SURATGARH SUPER CRITICAL THERMAL POWER PROJECT UNIT 7&8(2x660 MW)
Daily Observation Report(Area wise) Date-26/6/2019 Manpower in Sl.No Area Activities in progress Nos
Struture work
Final painting
1 Boiler-7
Turbine insulation work is progress 6
Steam blowing pipe dismantling work is progress 4
HP bypass area normalization work is progress 8
CRH NRV fit up work is progress 8
2 Boiler-8 Piping insulation work is progress 20 M/s BHEL needs to take prompt action to increase the manpower to avoid further delay-No action taken M/s BHEL to submit micro level schedule of balance work to monitor and control the project activities in daily reports-No action taken Balance Work Remarks
Spring hanger cover, cleaning and scale Manpower to be increased
fixing Damaged insulation rectification Balance insulation Silencer final painting Exhaust piping final painting Structure final painting Piping Support structure final painting Smart soot blowers commissioing LRSB commissioing HPU skid shifting Hydralic piping proper supports
Airheater leakage system commissioing
Burner tilting correction
HFO line hydro test and commissioing HFO line modification in burner area Sand blowers commissioing Feeder and Mill F & G commissioing Fan lube oil piping proper supppot
Burner fire fighting system commissioing
Roof casing painting Roof area balance insulation
Control oil line flushing Insulation manpower to be increased
Balance instrumentation Work
TDBFP commissioning
Coal feeder completion and commissioing
Coal mill commissioing(Clean air flow test, trail run and flushing) Burner tilting checking Dampers and gate commissioing Balance oil elevations readiness ESP GD test and air load test & commissioing Smart soot blower modification Lighting Fire fighting Condensate return pump final alignment and grouting Condensate return piping and support Soot blower trail and commissioing Mill reject system
Furnace Flame monitoring and Analysis
system (FFMAS) (2 Nos. of Camera & Monitors not installed.) Stack monitoring system(CEMS) Mill Fire Detection System
Gas analyzers for O2, CO, PM2.5, PM10
,Opacity Measurement in APH , ESP & ID Fan outlet duct.
Furnace Temperature probe (FTP) 2 Nos.
Smart Soot blower system, WSB, LRSB, APH SB,. APH leakage control system (ALCS) SADC dampers for main windbox and SOFA windbox Burner Tilt
Coal Mill A,B,C bay instrumentation works.
Coal Mill D,E,F,G bay instrumentation works. Mill Seal air system APH A & B SCAPH Reheater & Super heater spray station PA header pressure Control Air & Flue Gas system Separator level control
ID FAN A & B Outlet gate blower (HNA 70
AN 001 & HNA 75 AN 001) not yet installed. FTDT Pump recirculation valves pneumatic type. ( LCL30AA101, LCL30AA102 , LCL30AA103 ) FTDT Drain water temperature control valve is not erected. (LCL20AA101) Boiler tube leakage detection system (BTLDS)
delay-No action taken
he project activities in daily basis and generate the variance and other necessary