PRE-ARRANGED JOBS
W e e k N o. 26
(June 26, 2017 - July 02, 2017)
Print Date & Time: 06-22-17 10:01 AM
1. Pre-arranged circuit interruption must be limited to once in fifteen (15) days. Momentary interruptions not
exceeding thirty (30) minutes are not counted.
2. Request for interruption with customers affected shall not exceed five (5) hour duration. Any request
exceeding five hours shall require the approval of Requesting Office's Distribution Head.
3. Observe on-time submission of original copy of RPJ (3 copies). Deadline for submission is every 4:00 PM of
Monday for jobs covering Monday to Sunday of a next succeeding week. Late submission would mean resetting
of the job for another week. Sending copy of RPJ through fax will only serve as an advance notice to OPU but it
is not a means of beating the deadline. It is therefore suggested that requesting party shall prepare their RPJ
earlier and submit to OPU on time. No original copy of RPJ would mean non-inclusion of job in the final PAJ
summary.
4. For jobs falling under the category of 'hazardous' request, Requesting Office shall see to it that RPJ are in the
custody of Operations Planning not beyond 1400H of the day immediately before the interruption. For those
falling under the category of 'urgent' request, RPJ should be submitted at least three (3) days before the
interruption. RPJ submitted beyond these time frames will be reset in order to meet the said time frame. This is
to provide us sufficient time to analyze and prepare a job summary for the said job and for Call Center to make
proper advisory if there are affected customers. For purposes of clarification, 'urgent' and 'hazardous' request is
defined below:
'Hazardous' conditions are any abnormalities on line or equipment that may endanger life or property and has to
be corrected within forty eight (48) hours
'Urgent' conditions are those abnormalities that need to be corrected or management initiated projects which
need to be executed within seven (7) days
5. Advanced copy is available every Tuesday and the final copy every Thursday. The final copy includes the
corrections/revisions and additional jobs (in blue fonts) covered by the pre-arranged job week. For more
inquiries, contact us at locals 6457 and 6772. However, Operations Planning will not entertain inquiries if the
subject of the inquiry is only the schedule of the job. It is our intent that all requesting parties should read and
verify their schedules through this Pre-Arranged Job Summary.
6. Heads with access to e-mail should provide copy of Job Summary to all supervisors directly involved to
countercheck their schedule with the Pre-Arranged Job Summary as well as the accuracy of the Job Summary
involving their job. Operations Planning will not be liable for cancellation of jobs on the date of interruption
due to inaccurate request or for failure to verify the schedule in the Final copy of the Pre-Arranged Job
Summary.
7. For all PAJs which will affect the station service transformer, the requesting party shall specifically indicate
it in their submitted RPJs.
8. This PAJ summary does not include Additional PAJs which may be accommodated and scheduled within the
same week. Instead, Lotus Notes Advisories will be sent to involved offices regarding these additional PAJs.
9. Any caution request by performing crew relative to a PAJ shall be made to Delta by the former before the
start of the job.
10. Any scheduled job maybe cancelled or modified as needed and involved offices will be properly advised.
1
Final Copy
2
Final Copy
b) Reason: Replacement of rotted wood pole (K3-1015) and re-conductoring of 3-spans to 3#336.4 MCM TW
ACSR from pole no. K3-1015 to K3-0031-T along Velasquez St. corner Ugbo St., Tondo, Manila
under 2017 Planned MA P1701003116.
c) Clearance: W.C.P. Amaca
d) Performing Crew: Manila Construction 2, Manila Maintenance
e) Customer Affected: 0830H-0900H then again 1300H-1330H
1. Portion of North Port 34.5kV ckt. 403H, bounded by disconnected 3-34.5kV jumpers on pole # K3-0031-T
along Ugbo cor. Jacinto Sts., Tondo, Manila, normally open LBS 47H15R & 43VM13 and opened RCLR
403Hr2 (K3-2337).
0830H to 1330H
2. Portion of North Port 34.5kV ckt. 403H, bounded by opened “hot” LBS 47H13R, opened RCLR 403Hr3
(K3-2540) and disconnected 3-34.5kV jumpers on pole # K3-0031-T along Ugbo cor. Jacinto Sts., Tondo,
Manila.
f) Notes: 1. Shift unaffected portions of the line to adjoining circuits prior to interruption.
2. Item e1 will be de-energized twice to allow disconnection & reconnection of jumpers. Said portion
will be shifted to adjoining circuit after disconnection of jumpers.
3. Install caution tag on North Port 34.5kV ckt. 403H.
3
Final Copy
4
Final Copy
5
Final Copy
6
Final Copy
7
Final Copy
8
Final Copy
3. Open "hot" FCOs of TLNs 052353 & 123355 and LCOs I14-0064 & I4-0118 prior to "hot"
disconnection of jumpers.
9
Final Copy
a) De-energize: Portion of San Pedro 34.5kV ckt. 43WH, bounded by opened RCLS 43WH19, normally open
LBS 43WH15 and opened "hot" temporarily installed 3-LCOs on pole #DM3-0029-T along
Gen. Malvar St. nr. National Hi-way, Binan, Laguna.
b) Reason: 1. Replacement of rotted poles nos. STR1-2446 & DM3-0040.
2. Replacement of rotted cross-arms on poles nos. DM3-0932 & DM3-0096-Z.
c) Clearance: L.S. Badayos
d) Performing Crew: Sta Rosa - Construction 2
e) Customer Affected: 0001H to 0500H
Portion of San Pedro 34.5kV ckt. 43WH, bounded by opened RCLS 43WH19R, normally open LBS
43WH15 and opened "hot" temporarily installed 3-LCOs on pole #DM3-0029-T along Gen. Malvar St. nr.
National Hi-way, Binan, Laguna.
f) Notes: 1. Install caution tags on circuits 45WL and 42XV.
2. Shift unaffected portion of ckt. 43WH to adjoining ckt. prior to interruption.
10
Final Copy
a) De-energize: Portion of Grace Park 34.5kV ckt. 413RD, bounded by opened “hot” temporarily installed 3-
LCOs on pole # M5-1132 along A. Bonifacio Ave. near Citra pole #PS4-120, opened LBS
45VB25 and normally open LBS 413RD21.
b) Reason: Stringing and energizing of new spun cables installed on relocated poles affected by CITRA
(Skyway) Project, related to EAM WO Nos. R15401586, R15475742, R15520997, R15018898 &
R15018926.
c) Clearance: Louis Nikko M. Castro
d) Performing Crew: Manila Network and Underground, Balintawak Construction Team 1
e) Customer Affected: 1630H to 1700H
1. Portion of Grace Park 34.5kV ckt. 413RD, bounded by opened “hot” RCLR 413RDr1 (M5-0610),
normally open LBS 413RD23 and disconnected 3-34.5kV jumpers on pole # M5-1132 along A. Bonifacio
Ave. near Citra pole #PS4-120.
0900H to 1700H
2. Portion of Grace Park 34.5kV ckt. 413RD, bounded by opened “hot” temporarily installed 3-LCOs on pole
#M5-1132 along A. Bonifacio Ave. near Citra pole PS4-120, opened LBS 45VB25 and normally open LBS
413RD21.
f) Notes: 1. Shift unaffected portion of the line to adjoining ckt. prior to interruption.
2. Install “hot” temporary by-pass 3-LCOs (in parallel with jumper wires) on pole # M5-1132 along
A. Bonifacio Ave. near Citra pole #PS4-120 then disconnect "hot" 3-34.5kV jumpers on pole
#M5-1132 prior to "hot" opening of temporarily installed 3-LCOs.
3. After stringing of new spun cable, item e.1 will be de-energized to allow reconnection of jumpers
on bus type insulators.
4. Conduct phase-out test on LBS 413RD21 (413RD vs. 53E) and LBS 45VB25 (413RD vs.
415BNW) prior to normalization of line set-up.
5. Install caution tags on Grace Park 34.5kV ckt. 413RD at RCLR 413RDr1.
WARNING: IN CASE ANY OF THE JOBS IS FINISHED AHEAD OF TIME, SUBJECT LINE
OR EQUIPMENT MAY BE ENERGIZED EARLIER THAN SCHEDULED TIME.
11