1330H
1. Portion of North Port 34.5kV ckt. 403H, bounded by disconnected 3-34.5kV jumpers on pole # K3-0031-T
along Ugbo cor. Jacinto Sts., Tondo, Manila, normally open LBS 47H15R & 43VM13 and opened RCLR
403Hr2 (K3-2337).
0830H to 1330H
2. Portion of North Port 34.5kV ckt. 403H, bounded by opened “hot” LBS 47H13R, opened RCLR 403Hr3
(K3-2540) and disconnected 3-34.5kV jumpers on pole # K3-0031-T along Ugbo cor. Jacinto Sts., Tondo,
Manila.
f) Notes: 1. Shift unaffected portions of the line to adjoining circuits prior to interruption.
2. Item e1 will be de-energized twice to allow disconnection & reconnection of jumpers. Said portion
will be shifted to adjoining circuit after disconnection of jumpers.
3. Install caution tag on North Port 34.5kV ckt. 403H.

Tuesday, June 27, 2017 - Wednesday, June 28, 2017

Job # 1 2230H - 0530H Code : 17-015923


a) De-energize: 1. Portion of Cainta 34.5kV ckt. 42XG, from disconnected “hot” 3-34.5kV jumpers on pole
#H10-0165-T along Ortigas Ave. cor. De Castro St., Pasig City up to opened LBS 42XG19R
- NO CUSTOMER
2. Portion of Cainta 34.5kV ckt. 421XG, from opened temporarily installed LBS on pole #H10-
0166-T along Ortigas Ave. near De Castro St., Pasig City up to disconnected “hot” 3-34.5kV
jumpers on pole #H10-1534 along Ortigas Ave. near One Oasis, Pasig City.
b) Reason: Re-conductoring to 3-336.4 MCM Tree Wire and re-configuration of main lines due to BWS and
structures along Ortigas Ave. near De Castro St., Pasig City (10 spans from pole nos. H10-1534 up
to H10-0165-T).
c) Clearance: D.D. Mendoza
d) Performing Crew: Pasig Maintenance Implementation Team
e) Customer Affected: 2230H to 0530H
1. Portion of Cainta 34.5kV ckt. 421XG, from opened temporarily installed LBS on pole # H10-0166-T
along Ortigas Ave. near De Castro St., Pasig City up to disconnected “hot” 3-34.5kV jumpers on pole #
H10-1534 along Ortigas Ave. near One Oasis, Pasig City.
f) Notes: 1. Shift unaffected portions of the lines to adjoining circuits prior to interruption.
2. Install caution tags on Cainta ckts. 42XG & 421XG and Hillcrest ckt. 412VZ at RCLR 412VZr1.

Job # 2 2300H - 0500H Code : 17-015937


a) De-energize: Cubao 83MVA transformer bank #3.
b) Reason: Warranty test of transformer bank and checking & sealing of transformer safety devices.
c) Clearance: R.S. Rillera
d) Performing Crew: PSP COM, Substation COM, Testing
e) Customer Affected: NONE
f) Notes: Utilize bus-tie VCB 50VQ834 during the job.

Job # 3 2300H - 0600H Code : 17-015934 and 17-015976


a) De-energize: Bagbaguin-Meycauayan 115kV line 63YM-61YZ
b) Reason: PSP job:
Replacement of TCSR and functional test of control, protection & alarms of 63YM4.
STL job:
Erection and dressing of several 90ft concrete poles along Malhacan Rd, Meycauayan affected by
road widening project of DPWH.
c) Clearance: M.C. Argabioso/L.A. Ragasa
d) Performing Crew: Substation North O&M, STL North O&M, PSP North O&M
e) Customer Affected: NONE
f) Notes: 1. NGCP was advised.
2. This job was originally scheduled June 29-30, 2017.

3
Final Copy

Job # 4 2300H - 0600H Code : 17-015951


a) De-energize: 1. Portion of Marikina 34.5kV ckt. 41VG, from disconnected 3-34.5kV jumpers on pole #L9-
0090-T along Katipunan Ave. cor. XavierVille Ave., Q.C. up to opened temporarily installed
LBS on pole # K9-1543 along Aurora Blvd., Q.C.
2. Portion of Marikina 34.5kV ckt. 46VG, from disconnected 3-34.5kV jumpers on pole #L9-
0947-T along Katipunan Ave. near cor. XavierVille Ave., Q.C. up to disconnected “hot” 3-
34.5kV jumpers on pole # K9-0148-T along Katipunan Ave. near cor. Aurora Blvd., Q.C.
- NO CUSTOMER
3. Portion of Cubao 34.5kV ckt. 432VQ, in-between 2 sets of disconnected 3-34.5kV jumpers;
one on pole # K9-0148-T along Katipunan Ave. near cor. Aurora Blvd., Q.C. and the other
one on pole # K9-0151-T along Katipunan Ave. near cor. XavierVille Ave., Q.C.
b) Reason: Re-conductoring to 3-336.4 MCM per circuit (18 spans) due to several BWS and structures along
Aurora Blvd. and Katipunan Ave., Q.C. (from pole no. K9-0068-T up to pole no. L9-0947-T).
c) Clearance: D.D. Mendoza
d) Performing Crew: Pasig Maintenance Implementation Team
e) Customer Affected: 2300H-2330H then again 0530H-0600H
1. Portion of Marikina 34.5kV ckt. 41VG, from Marikina s/s up to disconnected 3-34.5kV jumpers on pole
#L9-0090-T along Katipunan Ave. cor. XavierVille Ave., Q.C.
2300H to 2330H
2. Portion of Marikina 34.5kV ckt. 46VG, from Marikina s/s up to disconnected 3-34.5kV jumpers on pole
#L9-0947-T along Katipunan Ave. near cor. XavierVille Ave., Q.C.
2300H-2330H then again 0530H-0600H
3. Portion of Cubao 34.5kV ckt. 432VQ, from opened “hot” LBS 42VG11 up to disconnected 3-34.5kV
jumpers on pole # K9-0148-T along Katipunan Ave. near cor. Aurora Blvd., Q.C.
4. Portion of Cubao 34.5kV ckt. 432VQ, from disconnected 3-34.5kV jumpers on pole #K9-0151-T along
Katipunan Ave. near cor. XavierVille Ave., Q.C. up to normally open LBS 42VG13.
2300H to 0600H
5. Portion of Marikina 34.5kV ckt. 41VG, from disconnected 3-34.5kV jumpers on pole #L9-0090-T along
Katipunan Ave. cor. XavierVille Ave., Q.C. up to opened temporarily installed LBS on pole #K9-1543
along Aurora Blvd., Q.C.
6. Portion of Cubao 34.5kV ckt. 432VQ, in-between 2 sets of disconnected 3-34.5kV jumpers; one on pole
#K9-0148-T along Katipunan Ave. near cor. Aurora Blvd., Q.C. and the other one on pole #K9-0151-T
along Katipunan Ave. near cor. XavierVille Ave., Q.C.
f) Notes: 1. Shift unaffected portions of Marikina ckts. 41VG & 46VG to adjoining ckts. prior to interruption.
2. Items e.1, e.2, e.3 & e.4 will be de-energized twice to allow disconnection & reconnection of
jumpers. Item e.4 will be shifted to adjoining circuit after disconnection of jumpers
3. Install caution tags on Marikina ckts. 41VG & 46VG and Cubao ckts. 42VQ & 432VQ.
4. Open "hot" FCOs of TLNs 126495, 126496 & 126569 (all included in Item e.2) prior to "hot"
disconnection of jumpers on pole #K9-0148-T. Said TLNs will be re-energized after disconnection
of jumpers on pole # L9-0947-T.

Job # 5 2330H - 0500H Code : 17-016000


a) De-energize: Ayala Alabang-Pamplona 115kV Line 66WR-61XD
b) Reason: Replacement of rotted pole CV8-9T & CV8-856T along Zapote Road, Muntinlupa City related to
EAM P1701004321 & P1706000661
c) Clearance: Julio U. Leopando Jr.
d) Performing Crew: STL South O&M
e) Customer Affected: NONE
f) Notes: 1. Pamplona s/s will be radially fed by Zapote-Bacoor-Pamplona 115kV line 71WV-61/62WX-63XD
while Filinvest & Ayala Alabang substations will be radially fed by Sucat-Filinvest 115kV line
67SC-61FIL during the job.
2. NGCP was advised.

Wednesday, June 28, 2017

Job # 6 0001H - 0600H Code : 17-015843


a) De-energize: Dila 83 MVA transformer bank
b) Reason: Monitoring test of power transformer.
c) Clearance: J.G. Pascual
d) Performing Crew: Electrical Testing, Substation - SOM, PSP - SOM

4
Final Copy

e) Customer Affected: NONE


f) Notes: 1. Shift loads of above bank to adjoining ckts. prior to interruption.
2. This job was originally scheduled June 27, 2017.

Job # 7 0800H - 1300H Code : 17-015949


a) De-energize: Portion of Sun Valley 34.5 kV ckt. 42WG, from opened "hot" 3-temporary LCOs on pole
DY1-0149 along Severina Industrial Estate, Marcelo Green Vill., Paranaque, Metro Manila up
to the end of line.
b) Reason: Replacement of tanalized pole (no. DY1-0352)
c) Clearance: R.R. de Quiroz
d) Performing Crew: Parañaque Sector Construction Team 2
e) Customer Affected: 0800H to 1300H
Portion of Sun Valley 34.5 kV ckt. 42WG, from opened "hot" 3-temporary LCOs on pole DY1-0149 along
Severina Industrial Estate, Marcelo Green Vill., Paranaque, Metro Manila up to the end of line.
f) Notes: Install caution tag on ckt. 42WG served by RCLR 42WGr1.

Wednesday, June 28, 2017 - Thursday, June 29, 2017

Job # 1 2200H - 0700H Code : 17-015955


a) De-energize: Kamagong 34.5kV bus # 1.
b) Reason: Replacement of control plugs of PCBS and functional testing of protection control & alarms.
c) Clearance: M.A.P. Lavado
d) Performing Crew: PSP COM, Substation COM
e) Customer Affected: NONE
f) Notes: 1. Shift loads of above bus to adjoining circuits prior to interruption.
2. Station service will be affected.

Job # 2 2300H - 0400H Code : 17-015723


a) De-energize: Portion of Ayala Alabang 34.5 kV ckt. 422WR, bounded by Ayala Alabang s/s, normally open
LBS 422WR13 and disconnected "hot" 3-34.5kV jumpers on pole #DU1-2437.
b) Reason: Re-conductoring of 16 spans of dilapidated covered conductor from pole #CU9-0737 to pole #DU1-
2437.
c) Clearance: I.C.G. Lazaro
d) Performing Crew: Paranaque Sector Maintenance crew
e) Customer Affected: 2300H to 0400H
Portion of Ayala Alabang 34.5 kV ckt. 422WR, bounded by Ayala Alabang s/s, normally open LBS
422WR13 and disconnected "hot" 3 - 20 kV jumpers on pole DU1-2437.
f) Notes: 1. Shift unaffected portion of Ayala Alabang ckt. 422WR to adjoining ckt. prior to interruption.
2. Install caution tag on Filinvest 34.5 kV ckt. 414FIL.

Job # 3 2300H - 0500H Code : 17-015954


a) De-energize: Parang feeder VCB 415YL4.
b) Reason: Installation of CSF, checking of wiring termination of control plugs and functional testing of
protection control & alarms.
c) Clearance: M.A.P. Lavado
d) Performing Crew: PSP COM, SCADA COM
e) Customer Affected: NONE
f) Notes: Shift load of above feeder VCB to adjoining circuit prior to interruption.

Job # 4 2300H - 0500H Code : 17-015957


a) De-energize: NAIA-3 83MVA transformer bank # 1, high side GCB 62VX4 & low side VCB 411VX4.
b) Reason: 1. Replacement of AVR relay for OLTC.
2. Installation of remote control and indication for OLTC.
3. Functional testing of protection control and alarms.
c) Clearance: M.A.P. Lavado
d) Performing Crew: PSP COM, PSP PSAS, SCADA COM, Substation COM
e) Customer Affected: NONE
f) Notes: Shift loads of above transformer bank to adjoining circuits prior to interruption.

Job # 5 2300H - 0500H Code : 17-016014


a) De-energize: 1. Portion of Meycauayan 34.5kV ckt. 52YM, bounded by Meycauayan s/s, normally open

5
Final Copy

LBS’ 45YM19 & 43YM13 and opened LBS 52YM11.


2. Portions of Meycauayan 34.5kV ckt. 42YM:
a. From opened “hot” RCLR 42YMr1 (pole #U4-0570) along Camalig Rd., Meycauayan,
Bulacan up to normally open LBS 42YM13.
b. From opened “hot” temporary LBS on pole #V4-0514 along Muralla Industrial Rd.,
Muralla Subd., Meycauayan, Bulacan up to the end of the line.
(Note: Maintenance Team work area)
b) Reason: Relocation of facilities affected by DPWH road widening project and Upgrading of existing
facilities at Meycauayan, Bulacan under EAM WO:P1701005624, P1701005623, P1701005622,
P1701005589 & P1701005586.
c) Clearance: A.A. Cruz
d) Performing Crew: Valenzuela Sector Maintenance Team 1, Valenzuela Sector Construction Team 1
e) Customer Affected:
2300H to 0500H
1. Portion of Meycauayan 34.5kV ckt. 52YM, bounded by Meycauayan s/s, normally open LBS’ 45YM19
& 43YM13 and opened LBS 52YM11.
2. Portions of Meycauayan 34.5kV ckt. 42YM from opened “hot” RCLR 42YMr1 (pole #U4-0570) up to
normally open LBS 42YM13.
3. Portions of Meycauayan 34.5kV ckt. 42YM from opened “hot” temporary LBS on pole #V4-0514
along Muralla Industrial Rd., Muralla Subd., Meycauayan, Bulacan up to the end of the line.
f) Notes: 1. Shift unaffected portion of the line to adjoining circuits prior to interruption.
2. Install caution tags on Meycauayan 34.5kV ckts. 52YM and 42YM.

Job # 6 2300H - 0600H Code : 17-015959


a) De-energize: Marikina-Masinag 115kV line 62VG-63WN
b) Reason: Pole erection along Marcos Highway for the relocation of 115kV facilities affected by the
construction of LRT2 Extension infront of Robinson Mall (WO R14853354)
c) Clearance: L.N.D.L. Medina
d) Performing Crew: Sub-Transmission Lines Central O&M
e) Customer Affected: NONE
f) Notes: 1. Masinag & Parang s/s will be radially fed by Dolores-Masinag line 64XM-62WN during the job.
2. NGCP was advised.

Job # 7 2300H - 0600H Code : 17-015861


a) De-energize: Portion of Manggahan 34.5kV ckt. 45ZM, from disconnected “hot” 3-34.5kV jumpers on pole #
I10-0072 along M.L. Quezon cor. Amang Rodriguez up to the end of the line.
b) Reason: 1. Re-conductoring to tree wire & installation of OHSW for 33 spans of 3-leg 34.5 kV lines, under
WO P1704001448 & P1704001447.
2. Retirement of 1-span 3-leg 34.5kV lines located directly above the building from pole I10-0083 to
I10-0084.
c) Clearance: M.L.D. Villaluz
d) Performing Crew: Pasig Construction Team 2
e) Customer Affected: 2300H to 0600H
Portion of Manggahan 34.5kV ckt. 45ZM, from disconnected “hot” 3-34.5kV jumpers on pole # I10-0072
along M.L. Quezon cor. Amang Rodriguez up to the end of the line.
f) Notes: 1. Install caution tag on Manggahan 34.5kV ckt. 45ZM.
2. Open "hot" 2-sets of temporarily installed 3-LCOs; one on pole # I10-2516 along Ramos cor. A.
Mabini St. & the other one on pole # I10-0074 along M.L. Quezon nr. Shoe Ave and FCOs of TLNs
024664 & 630335 prior to "hot" disconnection of above jumpers.

Thursday, June 29, 2017

Job # 8 0001H - 0600H Code : 17-015941


a) De-energize: Sta. Mesa feeder GCBs 55F8 & 58F8.
b) Reason: PMT.
c) Clearance: R.S. Rillera
d) Performing Crew: PSP COM, Substation COM, Testing
e) Customer Affected: NONE
f) Notes: Shift loads of above feeder GCBs to adjoining circuits prior to interruption.

6
Final Copy

Job # 9 0001H - 0700H Code : 17-015936


a) De-energize: Marikina 83MVA transformer bank # 1 and 133MVA transformer bank # 2
- ONE AT A TIME
b) Reason: 1. Corrective works for abnormal heating spotted on Bank 1 Differential CT Circuit.
2. Corrective works for abnormal heating spotted on Bank 2 kWhr Metering CT Circuit.
3. Retirement of Bank 2 kWhr Analog Meter.
c) Clearance: M.C. Argabioso
d) Performing Crew: PSP NOM, Substation NOM
e) Customer Affected: NONE
f) Notes: Unload above transformer banks then utilize bus-tie GCB 40VG48 during the job.

Job # 10 0001H - 0700H Code : 17-015933


a) De-energize: Meycauayan GCB 61YM4 (Marilao 115kV line)
b) Reason: Replacement of TCSR and functional test of control, protection & alarms.
c) Clearance: M.C. Argabioso
d) Performing Crew: Substation North O&M, PSP North O&M
e) Customer Affected: NONE
f) Notes: 1. Unload Meycauayan & Camarin s/s then shift Diliman banks 2 & 3 to Sector 2 as N-1 contingency.
2. Marilao-Meycauayan line 63MRL-61YM will be on floating status during the job. Consequently,
Marilao s/s will be radially fed by Duhat-Marilao 115kV line 62YY-62/63MRL during the job.
3. NGCP was advised.
4. This job was originally scheduled June 28, 2017.

Job # 11 0900H - 1500H Code : 17-015939


a) De-energize: Sta. Mesa feeder ACBs 20F4, 21F4 & 22F4 and bus-tie VCB 210F8
b) Reason: PMT and lubrication of mechanism.
c) Clearance: R.S. Rillera
d) Performing Crew: PSP COM, Substation COM, Testing
e) Customer Affected: NONE
f) Notes: Shift loads of above feeder ACBs to adjoining circuits prior to interruption.

Thursday, June 29, 2017 - Friday, June 30, 2017

Job # 1 2300H - 0600H Code : 17-015878


a) De-energize: Portion of Valencia 34.5kV ckt. 412VAL, in-between 2 sets of disconnected 3-34.5kV
jumpers; one on pole #I7-0207 along Wilson cor. Barcelona and the other on pole #I7-0223
along Mariano Marcos cor. Allenby, San Juan City.
b) Reason: Re-routing of 34.5kV lines along Wilson and Mariano Marcos and re-conductoring of primary lines
to covered conductor along Wilson and Hoover, under Project No. R16014088 (Iconic
Construction) & C170318900 (Eddy Q. Tan).
c) Clearance: G.P.C. Go
d) Performing Crew: Pasig Construction 1&2
e) Customer Affected: 2300H-2330H then again 0530H-0600H
1. Portion of Valencia 34.5kV ckt. 412VAL, bounded by opened “hot” RCLR 412VAr1 (I7-1318), normally
open LBS 412VAL11 and disconnected 3-34.5kV jumpers on pole #I7-0207 along Wilson cor. Barcelona.
2. Portion of Valencia 34.5kV ckt. 412VAL, from disconnected 3-34.5kV jumpers on pole #I7-0223 along
Mariano Marcos cor. Allenby, San Juan City up to normally open LBS 41F19.
2300H to 0600H
3. Portion of Valencia 34.5kV ckt. 412VAL, in-between 2 sets of disconnected 3-34.5kV jumpers; one on
pole #I7-0207 along Wilson cor. Barcelona and the other on pole #I7-0223 along Mariano Marcos cor.
Allenby, San Juan City.
f) Notes: 1. Items e.1 & e.2 will be de-energized twice to allow disconnection & reconnection of jumpers. Item
e.2 will be shifted to adjoining circuit after disconnection of jumpers.
2. Install caution tag on Valencia 34.5kV ckt. 412VAL.

Job # 3 2300H - 0600H Code : 17-015960


a) De-energize: Marikina-Masinag 115kV line 62VG-63WN
b) Reason: Transfer of 115kV line to newly erected pole along Marcos Highway for the relocation of 115kV
facilities affected by the construction of LRT2 Extension infront of Robinson Mall.
W.O. R14853354
c) Clearance: L.N.D.L. Medina

7
Final Copy

d) Performing Crew: STL Central O&M


e) Customer Affected: NONE
f) Notes: 1. Masinag & Parang s/s will be radially fed by Dolores-Masinag line 64XM-62WN during the job.
2. NGCP was advised.

Job # 4 2330H - 0530H Code : 17-015758


a) De-energize: Portion of CBP1A 34.5kV ckt. 416RF, from opened “hot” LBS 416RF21 up to opened LBS
413RF11 & 41U15.
b) Reason: Reconstruction of Distribution facilities to accommodate additional lines for Flexibility
Improvement (1) along Metrobank Road near EDSA, (2) Roxas Blvd. near EDSA, and (3) D. B.
Hernandez St. bet. Roxas Blvd. & F. B. Harrison St., Pasay City; under ECP-SR Project
Development of PAGCOR, Job 2 P1701003537.
c) Clearance: R.A. Garania
d) Performing Crew: Manila Contruction 2 , Manila Maintenance
e) Customer Affected: : 2330H to 0530H
Portion of CBP1A 34.5kV ckt. 416RF, from opened “hot” LBS 416RF21 up to opened LBS 413RF11 &
41U15.
f) Notes: 1. Shift unaffected portions of the line to adjoining circuits prior to interruption.
2. Install caution tag on CBP1A 34.5kV ckt. 416RF.

Friday, June 30, 2017

Job # 5 0001H - 0600H Code : 17-015975


a) De-energize: Grace Park-MGTPP-TMO 115 kV line 66RD-61NV-61TMO.
b) Reason: Relocation of 115kv lines to newly erected self support steel pole. To effect the relocation of 115kv
facilities affected by DPWH Road widening project
c) Clearance: Lemuel A. Ragasa
d) Performing Crew: STL NOM
e) Customer Affected: NONE
f) Notes: 1. As N-1 Contingency, unload Malabon, Malinta and Veinte Reales substations prior to interruption.
2. Malabon s/s will be radially fed by Malinta-Malabon 115kV line 62YB-63YD while Grace Park s/s
will be radially fed by North Port-Grace Park 115kV line 61H-61Rd during the job.
3. MGTPP will be affected.
4. NGCP, TMO & MGTPP were advised.

Job # 6 0001H - 0700H Code : 17-015875


a) De-energize: Paranaque feeder OCBs 45ZJ4 & 47ZJ4 and normally open OCB 43ZJ8
b) Reason: PMT
c) Clearance: R.J.A. Reyes
d) Performing Crew: Electrical Testing, Substation - SOM, PSP - SOM, Chemical Testing
e) Customer Affected: NONE
f) Notes: Shift load of feeder OCBs to adjoining ckts. prior to interruption.

Job # 7 1000H - 1400H Code : 17-015929


a) De-energize: Portion of Dolores 34.5kV ckt. 45XM, from opened temporarily installed LBS on pole # H15-
1479 along Sumulong Highway near Bankers Village, Dela Paz, Antipolo, Rizal up to
disconnected “hot” 3-34.5kV jumpers on pole # I14-0063 along Sumulong Highway near
Greenland Subd., Dela Paz, Antipolo, Rizal.
b) Reason: Relocation of six (6) poles affected by DPWH Road widening along Sumulong Highway, Dela Paz,
Antipolo, Rizal.
c) Clearance: J.F. De Ungria
d) Performing Crew: Rizal Construction 2
e) Customer Affected: : 1000H to 1400H
Portion of Dolores 34.5kV ckt. 45XM, from opened temporarily installed LBS on pole # H15-1479 along
Sumulong Highway near Bankers Village, Dela Paz, Antipolo, Rizal up to disconnected “hot” 3-34.5kV
jumpers on pole # I14-0063 along Sumulong Highway near Greenland Subd., Dela Paz, Antipolo, Rizal.
f) Notes: 1. Shift unaffected portion of the line to adjoining circuit prior to interruption.
2. Install caution tag on Masinag 34.5kV ckt. 42WN at RCLR 42WN13R.

8
Final Copy

3. Open "hot" FCOs of TLNs 052353 & 123355 and LCOs I14-0064 & I4-0118 prior to "hot"
disconnection of jumpers.

Friday, June 30, 2017 - Saturday, July 01, 2017

Job # 1 2300H - 0600H Code : 17-015920


a) De-energize: Portion of Hillcrest 34.5kV ckt. 423VZ, from opened LBS 41ZK15 up to opened “hot”
temporarily installed 3-LCOs on pole # G9-0545 along C. Raymundo cor. Mercedes Ave.,
Pasig City.
b) Reason: Re-conductoring to 3-336.4 MCM Tree Wire (22 spans, F9-0529 up to G9-0545), Installation of
OHSW along C. Raymundo Ave., Pasig City due to BWS, vegetation & structures and replacement
of one 55' wood pole (F9-0901).
c) Clearance: D.D. Mendoza
d) Performing Crew: Pasig Maintenance Implementation Team
e) Customer Affected:
2300H to 0600H
Portion of Hillcrest 34.5kV ckt. 423VZ, from opened LBS 41ZK15 up to opened “hot” temporarily
installed 3-LCOs on pole # G9-0545 along C. Raymundo cor. Mercedes Ave., Pasig City.
f) Notes: 1. Temporarily installed 3-LCOs on pole # G9-0545 will be by-passed before loadshifting and
normalization of line set-up.
2. Shift unaffected portions of the line to adjoining circuits prior to interruption.
3. Install caution tags on Hillcrest 34.5kV ckt. 423VZ and Manggahan 34.5kV ckt. 43ZM on
RCLR 43ZMr1.

Saturday, July 01, 2017

Job # 2 0300H - 0800H Code : 17-015872


a) De-energize: Imus 33 MVA transformer bank #1, high side GCBs 63WK24 & 62WK4 and low side PCB
31WK4.
b) Reason: PMT including PT of transformer bank and station service.
c) Clearance: R.J.A. Reyes
d) Performing Crew: Electrical Testing, Substation - SOM, PSP - SOM, Chemical Testing
e) Customer Affected: NONE
f) Notes: Shift loads of Imus 33 MVA bank to adjoining ckts. prior to interruption. Ckts. 34WK, 35WK &
36WK will be de-energized momentarily for few minutes, due to phase angle difference, between
0200H to 0300H and again between 0801H to 0900H, to effect load shifting and normalization of set-
up, respectively.

Job # 3 0800H - 2359H Code : 17-015551


a) De-energize: Pamplona GCB 43XD4 (Las Pinas line 2)
b) Reason: Servicing due to high concentration of decomposition product (SO2)
c) Clearance: E. C. Arcega
d) Performing Crew: Testing, Substation SOM, PSP SOM,
e) Customer Affected: NONE
f) Notes: Shift loads of GCB prior to interruption.

Job # 4 0900H - 1200H Code : 17-015952


a) De-energize: Legaspi GCB 66RA4 (Kamagong line)
b) Reason: Functional test of protection controls and alarms.
c) Clearance: Mick Andrew P. Lavado
d) Performing Crew: PSP Central O&M
e) Customer Affected: NONE
f) Notes: 1. Unload Kamagong s/s as N-1 contingency.
2. Kamagong-Legaspi line will be on floating status during the job. Consequently, Kamagong s/s will
be radially fed by New Rockwell-Kamagong 115kV line 64VV-63VK during the job.
3. NGCP was advised.

Sunday, July 02, 2017

Job # 1 0001H - 0500H Code : 17-015970

9
Final Copy

a) De-energize: Portion of San Pedro 34.5kV ckt. 43WH, bounded by opened RCLS 43WH19, normally open
LBS 43WH15 and opened "hot" temporarily installed 3-LCOs on pole #DM3-0029-T along
Gen. Malvar St. nr. National Hi-way, Binan, Laguna.
b) Reason: 1. Replacement of rotted poles nos. STR1-2446 & DM3-0040.
2. Replacement of rotted cross-arms on poles nos. DM3-0932 & DM3-0096-Z.
c) Clearance: L.S. Badayos
d) Performing Crew: Sta Rosa - Construction 2
e) Customer Affected: 0001H to 0500H
Portion of San Pedro 34.5kV ckt. 43WH, bounded by opened RCLS 43WH19R, normally open LBS
43WH15 and opened "hot" temporarily installed 3-LCOs on pole #DM3-0029-T along Gen. Malvar St. nr.
National Hi-way, Binan, Laguna.
f) Notes: 1. Install caution tags on circuits 45WL and 42XV.
2. Shift unaffected portion of ckt. 43WH to adjoining ckt. prior to interruption.

Job # 2 0100H - 0600H Code : 17-015811


a) De-energize: Angat low side VCB 31YT4.
b) Reason: Re-testing of VCB and re-activation of space heaters.
c) Clearance: R.P. Lualhati
d) Performing Crew: Electrical Testing, Substation NOM
e) Customer Affected: NONE
f) Notes: 1. Shift load of Angat 7MVA transformer bank #1 to adjoining ckt. prior to interruption.
2. Angat 13.2kV ckt. 36YT and portion of Baliwag 13.8kV ckt. 313YW, from RCLR 313YWr1
(VJ4-441) up to normally open PLS VJ7-17, will be de-energized momentarily for a few minutes
(due to phase angle difference) between 0001H to 0100H and then again between 0600H to 0700H
to allow loadshifting and normalization of line set-up, respectively.

Job # 3 0100H - 0700H Code : 17-015871


a) De-energize: Imus 83 MVA transformer bank #2, high side GCBs 62WK24 & 63WK8 and low side VCB
421WK4
b) Reason: PMT including PT of transformer bank
c) Clearance: R.J.A. Reyes
d) Performing Crew: Electrical Testing, Substation - SOM, PSP - SOM, Chemical Testing
e) Customer Affected: NONE
f) Notes: Shift loads of the transformer bank to adjoining ckts. prior to interruption.

Job # 4 0600H - 1800H Code : 17-015886/016010


a) De-energize: 1. Gardner 115kV bus #2
2. Gardner-FBGC4 115kV line 63GG-65RJ
b) Reason: 1. Retirement of old GCBs 62GG8, 62GG24, 63GG8 & 63GG24 and OCB 61GG24.
2. Retirement of old D.S. 62GG7/9/23/25 & 63GG7/9/23/25
c) Clearance: R.J.A. Reyes
d) Performing Crew: Substation South O&M, PSP South O&M
e) Customer Affected: NONE
f) Notes: 1. Unload Kamagong s/s as N-2 contingency.
2. FGBC & Urdaneta s/s will be radially fed by Rockwell-Urdaneta line 67WV-61VS during the job.
3. NGCP was advised.

Job # 5 0800H - 1700H Code : 17-015858


a) De-energize: NGCP Bay-Calamba 69kV line 56MB.
b) Reason: Preventive maintenance along the line.
c) Clearance: NGCP Biñan-ACC
d) Performing Crew: NGCP Batangas
e) Customer Affected: 0800H to 1700H
Batangas Paper Corporation (St. Thomas Paper)
f) Notes: NGCP Calamba s/s is being fed by above 69kV line. Shift load of Calamba ckt. 31XO to adjoining
ckt. prior to interruption.

Job # 6 0900H - 1700H Code : 17-015796

10
Final Copy

a) De-energize: Portion of Grace Park 34.5kV ckt. 413RD, bounded by opened “hot” temporarily installed 3-
LCOs on pole # M5-1132 along A. Bonifacio Ave. near Citra pole #PS4-120, opened LBS
45VB25 and normally open LBS 413RD21.
b) Reason: Stringing and energizing of new spun cables installed on relocated poles affected by CITRA
(Skyway) Project, related to EAM WO Nos. R15401586, R15475742, R15520997, R15018898 &
R15018926.
c) Clearance: Louis Nikko M. Castro
d) Performing Crew: Manila Network and Underground, Balintawak Construction Team 1
e) Customer Affected: 1630H to 1700H
1. Portion of Grace Park 34.5kV ckt. 413RD, bounded by opened “hot” RCLR 413RDr1 (M5-0610),
normally open LBS 413RD23 and disconnected 3-34.5kV jumpers on pole # M5-1132 along A. Bonifacio
Ave. near Citra pole #PS4-120.
0900H to 1700H
2. Portion of Grace Park 34.5kV ckt. 413RD, bounded by opened “hot” temporarily installed 3-LCOs on pole
#M5-1132 along A. Bonifacio Ave. near Citra pole PS4-120, opened LBS 45VB25 and normally open LBS
413RD21.
f) Notes: 1. Shift unaffected portion of the line to adjoining ckt. prior to interruption.
2. Install “hot” temporary by-pass 3-LCOs (in parallel with jumper wires) on pole # M5-1132 along
A. Bonifacio Ave. near Citra pole #PS4-120 then disconnect "hot" 3-34.5kV jumpers on pole
#M5-1132 prior to "hot" opening of temporarily installed 3-LCOs.
3. After stringing of new spun cable, item e.1 will be de-energized to allow reconnection of jumpers
on bus type insulators.
4. Conduct phase-out test on LBS 413RD21 (413RD vs. 53E) and LBS 45VB25 (413RD vs.
415BNW) prior to normalization of line set-up.
5. Install caution tags on Grace Park 34.5kV ckt. 413RD at RCLR 413RDr1.

Job # 7 0900H - 2300H Code : 17-015694


a) De-energize: Malibay 83MVA transformer bank #2 and 34.5kV bus #2. CANCELLED
b) Reason: 1. Replacement of PCB 51VJ8 due to problematic pneumatic mechanism.
2. Repainting of bus support steel structures
c) Clearance: Clarito S. Alvareda
d) Performing Crew: PSP Central O&M, Substation Central O&M, Electrical & Chemical Testing
e) Customer Affected: NONE
f) Notes: Shift loads of above transformer bank/bus to adjoining ckts. prior to interruption.

WARNING: IN CASE ANY OF THE JOBS IS FINISHED AHEAD OF TIME, SUBJECT LINE
OR EQUIPMENT MAY BE ENERGIZED EARLIER THAN SCHEDULED TIME.

J.I. SANTIAGO, JR.


Head, Operations Planning
AAA/JAGT/NMP/LVA/RNBV System Control Center