TATA CONSULTING ENGINEERS LTD.

SURATGARH SUPER CRITICAL THERMAL POWER PROJECT UNIT 7&8(2x660 MW)


Daily Observation Report(Area wise)
Date-26/6/2019
Manpower in
Sl.No Area Activities in progress Nos

Struture work

Final painting

1 Boiler-7

Turbine insulation work is progress 6

Steam blowing pipe dismantling work is progress 4

HP bypass area normalization work is progress 8

CRH NRV fit up work is progress 8


2 Boiler-8
Piping insulation work is progress 20
M/s BHEL needs to take prompt action to increase the manpower to avoid further delay-No action taken
M/s BHEL to submit micro level schedule of balance work to monitor and control the project activities in daily
reports-No action taken
Balance Work Remarks

Spring hanger cover, cleaning and scale Manpower to be increased


fixing
Damaged insulation rectification
Balance insulation
Silencer final painting
Exhaust piping final painting
Structure final painting
Piping Support structure final painting
Smart soot blowers commissioing
LRSB commissioing
HPU skid shifting
Hydralic piping proper supports

Airheater leakage system commissioing

Burner tilting correction


HFO line hydro test and commissioing
HFO line modification in burner area
Sand blowers commissioing
Feeder and Mill F & G commissioing
Fan lube oil piping proper supppot

Burner fire fighting system commissioing


Roof casing painting
Roof area balance insulation

Control oil line flushing Insulation manpower to be increased

Balance instrumentation Work

TDBFP commissioning

Coal feeder completion and commissioing


Coal mill commissioing(Clean air flow test,
trail run and flushing)
Burner tilting checking
Dampers and gate commissioing
Balance oil elevations readiness
ESP GD test and air load test &
commissioing
Smart soot blower modification
Lighting
Fire fighting
Condensate return pump final alignment
and grouting
Condensate return piping and support
Soot blower trail and commissioing
Mill reject system

Furnace Flame monitoring and Analysis


system (FFMAS)
(2 Nos. of Camera & Monitors not
installed.)
Stack monitoring system(CEMS)
Mill Fire Detection System

Gas analyzers for O2, CO, PM2.5, PM10


,Opacity Measurement in APH , ESP & ID
Fan outlet duct.

Furnace Temperature probe (FTP) 2 Nos.


Smart Soot blower system, WSB, LRSB,
APH SB,.
APH leakage control system (ALCS)
SADC dampers for main windbox and SOFA
windbox
Burner Tilt

Coal Mill A,B,C bay instrumentation works.


Coal Mill D,E,F,G bay instrumentation
works.
Mill Seal air system
APH A & B
SCAPH
Reheater & Super heater spray station
PA header pressure Control
Air & Flue Gas system
Separator level control

ID FAN A & B Outlet gate blower (HNA 70


AN 001 & HNA 75 AN 001) not yet
installed.
FTDT Pump recirculation valves pneumatic
type.
( LCL30AA101, LCL30AA102 ,
LCL30AA103 )
FTDT Drain water temperature control
valve is not erected. (LCL20AA101)
Boiler tube leakage detection system
(BTLDS)

delay-No action taken


he project activities in daily basis and generate the variance and other necessary