Beruflich Dokumente
Kultur Dokumente
60A1 (READING)
C&I GENERAL FWUK OU PAGE 1 OF 58
SPECIFICATION STANDARD ENGINEERING REV 2
REVISION: ORIG.
Signature
DATE: 07 OCT 2013
ORIG. BY: T. THANGMAHASUK
APP. BY: DINKAR PATEL
CONTENTS
This document has been substantially revised therefore changes are not highlighted. A
summary of the changes of the changes is provided on the appropriate Quality.net
webpage.
1.0 INTRODUCTION
1.1 Purpose
This specification, together with other referenced documentations in Section 3.0
defines the minimum general requirements for the Control and Instrumentation.
1.2 Definitions
Term Definition
Contractor The party which has contractual responsibility for the design,
procurement and construction of the plant.
Supplier The Company having a purchase order with the Contractor for
the supply of specified equipment and associated services.
Client The owner of the Plant
Shall Refers to a mandatory requirement
Should Refers to a recommendation
1.3 Abbreviations
Abbreviations Description
AAMS Ambient Air Monitoring System
BEDD Basic Engineering Design Data
BMS Burner Management System
CCR Central Control Room
CCS Compressor Control System
CEMS Continuous Emission Monitoring System
CRER Control Room Equipment Room
DC Direct Current
DCS Distributed Control System
EU European Union
FGS Fire & Gas System
FMS Fiscal Metering System
HART Highway Addressable Remote Transducer
HMI Human Machine Interface
ICSS Integrated Control and Safety System
I/O Input /Output
ISB Instrument Satellite Building
ISO International Organisation for Standardization
MCC Motor Control Centre
MMS Machine Monitoring System
MOV Motor Operated Valve
60A1 READING Rev 2 COPY DSN:
C& I ENGINEERING
60A1 (READING)
C&I GENERAL FWUK OU PAGE 6 OF 58
SPECIFICATION STANDARD ENGINEERING REV 2
Abbreviations Description
NPS Nominal Pipe Size
NPT National Pipe Tread
NPT(F) National Pipe Taper Female
PDP Power Distribution Panels
PED Pressure Equipment Directive
SIF Safety Instrument Function
SIS Safety Instrumented System
UPS Uninterruptible Power Supply
2.0 SCOPE
All instrumentation and system equipment shall be furnished in accordance with this
specification as well as standards and specifications referenced in Section 3.0.
The following Local standards are applicable to this specification. The latest published
issue or amendment at the time of contract placement shall apply unless otherwise
stated.
4.0 GENERAL
Typical loops and their associated tags that shall be used to populate the SmartPlant
Instrumentation (SPI) database shall be provided in accordance with 60A43,
SmartPlant Loop Template Specification.
Control and Instrumentation requirement for packaged units shall generally comply with
60A20, C&I for Packaged Units Specification, together with the related reference
documents and technical description of the packaged equipment requisition.
4.5 Standardisation
Control and Instrumentation equipment shall be standardised including equipment
used in packaged units, to reduce spares holding capacity and to simplify
maintenance. This is not only includes standardisation in terms of instrument or valve
make and models, but includes standardisation of design approaches such as JB
layouts, hook up drawings, loop design, linearization algorithms, DCS and SIS software
function blocks, etc.
The directives applicable to the Plant shall include, but not be limited to the following:
5.1 General
All instrumentation shall be identified by Tag Number in accordance with 60A3, C&I
Symbols and Identification Specification.
Instruments and their installation shall be selected for reliability in the working
environment without the need for special environmental control. Particular attention
shall be paid to possible effects of corrosion, vibration, humidity, and extremes of
temperature.
All field Instruments / enclosures shall be protected to IP65 as a minimum and shall be
finished to the manufacturer’s standard practice suitable for the environmental
conditions. For details of site environmental conditions refer to 01A1, Basic
Engineering Design Data (BEDD).
All control system equipment shall be located in a Central Control Building (CCB) or
Instrument Satellite Building (ISB).
All process control shall be by the DCS. Local controllers shall not be used.
Instruments and their pneumatic process piping shall be provided with protection to
mitigate the effects of damage from process fluids, maintain the process fluid in a state
to achieve accurate measurement and to prevent freezing in accordance with 67A1,
Protection of Instruments Specification.
Instruments and their equipment shall be installed in accordance with 60A24, C&I
Installation Specification.
All Instrument process and pneumatic tubing/piping shall be in accordance with 60A10,
C&I Piping Material Specification.
Multiple transmitters with different ranges may be used as necessary depending on the
measurement range required.
Separate low range transmitter shall be used to achieve required accuracy where the
minimum process measurement is lower than the maximum possible turndown point of
the high range transmitter
All instruments used in multiple voting and comparison loop shall have the same
calibration range.
5.4 Accuracy
Unless otherwise stated, accuracy of normal applications instruments shall be:
5.5 Accessibility
All locally mounted indicators, including thermometers shall be readable from grade or
permanent platforms. All other measuring elements with pipework connections
including fire and gas detectors shall be accessible from grade or platforms.
Post or Gauge Board mounted instruments shall be located at a minimum 1400mm and
maximum 1600mm above grade or permanent platform level.
5.6 Location
Instrumentation shall be positioned to minimise the effects of fire, solar radiation, heat
from adjacent equipment, condensation, spillage, rain, wash water and maintenance
activities.
Instrumentation may be post or gauge board mounted. Posts or gauge board shall not
be attached to piping, removable flooring, handrails or mounted directly on machinery
and equipment subject to vibration.
60A1 READING Rev 2 COPY DSN:
C& I ENGINEERING
60A1 (READING)
C&I GENERAL FWUK OU PAGE 13 OF 58
SPECIFICATION STANDARD ENGINEERING REV 2
Each instrument shall have its own process connections with dedicated process
isolation valves to minimise the potential of common mode failure.
Shared vessel nozzles are permitted for multiple instrument connections on standpipes
although safety instruments shall be via dedicated nozzles.
Shared impulse lines are permitted for differential flow measurement where high and
low range transmitters are required for flow accuracy.
Vent and drain valves shall be incorporated as discrete valves or incorporated within
the instrument manifold (preferred). Vent plugs shall be used.
Impulse lines shall be as short as possible, free from blockages and directed to ensure
self draining and venting, and ensuring that vibration is avoided.
When process fluids are liable to separate, solidify or deposit in impulse lines, or have
extreme temperatures or pressures, the choice of instrumentation coupling should be
designed to prevent damage to the transmitter or unreliable measurement. Typically
direct mount diaphragm seals with equal length capillaries are preferred. All diaphragm
seals shall be installed on dedicated process isolation valves and full size flanged
bleed ring with vent and drain valves.
Capillary systems shall be routed and protected against differential heating especially
when used for differential pressure measurement.
For detail of Instrument process connection requirements refer to 65A1, C&I / Piping
Interface Specification.
Pneumatic connections shall be NPT (F), normally ¼” or ½”, but larger as required, e.g.
for high speed actuators. Compression fittings shall be double ferrule type.
Solenoids 24V DC
Pneumatic instrumentation shall be limited to the actuator for the final control element.
5.8.1 Transmitters
Transmitters shall be used for all process indication, control, alarm, and shutdown
services.
Transmitters shall be electronic and of the Smart type with HART / Foundation Fieldbus
protocol technology in order to facilitate easier maintenance, simple adjustment,
provide improved diagnostics, and additional functionality, such as linearization.
Nucleonic transmitters and switches may only be used by exception and then only if
the application cannot be handled by any other instrument type. Nucleonic
instrumentation shall also only be used with the Client’s written approval.
5.8.2 Switches
Switches shall only be considered on non-critical auxiliary systems, e.g. seal oil
systems for non critical pumps and shall only be used with the Client’s written approval.
Switches shall have reliable, high integrity switch mechanisms, e.g. flow switches shall
be avoided.
Switches shall have adjustable set points and have DPDT or SPDT contacts rated at
1A at 24V DC. Switch modules shall be hermetically sealed and vibration resistant.
Control systems and Instrumentation shall be tested by the Manufacturer to meet the
requirements of Level 3 severity for susceptibility to effects of electromagnetic fields
generated by portable radio transceivers or any other device that generates continuous
wave electromagnetic energy as per IEC 61000 Part 3. Test shall be carried out at field
strength of 10 V/m in the frequency band 27 MHz to 500 MHz.
Control Systems and Instrumentation shall be tested by the Manufacturer to meet the
requirements of Level 4 severity for susceptibility to effects of repetitive fast transient /
burst on supply, signal or control lines as per IEC 61000 Part 4.
The allocation of the SIL, the selection and design of the instrumentation and
supporting equipment, and the validation calculations shall be performed in accordance
with IEC 61508 and IEC 61511.
The SIL target requirement for each instrument, together with any supporting
infrastructure or equipment required to ensure that the instrument meets the required
SIL target, shall be indicated on the instrument data sheet and C&I database.
All supporting infrastructure and equipment, such as partial valve stroke testing
systems etc. shall be provided to ensure that the instrumentation meets the SIL
requirements.
Each SIS system shall have Safety Requirement Specification(s) describing the SIL
requirements for each SIF loop with supporting calculations, justifications for the SIL
targets selected, references to the applicable data sheets of the instruments, and any
other supporting information.
The selection of materials for on-line instruments such as level displacers shall follow
the associated vessel material specification as a minimum.
Where the material of the instrument differs to that of the associated piping / vessel
connection, yield stress requirements of the pipe work / vessel shall not be
compromised.
Thermowells and orifice plates shall be 316 stainless steel unless process conditions
require a higher grade of material.
Off-line instruments such as transmitters shall have 316 stainless steel process wetted
parts unless process conditions require a more suitable material.
The version of SPI to be used shall require approval by the Client but shall generally be
the latest version available at the commencement of detailed design.
For Instrument Power Supply voltage level refer to 01A1, Basic Engineering Design
Data (BEDD).
Where possible, all instruments shall be loop-powered with 24V DC supply from their
respective systems.
Suitable segregation of the UPS supply feeds shall be incorporated to prevent common
mode failures to the Power Distribution Panels (PDPs).
PDPs shall be utilised to distribute feeds, via isolators, directly to system cabinets,
marshalling cabinets and to field instrumentation where required. The PDPs shall have
protection to isolate the fault of any system or logical grouping of instruments, to
maximise the availability of the process equipment.
Non UPS power supplies for lighting, rotation beacons and utility outlets shall be kept
separate from the instrument power supplies so as to restrict UPS usage to critical
applications.
For details of the earthing of instruments refer to the 60A24, C&I Installation
Specification and Project Instrument Earthing Philosophy Diagram.
Two grounding systems shall be provided in the CRER and ISBs in order to prevent
start-up and circulating currents of large motors and other electrical equipment from
interfering with the sensitive low current/power instrumentation equipment:
The following signal and equipment connections shall be made to the instrument
earth:
Where ICSS subsystems require a segregated system earth, then separate system
earth grounding shall be provided.
The Instrument earth, safety earth and system earth shall join electrically at a single
point as close as possible to a high-quality earth ground mat to prevent earth loops
between the two earthing systems.
Since various suppliers have different grounding requirements, care must be taken to
develop a scheme that meets those requirements, meets the BS 7430 and BS 7671
requirements, has testing capabilities and has the Supplier approval.
Removable link shall be provided between the safety earth ground and the instrument
ground to allow testing of the instrument ground.
All instrument earth bars, plates, and wire shall be isolated from building safety earth
ground path, except at the one point specified above.
Each cabinet used in the instrumentation system shall have a redundant connection to
the high quality earth.
Each ISB shall have its own high quality earth mat installed to reduce the cable lengths
from the system cabinets to the high quality earth mat.
Where instruments fall outside the protective shadow of a lightning conductor, the
instrument signal shall be connected via a lightning barrier such that any voltage /
current surges are isolated or directed to the safety earth.
6.1 Standards
Equipment for use in potentially hazardous atmospheres shall be selected in
accordance with IEC 60079.
6.2 Protection
Electrical signals out to the field shall be designed to prevent causing ignition of a
hazardous gas or dust in the vicinity of the instrumentation in the field.
Where Intrinsically Safe is used as a method of hazardous area protection, zener type
safety barriers shall only be used when an equivalent galvanic isolator is not available.
IS calculations shall be done for all intrinsically safe instruments taking into account
worst case scenario for cable length and cable parameters.
A hazardous schedule dossier with all the required information shall be prepared for
instruments that are located in hazardous areas. A hazardous area certificate shall be
issued for each associated device.
In addition, all components in hazardous areas shall be certified per ATEX directive
94/9/EC which shall be actively managed to ensure full compliance before
commissioning.
7.1 General
Dried, filtered, oil-free compressed air shall normally be made available at plot limits at
a pressure detailed in 01A1 Basic Engineering Design Data (BEDD). The minimum
supply pressure for actuator sizing shall be 3.5 barg.
Filter regulators of ≤ 5µm shall be installed on each valve positioner and solenoid valve
to protect the equipment from particles coming off the pipe walls of the distribution
piping.
7.2 Distribution
Instrument air shall be locally distributed in the field through the use of air distribution
manifolds. Where the density of air users is low in a particular area, a ‘spider’ air
distribution arrangement shall be used.
There shall be no interconnection between the instrument air distribution system and
any service air distribution system.
The choice between RTDs and Thermocouples shall take the following into account
Temperature transmitters shall be provided for all control, indication and safety
applications
All thermocouple actuated control systems shall contain 'burn-out' protection. The
design shall enable this feature to be switched between upscale and downscale
operation.
Gas or liquid filled systems shall be used only where Bi-metallic type are not suitable.
All capillary tubing shall be corrosion resistant and sheathed or armoured. Preferred
lengths are 3m and 10m (maximum). Capillary tubing shall be supported throughout its
length.
8.3 Thermocouples
For temperatures up to 1100°C, thermocouples shall be manufactured from nickel /
chromium – nickel / aluminium (Type K) wires with reference characteristics in
accordance with IEC 60584.
60A1 READING Rev 2 COPY DSN:
C& I ENGINEERING
60A1 (READING)
C&I GENERAL FWUK OU PAGE 20 OF 58
SPECIFICATION STANDARD ENGINEERING REV 2
For temperatures above 1100°C or for H2 service above 750 oC, thermocouple shall be
manufacturer from platinum / 10% rhodium – platinum (Type S) wires with reference
characteristics in accordance with IEC 60584.
Thermocouples shall be mineral insulated, with 6mm diameter and hot junction
insulated from the sheath.
Thermocouple head terminals shall be marked with positive and negative symbols.
The signal from any thermocouple used in conjunction with SIS shall not be connected
to any other systems.
Where duplex thermocouples are identified on the P&IDs, the purpose must be clearly
stated, e.g. spare, and separately tagged, if appropriate.
The use of resistance thermometers is normally limited to the range – 175 to 475°C.
8.5 Thermowells
Thermowells shall be machined from solid bar stock and have flange connection not
screwed.
Thermowells shall be made of 316 stainless steel unless process conditions require a
higher grade of material.
Calculations shall be tabulated by the thermowell Supplier to show that all thermowells
are suitable for stress due to maximum stream velocity conditions (Vortex shedding
effect). Thermowell wake frequency calculation shall be carried out in accordance with
ASME PTC 19.3.
Thermowells shall be installed in a minimum DN 100 (4") pipe. Pipe sizes DN 80 (3”)
and below shall be swaged up locally to 4” to accommodate the thermowell. Where a
connection is on a stream axis, in a bend or tee, DN 80 (3”) minimum line size is
acceptable.
8.6 Transmitters
Head-mounted SMART type temperature transmitters shall be used where possible for
thermocouples or RTDs. Remote-mounted SMART type temperature transmitters shall
be used for multi-element types (e.g. skin temperatures or bearing temperatures, in
order to minimise the use of compensation cables).
The field of view of the pyrometer, the transmission qualities of the collector system
and the band pass sensitivity of the detector are key design parameters for the
specification of a pyrometer.
The pyrometer shall be mounted so that it is not subject to vibration or movement, and
that the object to be measured fills up the cone of vision of the pyrometer.
An internal air purge should be used to keep the window of the pyrometer clear of
steam, smoke and dust. The pyrometer should also be shielded from excessive heat.
Multi-wavelength pyrometers are preferred over ratio pyrometers.
9.1 Applications
Rates of flow shall normally be measured by square edged, concentric, orifice plates.
If process conditions dictate other meter types may be considered including turbine
meters, variable area meters, positive displacement meters, coriolis mass flow meters,
ultrasonic flow meters, magnetic flow meters, vortex, thermal mass flow meters and
annubars or other differential pressure meters.
Flow meters for standard flow measuring applications shall be designed for accuracy of
±5%. For commercial or fiscal metering application where high accuracy is required,
refer to 60A34, Custody Metering System - Gas Specification and 60A35, Custody
Metering System – Liquid Specification
Small flows of liquid or gas such as purges to instrument tapings or sample flows to on-
line analysers shall be measured by variable area meters. Alternatively, they may be
measured by differential pressure transmitters fitted with integral orifices.
Care should be taken to ensure that the maximum velocity for a particular substance is
not exceeded (e.g. oxygen) and that choked flow conditions and cavitation do not occur
as a result of the selection of the flow measurement device.
Differential pressure type flow transmitters shall be sized so that normal flow falls below
70% of flow range, minimum flow is not less than 30% of flow range and maximum flow
is not more than 90% of flow range. If the actual operating range exceeds the minimum
or maximum limits described above, then an additional transmitter should be installed
across the same orifice plate with shared impulse lines to cater for the additional range.
Square edged, concentric, orifice plates are preferred, others type may be considered
if the application dictates.
The material for orifice plates shall be compatible with the fluid handles and shall be
made of 316 stainless steel unless process conditions require a higher grade of
material.
Orifice plates with flange taps in accordance with ISO 5167 shall generally be used.
Installation of orifice plates and pressure tapping orientation shall be designed to
ensure flow characteristics are as close as possible to laminar flow to ensure high
accuracy/reliability measurement of flow and shall be in accordance with 65A1,
C&I/Piping Interface Specification. Orifice plates in carrier rings with integral corner
tapings shall be in accordance with ISO 5167.
Conical entrance or quarter circle orifice plates to ISO 5167 or venturi tubes, may be
used to measure high viscosity liquids or slurries.
Segmental orifice plates may be used to measure liquids containing large amounts of
solids and for flows in large conduits.
Low loss flow tubes or venturi meters shall be used where good pressure recovery is
essential.
Averaging pitot tubes may be considered only where no appreciable pressure drop can
be tolerated and may be considered for economic reasons for large line sizes (greater
than 12”). Average pitot tubes shall be used for clean gas and clean liquid
measurement only.
Horizontal metering runs are preferred for liquid flow measurement and in all cases
where segmental orifices are used. Vertical runs with downward flow are acceptable
for steam and condensable gas.
60A1 READING Rev 2 COPY DSN:
C& I ENGINEERING
60A1 (READING)
C&I GENERAL FWUK OU PAGE 23 OF 58
SPECIFICATION STANDARD ENGINEERING REV 2
9.4 Compensation
Static Pressure and Fluid Temperature compensation to improve the accuracy of the
flow measurement shall be performed in the ICSS. The pressure and temperature
transmitters shall be located at least 8 pipe diameters downstream of the orifice plate to
avoid affecting the flow measurement.
For non immiscible liquids impulse lines shall be gently sloped downwards, for gases
impulse lines shall be gently sloped upwards.
Impulse line shall be kept to a minimum length and each impulse line within a
measurement set shall be kept to as equal a length as possible.
The full scale of a differential pressure meter shall be optimised to one of the following
values, after taking into consideration calculation variables such as flow range, beta
ratio, unrecovered pressure loss, static pressure, meter type, etc.
50 mbar
100 mbar
250 mbar
500 mbar
The preferred full scale differential for orifice plate measurements shall be 250mbar
wherever possible.
Diaphragm seals shall be used where it is necessary to protect the instrument from the
process fluid or from viscous liquids. Liquid seals shall not be used for this application.
Variable area meters shall not be used for fluids that may contain solids.
Variable area meters shall be located with sufficient clearance to permit tube and float
removal without removing the meter body.
If the flow cannot be interrupted during plant operation, line size block and bypass
valves shall be provided.
Where fluid properties can have an adverse effect on meter mechanical performance,
turbine meters with tungsten carbide, or similar, bearings are preferred. Adverse fluid
conditions may include solids, poor lubricity (e.g. liquefied gases), rouge and sulphur
compounds.
Meter selection shall take into account maximum process conditions to ensure the
meter does not over speed.
Magnetic flow meters shall have automatic empty pipe detection capability
incorporated.
Where magnetic flow meters are installed in non-conducting piping then the option of
either reference electrodes or earth rings shall be used depending on the meter
selected.
Care should be taken to provide sufficient straight run in the piping for the ultra-sonic
flow meter and that the pipe through the meter is always full of fluid to ensure the
accuracy meets requirements.
60A1 READING Rev 2 COPY DSN:
C& I ENGINEERING
60A1 (READING)
C&I GENERAL FWUK OU PAGE 25 OF 58
SPECIFICATION STANDARD ENGINEERING REV 2
Ultrasonic flow meters shall not be used where gas bubbles may be present in single
phase liquid flow applications.
Care should be taken in the installation to avoid dirt, air gaps and other piping
inclusions in the sensor area as this will adversely affect the accuracy. Ultra-sonic flow
meters shall be installed so that there is no vibration effect on the meter.
Vortex flow meters shall be installed so that there is no vibration effect on the meter.
Venting and draining shall be considered during placing and installation, especially for
hazardous and toxic fluids.
Coriolis flow meters shall be installed so that there is no vibration effect on the meter.
All coriolis installations shall be checked for cavitation and choked flow conditions due
to the high velocities of the fluid through the meter.
Coriolis meter’s sensitivity to specific heat variations in the process fluid due to
variation in composition or temperature of the fluid should be compensated for to
ensure the accuracy of the measurement.
Venting and draining shall be considered during placing and installation, especially for
hazardous and toxic fluids.
10.1 General
Each individual instrument shall be supplied with dedicated process connections,
process isolation, drain and vent valves.
Level nozzles should be placed such that influences of inlet / outlet disturbances are
minimised or deflectors should be installed to improve the accuracy of the
measurement.
Nozzle elevation should be selected so that offsets are eliminated and reduced range
calibrations are minimised.
A secondary method of checking the process level shall be provided, e.g. a level
gauge. The range of level gauges shall cover the completed operating range of any
related level transmitter installed on the same vessel section to provide the field
60A1 READING Rev 2 COPY DSN:
C& I ENGINEERING
60A1 (READING)
C&I GENERAL FWUK OU PAGE 26 OF 58
SPECIFICATION STANDARD ENGINEERING REV 2
operator with a means of verifying the actual level compared to the measurement on
the level transmitter.
Level instruments connected directly on the vessel shall be in accordance with the
65A1, C&I / Piping Interface Specification.
Where the number of vessel tapping is excessive, standpipes may be used although
safety instruments shall be via dedicated nozzles.
For vessels and columns: Magnetic level glasses shall be the first choice.
For tanks: Float type instruments or differential pressure instruments are
preferred.
For viscous fluids or high temperature applications: Magnetic type shall be used.
Tubular glass type gauges shall not be used, except where specified by a
Process Licensor.
Each gauge shall be stamped with the maximum working pressure and
temperature.
Through vision and reflex gauges shall be fitted with toughened glass.
Expansion and contraction of gauges used on hot or cold liquids shall be
compensated by integrally fitted pipe work.
Integral illuminators may be provided for through vision gauges. The power
supply to the illuminator shall be AC, 50Hz single phase.
Where multiple gauges are required to cover the required visible span, each gauge
shall overlap by at least 25 mm.
Reflex gauges shall be used for liquid and vapour interface detection except in the
following circumstances, where through vision gauges shall be used:-
Gauges that require heat tracing shall be supplied with the manufacturer standard
integral steam tracing tube / jacket.
All gauges shall be supplied with manual shut-off valves with ball check facilities on the
top and bottom mountings and full bore vent and drain valves. Valves shall be of a
quick acting, offset type and shall have bolted bonnets.
All gauges shall be designed for the design conditions of the vessel and should be
suitable for full vacuum conditions.
Nozzle elevation should be chosen to remove offsets (elevated zeros) and reduced
range calibrations minimised.
Where accuracy is not of prime importance, and where the tank is vented to
atmosphere, contents measurement may be made by a hydrostatic level instrument.
Diaphragm seals shall be of the flanged type. A “flushing ring” shall be fitted between
the primary isolation valve and the diaphragm seal. The “flushing ring” may serve as
flushing connections and/or calibration connection and/or be provided with a bleed plug
and/or drain valve to allow safe removal of the diaphragm seal. The flushing ring and
valves where required shall be supplied with the diaphragm seal assembly.
Where identified on the P&ID, diaphragm seals should be specified with extended
seals and not flushing rings. This is necessary to avoid collection of solids within the
vessel nozzle assembly.
While selecting pressure instruments with remote diaphragm seals and capillary,
consideration shall be given to material selection in view of design pressure (vacuum),
temperature (vapour pressure fill fluid) and chemical resistance. In general, remote
seals shall not be applied in services with an operating temperature in excess of 550F
(300C) or operating pressure in excess of 750 psig (50 barg). Seals in vacuum
services shall be avoided.
The diaphragm seal size and type of connections must match the vessel piping design.
Displacers shall use externally mounted chambers. Chambers shall be designed with
side-and-side connections wherever possible.
Only one level instrument is allowed per chamber, and the chamber shall have block,
drain and vent valves. Design should address the fact that the level in the chamber
could differ from the level in the vessel e.g. density differences.
Internal displacers may be used where an external arrangement is not possible e.g.
sumps. Where the displacer is subjected to turbulence, the effect shall be minimised by
shielding, guidance or other means.
Float type instruments shall use switches in externally mounted chambers. Float
operated level switches shall be glandless.
Integral stops shall be provided to limit the angle of float travel and shall be located as
near to the float as practical.
The float arm and float shall be able to pass through and clear the nozzle through
which they are installed.
Stilling wells can be used to reduce the effect of turbulent surfaces, stirrers and other
vessel internals on the measurement.
Manufacturer standard probe lengths shall be used wherever possible. Use of non-
standard lengths shall not be permitted. Probe shall be normally be fully insulated with
flange connections in accordance with the vessel trim specification.
11.2 General
Nucleonic instruments are not preferred and should only be considered as a last resort
and subject to Client approval.
The shielded container consisting of a steel encased lead holder with suitable
mounting facility shall house the nuclide.
Suitable top, bottom and side guards should be installed between the source container
face and the vessel or pipe wall such that the gap through which the radiation beam
passes is not accessible.
The shielded container design allows for either pencil (typically 5 degrees) or fan
(typically 20, 30 or 40 degrees) collimated beam of radiation for point or continuous
gauging respectively. The container shall be supplied with in-built shutter assembly and
shutter lock assembly.
When in the open position, the shutter design shall provide for automatic closure when
the locking device is removed from the lock assembly.
The converter analogue output signal shall be 4 to 20 mA and potential free contacts
for point measurement.
60A1 READING Rev 2 COPY DSN:
C& I ENGINEERING
60A1 (READING)
C&I GENERAL FWUK OU PAGE 31 OF 58
SPECIFICATION STANDARD ENGINEERING REV 2
The source serial number, type of isotope material, source activity, date of activity
measurement and design type shall be identified on a stainless steel label permanently
attached to the source container.
Radiation warning signs shall be displayed at all entrances to areas where radioactive
sources are used or installed (typically at 30 m), and where persons could be exposed
to ionizing radiation.
12.1 General
Close coupling of the pressure transmitter to the process fluid is preferred, but
diaphragm seals are acceptable where the fluid will damage or foul the pressure
transmitter or impulse lines.
For the measurement of slurries, viscous or highly corrosive fluids for which a Bourdon
tube or a bellows element is unsuitable, a diaphragm sealed element shall be used.
Instruments measuring pulsating pressures shall be fitted with pulsation dampers. The
use of partially closed isolation valves is not permitted.
All pressure type measurements shall be provided with direct mount manifolds - two-
way manifolds for single pressure and five-way manifolds for DP measurements.
Manifolds shall be minimum 316 stainless steel.
elevated zero may be used. In such instances a pressure gauge shall be installed
adjacent to the transmitter for start-up and shutdown operations.
Pressure elements measuring a steady normal operating pressure shall not exceed
75% of their maximum range. Pressure elements measuring a fluctuating pressure
shall not normally be operated beyond 60% of their maximum range.
For pressure gauges with ranges less than the process design pressure, over-range
protection shall be provided by design or by the use of a separate over-range protector.
Measuring elements shall be C-type Bourdon Tube, manufactured from 316 stainless
steel unless process fluid requires the use of other materials.
The measuring element shall withstand over-ranging to a pressure of 1.3 times the
maximum scale reading without a permanent off set that affects gauge calibration.
Gauge movements shall be constructed from stainless steel and shall be zero
adjustable.
The case shall be solid-front, weather proof and furnished with a blow-out back or
blow-out disc. Cases shall be made of stainless steel.
A visible stop pin shall be used to restrict the upper limit of the pointer travel.
Liquid filled gauges shall be used for pulsating and vibrating services where the
process conditions allow. Liquid filled gauges shall have a small vapour space for
thermal expansion of the liquid fill.
Gauges for the measurement of low pressure or differential pressure shall be of the
bellows or diaphragm type. Dual element gauges shall only be used when the
differential pressure exceeds 10% of the available static pressure.
Zero, normal and full scale pressure readings shall be indicated on the gauge. If the
required range is too large to provide the required accuracy, then another gauge
should be provided to indicate the reduced range.
12.4 Installation
Gauges and indicators shall be located so as to be easily read. Siphons shall be fitted
on steam and hot services.
Pulsation dampers and over-pressure protectors shall be fitted close to the pressure
measuring element. Where space is limited close coupled transmitters may be used.
Pressure gauges shall be connected through excess flow shut-off valves for safety in
the event of element rupture that could cause a hazardous release of process fluid.
60A1 READING Rev 2 COPY DSN:
C& I ENGINEERING
60A1 (READING)
C&I GENERAL FWUK OU PAGE 33 OF 58
SPECIFICATION STANDARD ENGINEERING REV 2
Refer to 60A24, C&I Installation Specification and 65A1 C&I / Piping Interface
Specification for further requirements.
Refer to the 65A1, C&I / Piping Interface Specification for tap-in details.
Body and sensor material shall be suitable for process conditions and be 316 stainless
steel as a minimum.
Diaphragm seals shall be used where it is necessary to protect the instrument from the
process fluid or from viscous liquids. Liquid seals shall not be used for this application.
Control valves shall be grouped into general purpose and severe service application
categories.
Control valves for process liquids and high pressure steam and gases shall in general
be globe type or rotary eccentric plug valves.
Other valve styles may be used where process conditions are such that a globe bodied
valve is not suitable. These valve styles are:
Globe valves may be fitted with double seated trim which shall be top and bottom
guided, or single seated trim with plug or stem guiding or with cage trim.
Control valves with special trim for noise reduction shall have globe bodies and cage
trims.
Angle valves may be used where necessary to prevent the accumulation of solids, on
erosive or flashing service, and for unusually high differential pressures. For very
severe service multi stage low noise valves may be used.
For stream mixing and diverting service such as temperature control of heat exchanger
fluids, dual control valves, one reverse and one direct acting, shall be used. Three-way
control valves shall be avoided.
Larger volume flows and high shut-off differential pressure may be controlled by
segmental ball valves or full bore ball valves. Larger volume flows at lower differential
pressure may be controlled by butterfly valves or rotary eccentric plug valves
Self-acting control valves may be used for local, fixed gain control of utilities, such as
pilot gas systems, nitrogen and potable water streams and where failure action and
lower precision of such devices is acceptable.
The final selection of all valve characteristics, including specialist noise reduction and
anti surge valve trims etc shall be made in consultation with the valve manufacturer.
In general, control valves shall be sized to pass at least the anticipated maximum flow
rate at the permissible pressure drop for the flow rate. Control valves shall be checked
to ensure operability at normal and minimum flow rates and associated pressure drops.
Rangeability shall be checked for the anticipated minimum flow rate.
The valve shall be sized to provide the design flow coefficient Cv plus 10-15% above
the maximum specified flow. Each Control valve shall have their specified design flow
coefficient Cv in the following operating range unless otherwise noted.
The effect of reduced inlet and outlet pipe sizes shall be taken into account when sizing
control valves and checks for cavitation and choked flow conditions shall be performed
at maximum, minimum and normal process conditions.
13.4 Noise
All valves shall be assessed for their noise SPL (Sound Pressure Level). Noise
calculations in accordance with ISO 3744 shall be provided. Predicted noise level at
1m downstream of the valve and 1m normal to the pipe shall not be greater than 80
dBA.
Where the above SPL could not meet with the standard valve then special noise
reduction trims shall be specified if available for application.
Each valve shall have a clearly defined failure action to meet the process application
requirements.
All automated valves opening to flare are fail closed valves in order to minimise the
release to the flare in case of air or power failures. Specific HAZOP Study approval is
required for the use of fail open valves.
Globe valves up to NPS 24” shall be flanged to ASME B16.5 and to ASME B16.47 for
valves larger than NPS 24”.
The face to face dimensions shall comply with ASME B16.10 for all designs of valves.
The minimum nominal size of globe and ball valve bodies shall be DN25 (1").
The body rating and flange rating for all flanged control valves shall be minimum rating
of class 300lb. Body and flange ratings for on / off valves shall be as per line class.
Flangeless valves employing long bolting are not acceptable where process
temperature is below –10°C, above 120°C or in high fire risk areas to prevent failure of
gaskets due to differential expansion.
The shaft on a butterfly valve shall be continuous, through the vane and shall be rigidly
locked to the shaft.
The direction of flow through a valve shall be permanently marked on the body or
flanges.
The degree of seat leakage shall be in accordance with ANSI/FCI 70-2. Control valves
shall have a leakage rate of ANSI/FCI 70-2 Class IV as a minimum.
Control valve leakage requirements will be shown on the instrument and process data
sheets as a minimum and may be included on the P&ID’s. Soft seated valves to meet
the classification “TSO” shall only be used by exception.
Gasket surface finish for raised face flanges shall be in accordance with ASME/ANSI
B16.5 paragraph 6.4.4.
Body and bolting materials shall comply with the ENG. STD 50A10, Piping Material
Specification.
Materials for sour service shall conform to the requirements of NACE MR0175.
Butterfly valves shall be fitted with stainless steel vanes and shafts in a precipitation
hardening material (e.g. 17-4 PH).
Valve internal trim materials shall be in accordance with ENG. STD 50A10, Piping
Material Specification. Manufacturer's equivalent specifications shall be used where
these are of a superior material and performance.
Hard faced trims or hardened trim materials at the seating surface shall be utilised
where fluid is erosive, choked, flashing or when cavitation exists at any flowing
condition
Soft seating materials shall be used only where tight shut off cannot be achieved with
hard seated valves and requires Client approval.
13.9 Actuators
Actuator selection will depend on upon valve selection, service, speed of response and
Supplier. Preferred operation of valves shall be by pneumatically-operated, spring
return, diaphragm or piston actuators. All actuators shall be capable of assuming a
given failure position as defined by the P&IDs
The torque provided by the actuator shall include a 1.5 safety factor in addition to the
basic valve torque requirements for seat material, fluid, operational frequency and
process conditions.
Valve actuators shall be designed to operate fully under a minimum instrument air
pressure in-line with current facility instrument air design.
For control valves, all actuators shall be sized for full range control.
Normal valve closing speeds shall be as below unless stated otherwise on the control
valve data sheet:
60A1 READING Rev 2 COPY DSN:
C& I ENGINEERING
60A1 (READING)
C&I GENERAL FWUK OU PAGE 38 OF 58
SPECIFICATION STANDARD ENGINEERING REV 2
15 – 65 mm ≈ 2 seconds
80 – 150 mm ≈ 3 – 6 seconds : dependant on size
200 – 600 mm ≈ 8 – 24 seconds : dependant on size
Actuator material shall be steel or ductile iron unless stated otherwise on the control
valve data sheet.
Valve actuators shall be sized for the maximum pressure upstream of the valve with
the downstream pressure taken as the lower of zero or the minimum downstream
pressure, which may be less than zero in vacuum service.
Piston actuators shall be used to provide longer strokes or greater thrust than is
available from spring diaphragm units.
Double-acting piston actuators that do not automatically fail to safe position in the
event of air failure shall be avoided if possible. A local receiver, with sufficient capacity
for at least two operations over the full travel of the valve shall be supplied with these
actuators. Receivers shall be supplied with full pressure vessel certification.
13.10 Accessories
Actuators shall be provided with electro-pneumatic, SMART positioners which support
the HART / Foundation Fieldbus Protocol. All positioners shall be fitted with an air filter
regulator and gauges for supply and output pressures.
Trip solenoid valves initiated by a shutdown system to override modulating valves shall
be fitted directly into the actuator inlet line.
All valves shall be fitted with a corrosion proof label marked with tag number,
Manufacturer, valve model number, actuator model number, trim size and type, CV
value, failure mode and input signal as a minimum.
Where the size of control valve has an influence of the capacity of relief valves, such
valves shall have full size trims and shall not be equipped with limit stops. They must
carry a warning label. The inscription shall state:-
WARNING
TRIM SIZE AFFECT RELIEF VALVE CAPACITY
All instrument air tubing and fittings shall be 316 Stainless Steel as a minimum.
Compression fittings shall be double ferrule type.
Limit switches shall be 2 wire proximity type. Limit switches shall be specified and
purchased with the control valves and identified on the P&ID.
All accessories shall be fully piped / wired as part of the valve assembly and shall be
suitably terminated in IP 65 enclosures as a minimum. No accessories shall be
supported by tubing or wiring.
Valves shall be shipped with the un-installed electronic stroke signature to be used as
a reference for set-up and configuration purposes.
Hand wheels shall be able to open or close the valve under full differential pressure.
Hand wheels are preferred to hand operated bypass valves provided that the service is
not severe. A non-severe condition means the valve is expected to last from shutdown
to shutdown. The following conditions are regarded as severe even if the valve is
expected to last from shutdown to shutdown:
Hand wheels shall also be supplied for fail open butterfly valves for installation and
removal. These valves shall be clearly labelled to ensure that the valve flap is not
damaged during removal.
Consideration shall be taken in determining the application of bypass valves where the
use of a bypass valve would exceed the relief valve capacity with or without the control
valve also fully open.
The sizing and specification of bypass valves shall be in accordance with the following:
For control valves DN25 (1") provide a DN25 (1") globe valve, or a DN25 (1")
needle valve, with reduced trim as necessary. In all cases the Cv of the bypass
valve shall be at least equal to and not greater than double the Cv of the control
valve.
60A1 READING Rev 2 COPY DSN:
C& I ENGINEERING
60A1 (READING)
C&I GENERAL FWUK OU PAGE 40 OF 58
SPECIFICATION STANDARD ENGINEERING REV 2
For control valves larger than DN25 (1"), provide a globe valve with Cv at least
equal to and not more than double the Cv of the control valve.
Where the control valve is a butterfly or ball valve, i.e. high capacity, use a valve
of the same design but with a hand actuator.
Consider the use of special hardened trim for bypass valves on noisy, erosive or
corrosive service when the selected control valve has such a trim. Noise control trim
shall not normally be furnished for bypass valves.
Bypass valves shall have the same characteristics as the associated control valve.
Bypass valves are only allowed on trip valves if the valve is tripped to the open position
(FO) or if the valve is tripped closed (FC) and the bypass are sized for a safe flow. In
cases the bypass valve has to be a tagged item with a CV statement and data sheet.
(A ¾” globe valve is typically used in steam service for warm-up purposes).
The block valves should be installed within reducers if the pressure drop and velocities
permit.
Valves with screwed or socket weld ends shall have their ends protected with metal,
wood or plastic plugs.
Valves with flanged ends shall have the gasket surface protected by means of a
suitable wired on disc.
Valves with butt-weld ends shall have the bevels covered with a suitable close fitting
protector.
13.15 Testing
13.15.1 Hydrostatic Test
Valves with carbon steel bodies shall be hydrostatically tested with water not
exceeding 50°C in accordance with ASME B16.5.
Valves leakage classes shall be specified and tested to ANSI / FCI 70-2 or API 598.
Valve shall be completely assembled with packing box fully packed and made up hand
tight. The test shall consist of measuring valve stem position for increasing and
decreasing input signals at 25%, 50% and 75% travel. For valves with positioners not
having a by-pass, dead band shall not exceed 0.5% of rated input signal.
For ‘fabricated’ valves, NDE procedures shall be submitted for review by Buyer in
accordance with ENG.STD 88A1, Submission of welding and manufacturing Procedure
for Review when specially requested.
For all pressure containing components/equipment that does not require CE marking in
accordance with PED, the following minimum requirements apply unless the Project
specification indicates otherwise. In the event of conflict, the Project specification shall
take precedence.
14.1 General
MOV shall only be used for applications that require valve automation for reasons other
than safety or continuous control. Suitable applications for MOVs include product
routing. It shall be noted that MOVs generally require both motor power and a control
command to travel to a given position which makes these unsuitable for applications
with a defined open or closed failure direction.
Special design MOVs that do have a defined failure direction shall only be used with
prior Client approval where technical justification has been provided that the solution is
superior to one using pneumatically or hydraulically actuated valves.
Motor Operated Valves (MOVs) can be used to provide non-safety related isolation on
large process lines where use of manually operated hand valves would be impractical.
Motor Operated Valves are either controlled by the DCS or locally operated manually
by the process operator.
Motor operated valves generally shall be rising-stem type such as gate valves. Other
body styles may be used where a rising-stem gate bodied valve is not suitable.
Standard body sizes shall be selected for each application. (2½” and 5” are not allowed).
The body rating and flange rating for all flanged valves shall be as per line class.
14.3 Actuators
Motors shall be rated for heavy service and the maximum number of starts/operations
of the valve actuator, as recommended by the manufacturer for the life cycle of the
actuator/MOV, shall not be exceed by the required number of operations over the
same period. Where this is not possible, either an alternative valve that does meet the
operational requirement shall be provided, or prior approval from the Client shall be
60A1 READING Rev 2 COPY DSN:
C& I ENGINEERING
60A1 (READING)
C&I GENERAL FWUK OU PAGE 43 OF 58
SPECIFICATION STANDARD ENGINEERING REV 2
obtained so that a reduced lifecycle of the MOV can be taken into consideration as part
of a maintenance plan.
The actuator should be sized to be able to produce twice the amount of torque required
in the application to enable it to handle valves being stuck in position.
The actuator shall also have over current or alternative protection to prevent damage to
the motor in the case of the valve being stuck in position.
The equipment supplied shall be suitable for continuous operation under normal
operating site conditions. Refer to document ENG.STD 01A1, Basic Engineering
Design Data.
Motor supply voltages to the MOV actuator controls shall be 400 VAC 3 phase and
Neutral at 50 Hz. Circuit protection shall be at the substation but a switch disconnector
and fuse shall be provided locally at the motor control centre for the valve actuator in
the field. All other required voltage levels shall be derived internally by MOV motor
controls.
Repositioning of the motor and control box around the centreline of the valve stem
shall be possible without the need for extra supports.
A limit switch and torque switch shall be used to stop the valve travel in the closing
direction. Similarly, a limit switch and torque switch shall be used to stop the valve
travel in the opening direction.
The reversing contactor shall be supplied as part of the valve actuator assembly. After
initiating a close or open action electrically, it shall be possible to reverse the action
without first completing the stroke to the end of valve travel.
The gearbox housing shall be either factory greased and sealed for long life or fitted
with sufficient grease nipples to enable proper maintenance.
Where actuators of the non-locking gear type are used, provisions shall be made to
prevent cycling of the motor due to repeated operations of the torque switches.
Each valve shall be provided with an integral valve position indicator showing
percentage of full travel.
Each valve actuator shall have integral pushbuttons to open or close and stop the
valve.
In addition each valve shall have an integral two position selector switch for “local” or
“remote” selection of operation. The switch shall be designed so that it can be locked
in either of the two positions and will only allow electrical actuation of the valve from the
selected position.
Each actuator shall have auxiliary contacts for remote indication of ‘Open’ and ‘Closed’
positions and ‘Available’ Status. The contacts shall be rated for 2A @ 24 VDC.
Each actuator shall have relays for the remote operation of the valve for ‘Close’ ‘Open’
and ‘Stop’ actions. The relays shall be 24 VDC 1000 Ohm.
Each actuator shall include an auxiliary 24 VDC supply for use by remote lamps /
control buttons, if required.
15.1 General
This section is applicable to automated on/off valves that perform a safety related
function. The term SIS valve as used in this section and the associated applicable
requirements shall not only apply to valves used in emergency isolation but shall also
be applied as relevant to any automated on/off valves on safety related service
including depressurisation and deluge. It should be further noted that the term SIS
valve is not limited to those valves operated by the SIS system and safety design
considerations equally apply to valves operated by other systems including BMS, FGS,
and proprietary packaged control systems.
SIS valves and their accessories shall be selected to meet the required SIL.
Robust actuated and failure action (typically quarter turn, spring return valves
shall be used)
Confirmation of the valve position (typically limit switches, proximity type, shall be
provided in fully open and fully closed positions)
Operation during fire (typically valves shall be fire-safe and approved for fire
isolation)
Tight shut-off requirement (typically for liquid application and inventory isolation
shall have a leakage rate of ANSI/FCI 70-2 class V minimum)
Facility for partial stroke testing (TÜV certified) shall be provided for all valves
that need to be tested on line, i.e. where the valve testing intervals are shorter
than the plant maintenance shutdown intervals
All inventory isolation valves shall comply with the above general requirements as well
as with the following specific requirements:
Only flanged quarter turn type valve bodies approved for fire isolation.
Only spring return actuators with fail close failure action.
All inventory isolation valves have a default leakage rate of ANSI Class VI with
TSO. Soft seated valves shall not be used.
SIS valves shall be ball and high performance butterfly (flanged) valves.
Standard body sizes shall be selected for each application. (2½” and 5” are not allowed).
The body rating and flange rating for all flanged valves shall be as per line class, with a
minimum rating of class of 300#.
Protective system valves for liquid shall have a minimum leakage class rating under the
non-fire conditions of Class V as defined by ANSI/FCI 70-2, Valve Leakage
Classifications. Valves shall have no internal cavities that may collect liquids.
Quarter turn valves shall be used in a protective system service. All protective system
valves shall be flanged.
If full port ball valves are used they shall be double metal seated and trunnion
mounted.
15.6 Actuators
Pneumatically operated, spring return, piston or diaphragm actuators are preferred for
fail open or fail closed valve applications. Hydraulically operated, piston actuators shall
be limited to applications where pneumatically operated actuators cannot produce the
required torque with the given air supply pressures or the physical size of a
pneumatically operated actuator presents major installation problems or is otherwise
not cost effective.
Spring and diaphragm actuators used within hazardous areas shall be fireproofed.
Facility for partial stroke testing (TÜV certified) shall be provided for all valves that need
to be tested online, i.e. where the valve testing intervals are shorter that the plant
maintenance shutdowns.
All actuators shall be sized to operate with a minimum instrument air pressure of 3.5
barg.
A backup energy source shall be provided for valves that do not utilize spring return
actuators to drive the valve to the safe position. Any air storage drums provided shall
be sized to stroke the valve three times (i.e. from open to closed to open).
Pneumatically operated, spring return, piston or diaphragm actuators are preferred for
fail open or fail closed valve applications. Hydraulically operated, piston actuators shall
be limited to applications where pneumatically operated actuators cannot produce the
required torque with the given air supply pressures or the physical size of a
pneumatically operated actuator presents major installation problems or is otherwise
not cost effective. Spring and diaphragm actuators used within hazardous areas should
be fireproofed.
Facility for partial stroke testing shall be provided where required, e.g. to be tested in
service based on SIL testing interval or Client requirement.
15.7 Accessories
15.7.1 Position Switches
SIS valves shall be fitted with open and closed limit switches to confirm the position of
the valve in cases of emergency. Limit switches shall be 2 wire proximity type. Limit
switches shall be specified and purchased with the SIS valves and identified on the
P&ID.
SIS valves shall be operated by solenoid valves. Solenoids shall be mounted on the
shutdown valve. Solenoid coils shall be of the epoxy-encapsulated type and quick
exhaust rated for continuous duty. The solenoid shall be of the three way type with a
316 stainless steel body. Solenoid Valves shall be certified for the SIL level
requirement.
A control valve with an independent SIS solenoid valve may be used to assist in
achieving a higher SIL rating, but shall not be used alone to perform a shutdown or
inventory isolation task. This shall be subject to SIL validation calculations.
SIS valves shall be operated by solenoid valves with a robust fail action that are
mounted on the valve. Typically the solenoid valves shall be constructed from 316
stainless steel and shall only be installed in pneumatic signal lines.
The valve, including the actuator and any associated positioner or solenoid valves,
shall not have a facility to apply a manual locking device that could be used to defeat
the operation of the valve to the tripped position by latching the valve in the normally
open or closed operating state.
Typically SIS valves shall be remotely reset by the operator in the control room via the
SIS logic. However, in some instances manual local reset shall be specified for SIS
valves when there is a specific action for the field operator to perform before the trip
can be cleared.
SIS valve, including the actuator and any associated positioner or solenoid valves,
shall not have a facility to apply a manual locking device that could be used to defeat
the operation of the SIS valve to the tripped position by latching the valve in the
normally open or closed operating state.
SIS valve accessories, such as air filter pressure regulator, solenoid valves, lock-up
relays, switches, etc., shall be specified and mounted on the valve as an integral part of
the valve assembly.
15.9 Testing
All SIS valves shall be completely assembled and tested in the factory. Tests shall
include hydrostatic test, seat leakage test, mechanical operation tests and testing of
valve opening and closing times.
In general, valves shall move to their de-energized (fail) position within 2 seconds.
When this target cannot be met with additional equipment (e.g. booster relay, quick
exhaust valve) the Client shall be consulted.
16.1 Selection
Safety relief valve types shall usually be determined based on a built up back pressure
at the valve no greater than:
10% of the valve set pressure for a conventional (non-balanced) type valve
30% of the valve set pressure for a balanced bellows type valve
In addition, total back pressure up to 50% of the valve set pressure is allowed for
balanced bellows type valve.
Pilot operated relief valves shall be used for back pressure greater than 50% of valve
set pressure.
Thermal relief valves shall be provided where liquid lines can be blocked in.
Rupture Disks and Rupture Pin Devices shall meet the relevant requirements of ASME
Sec VIII and be ASME Code Stamped UD.
16.2 Sizing
Relief valves shall be sized in accordance with the following basis:-
API RP520.
16.3 Design
Flanged Relief valves shall be designed in accordance with API RP 526. Minimum inlet
flange rating shall be ASME B 16.5 class 300 for relief valves with 16 inch and smaller
with exception to relief in atmospheric and low pressure tank services, where class 150
shall be used.
Lifting lever shall be as per ASME SEC I and ASME SEC VIII requirements.
Refer to API RP 521 for noise limitation requirements where no regulatory authorities
have defined the allowable levels of noise exposure for personnel or at property limits
on the Project. Sound power calculations are required if there is a vibration risk.
16.4 Installation
Relief valves shall be installed in accordance with API RP 520.
16.5 Application
16.5.1 Conventional Type
Conventional type pressure relief valves shall only be used where the back pressure is
substantially constant (e.g. atmospheric relief) and the sum of maximum variable
superimposed back pressure plus built up back pressure is less than 10% of set
pressure and fouling or corrosive conditions are not expected.
Conventional type relief valves shall be of the nozzle entry type having enclosed
springs and conforming to API RP 526 except for steam or hot condensate when open
bonnets shall be used.
Bodies shall be carbon or alloy steel and trims 12% Cr alloy or other suitable corrosion
resistant alloy.
For flammable or toxic service, bonnets shall be vented to the discharge side of the
valve.
Balanced type relief valves shall be used for all relief services into the flare systems. All
designs (piston type, bellows type etc.) may be considered.
Bonnet and bellows vent shall be routed with minimum restriction to a safe location.
In bellows type pressure relief valves, bonnet shall be vented separately from
discharge.
Pilot operated relief valves shall not be used in fouling or high temperature service.
Pilot assisted valves shall be considered where accuracy or rapid opening and closing
are required.
Gas chromatographs and analysers shall be provided to meet Project’s process and
utilities requirements and shall be engineered as a complete analyser system package
which receives samples from the analyser process probe, transports and conditions the
sample, performs the measurements and transmits the process variable signals and
associated status and alarm signals to the Analyser Data Acquisition and Maintenance
System and the ICSS.
Many materials commonly used in control valves have ignition temperatures above the
normal flowing temperature of gaseous oxygen. The danger is when abnormal,
localized, high temperatures lead to ignition of these materials.
Use of organic materials in contact with oxygen should be avoided, particularly when
the material is directly in the flow stream. When an organic material must be used for
parts such as valve seats, diaphragms, or packing, it is preferable to select a material
with the highest possible ignition temperature, the lowest specific gravity and the
necessary mechanical properties.
The following materials are listed from highest to lowest resistance to ignite, in on
oxygen service:
In general, diaphragm casings, diaphragm plates, springs, and other parts not in the
main flow stream may be of ordinary materials such as carbon steel, stainless steel, or
cast iron. However all valve body and trim parts in contact with the flow stream shall be
made of copper, copper alloy or nickel-copper alloys.
Organic materials shall be avoided for use in valve seats or other parts exposed to the
flow stream.
Non-ferrous, inorganic filters shall be placed upstream of valves and regulators. Filters
shall have regular maintenance and cleaning.
Plated parts shall not be used in the main oxygen flow stream because of their
potential contributions to foreign particle impingement.
The following standards should be referred for guidance in designing instrument hook-
ups, etc for oxygen services:
ASTM G128
ASTM G88
NFPA 53
The basic criteria when designing hook-ups for oxygen enriched services are:
Adding to the detrimental effects that hydrogen can have on the valve, operating
conditions such as temperature, pressure and concentration of hydrogen should be
considered when selecting the right materials. Additional steps, such as post-weld heat
treatment shall be required.
Much of this risk analysis associates the presence of hydrogen in the stream to the
possibility of metallic material corrosion such as hydrogen attack, embrittlement and
blistering. API 941 Recommended Practices shall be considered when selecting
instruments and valves in a Hydrogen service.
Heat-treating and inspection methodologies shall be used to reduce the risk of valve
leakage in hydrogen environments.
Hydrogen leakage in valves occurs through two key paths. Leakage at the seat allows
hydrogen to pass when the valve is closed. In this leakage, the gas is contained within
the process. The more critical leakage is through the stem, which can result in gas
escaping to the atmosphere.
19.3 Inspection
Radiographic x-rays and dye-penetration testing shall be used to check for internal
defects, including cracks, hot tears, holes and gas inclusions. The internal volume of
the valve is checked to address hydrogen blistering.
Testing fully assembled valves with high pressure helium to search for leakage shall be
considered. Because the helium atom is very close in size to the hydrogen, this testing
best simulates operating conditions. Low-pressure testing indicates losses due to leaks
and porosity, while the high pressure testing ensures there is no deformation of
sufficient magnitude to cause losses.
Post weld heat treatment shall be used on all valves in a hydrogen service. Post weld
heat treatment of 0.5 molybdenum (Mo) and chromium-Mo steels shall be considered.
The following factors shall be considered when specifying valves for hydrogen service:
The finish for the gasket contact surface, of metal flanges in hydrogen service is
typically between Ra 2 and 3.2 micrometers (79-125 micro inch).
20.1 General
60A1 READING Rev 2 COPY DSN:
C& I ENGINEERING
60A1 (READING)
C&I GENERAL FWUK OU PAGE 53 OF 58
SPECIFICATION STANDARD ENGINEERING REV 2
Requirements for Fire and Gas Detectors shall be in accordance with 60A22, Fire &
Gas System Specification.
Analyser houses shall be treated as a normal process area and not as a building. For
specifics on Fire and Gas detection in analyser houses refer to the 60A25, Process
Analyser System Specification.
Field tests shall be required to establish optimum sighting angles of burners or nozzles
and to check the effective angular range of flame detectors in relation to burners or
nozzles.
Clean air, where necessary, shall be supplied to minimize problems with dirty detector
lenses. The cleanliness of the lens should be verified automatically by the detector.
Self-checking features shall be provided to ensure that the failure of any single
component cannot result in a false indication of flame.
Care should be taken to ensure that the effects of lighting, arc welding, radiation and
sunlight do not affect the accuracy or reliability of the flame detector.
21.1 General
The Project shall provide for safe and reliable process operations by installing an
Integrated Control and Safety System (ICSS) consists of Distributed Control System
(DCS), Safety Instrumented System (SIS), Fire and Gas System (FGS), Burner
Management System (BMS) and other auxiliary monitoring and control systems which
are indicated in this section e.g. Compressor Control System (CCS), Machine
Monitoring System (MMS), Custody Metering System and Packaged proprietary control
and trip systems.
The ICSS shall maintain a fully integrated concept to provide a ‘single window’ to the
operator where all subsystem operator interface requirements are incorporated within
the same system.
All ICSS shall be time synchronised to an external GPS master clock system typically
using Network Time Protocol. In this way, information gathered by all the subsystems
within the ICSS system’s devices on alarms and events shall be accurately sequenced.
The ICSS shall generate and transfer all system maintenance diagnostics and trouble-
shooting data to the DCS which shall consolidate this information from all devices and
all subsystems into a graphical interface.
All ICSS shall have centralised engineering and maintenance capability which enable
routine engineering and maintenance activities to be performed from engineering and
maintenance consoles located in the Engineering Room in the Central Control Building.
In addition, engineering and maintenance activities can also be conducted from the
operator consoles located in the respective ISBs. These consoles can also be used for
start-up and shutdown activities.
The DCS processing equipment including networks, interfaces, system and marshalling
cabinets shall be located in the respective ISBs located close to the process
equipment. Field instrumentation shall be wired directly to the I/O processors within
the ISB.
Field mounted remote I/O processors shall, in principle, not be used unless distance
becomes a factor to be considered.
The DCS shall seamlessly interface with all ICSS subsystems (such as the SIS, BMS,
FGS, CCS, MMS, etc) allowing the operator to view the entire plant via operator
consoles.
Pre-alarms shall be provided for all trip signals where operator intervention is possible
to prevent a trip situation. Additional alarms shall be provided to warn the operator of
impending shutdown or shutdown occurrence. All alarm signals shall be routed to the
DCS.
Instruments used on non voted shutdown duty shall be separate from those used on
control, indicating or recording duty and shall have separate process connections,
except in the case of flow trips with a common orifice plate which may be used. Each
DP flow instrument shall have separate tapings.
Where three or more transmitters are used in a multiple voting configuration for
safeguarding, the median value from transmitters may be used for the control
application in the DCS. The signal is available in the DCS directly from the SIS and an
independent transmitter for the DCS is not required. The loop power for the transmitter
shall be provided by the SIS.
Safety Integrity level (SIL) classification shall be determined for all safeguarding
instrument loops (SIF) including within packaged units. For instruments and final
elements connected to the SIS, the field redundancy depends on Safety Integrity Level
(SIL) requirements and the reliability and integrity of the chosen devices and as such,
specific attention shall be applied during the equipment selection stage to meet these
requirements including overall PFDavg values. Suitable testing facilities shall be
provided to be able to test both the initiators and final elements in line with the
specified SIL requirements to meet IEC 61508 and IEC 61511 requirements.
The SIS shall be designed to meet the requirements of IEC 61508 and IEC 61511
specifications with a maximum scan time of 300 milliseconds and a minimum safety
system SIL rating of SIL 3 with full redundancy on all components.
The SIS shall be interfaced to the DCS via separate redundant communication links.
Safety Instrumented System (SIS) shall be designed in accordance with 60A11, Safety
Instrumented System Specification.
The FGS shall be designed to meet the requirements of IEC 61508 and IEC 61511
specifications and shall be based on the same hardware and software as used for the
SIS.
The FGS shall be interfaced to the DCS via separate redundant communication links.
Fire and Gas System (FGS) shall be designed in accordance with 60A22, Fire & Gas
System Specification.
The BMS is a stand-alone system that does not rely on any other system to protect the
fired equipment. In exceptional cases the BMS functions may be incorporated into the
SIS of the particular unit if the number of I/O involved is too small to warrant a stand-
alone BMS and shall only be used with the Client’s written approval.
The BMS shall be designed to meet the requirements of IEC 61508 and IEC 61511
specifications and shall be based on the same hardware and software as used for the
SIS.
Each BMS shall be interfaced to the DCS via separate redundant communication links.
Burner Management System (BMS) shall be designed in accordance with 60A9, Burner
Management System for Fired Equipment Specification.
Machinery shall be categorised into critical, normal and low priority machines which in
turn will define the required level of condition monitoring requirements. These can vary
from offline monitoring to continuous monitoring including diagnostic analysis and
decision support functions.
The MMS shall be interfaced with the DCS via redundant communication links and
MMS trip outputs shall be hardwired to the SIS as required where the tripping function
shall be performed.
The CCS comprises a compressor load control system and a compressor protection
system on all centrifugal compressors, but only a compressor load control system on
all reciprocating and screw compressors.
The protection functions (typically anti-surge protection, overload protection and over-
speed protection etc.) shall be handled by stand-alone compressor protection system
provided by Supplier, unless the compressor is equipped with a compressor
manufacturer’s proprietary control system comprising an integrated load control and
protection system.
Each CCS shall be interfaced to the DCS via redundant communication links.
Packaged proprietary control and trip systems shall only be used with the Client’s
written approval.
60A1 READING Rev 2 COPY DSN:
C& I ENGINEERING
60A1 (READING)
C&I GENERAL FWUK OU PAGE 57 OF 58
SPECIFICATION STANDARD ENGINEERING REV 2
The DCS shall perform the following functions for the packaged equipment: alarm
management, trending, reporting, data archiving, and all advanced functionality. The
DCS shall also integrate the package unit into a single operator interface HMI and shall
integrate the package unit SOE information into a single SOE database.
Each packaged proprietary control and trip system shall be interfaced to the DCS via
redundant communication links.
The Custody Metering System cabinet including flow computers shall be housed in the
associated ISB and shall be linked to a supervisory flow computer located in the CCR
which shall facilitate remote access for support and maintenance.
The Custody Metering System shall be interfaced to the DCS via redundant
communication links.
Each Custody Metering System shall be provided as a complete set of tested and
certified metering system including provers and all instrumentation and electronic
equipment in accordance with:-
Ambient Air Monitoring System (AAMS) shall be designed in accordance with 60A39,
Ambient Air Monitoring System Specification.
Intelligent Motor Control System (IMCS) shall be used with both status and control
signals transmitted over a redundant communications link to the DCS.
Operator starts and stops, and diagnostic information shall be transmitted over this
redundant communications link.
All safety related signals shall be hardwired through IRPs between the SIS and the
MCC.
Any relays installed as part of a safeguarding Instrument loops (SIF) are required to
meet the associated SIL targets.
The DCS shall also interface with the PMS for monitoring of power distribution status
and loads.
The extent of control and indication of motors and switchgear shall be shown on the
P&ID’s.