Sie sind auf Seite 1von 4

Minera Panamá Project / OPERATIONS LOTO IMPLEMENTATION

First Quantum

Project Start Date 10/21/2018 (Sunday) Display Week 1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
Project Lead Robert Gordon 22 Oct 2018 29 Oct 2018 5 Nov 2018 12 Nov 2018 19 Nov 2018 26 Nov 2018 3 Dec 2018 10 Dec 2018
22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

WORK
0 TASK LEAD START END DAYS % DONE M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DAYS

1 PROCEDURE Mon 10/22/18 Thu 12/20/18 60 44


1.1 PROCEDURES Carlos Quispe Tue 10/23/18 Tue 12/11/18 50 36
1.1.1 PTW Carlos Quispe Wed 10/24/18 Wed 10/31/18 8 75% 6
1.1.1.1Draft procedure Thu 10/25/18 Fri 10/26/18 2 100% 2
1.1.1.2Approve procedure Fri 10/26/18 Sat 10/27/18 2 0% 1
1.1.1.3Checklist form - -
1.1.1.4Template - -
1.1.1.5Checklist form Sat 10/27/18 Sun 10/28/18 2 100% 0
1.1.2 JHA Carlos Quispe Tue 10/30/18 Tue 11/06/18 8 75% 6
1.1.2.1Draft procedure Wed 10/31/18 Thu 11/01/18 2 100% 2
1.1.2.2Approve procedure Thu 11/01/18 Fri 11/02/18 2 0% 2
1.1.2.3Checklist form Fri 11/02/18 Sat 11/03/18 2 100% 1
1.1.3 LOTO Carlos Quispe Mon 11/05/18 Mon 11/12/18 8 75% 6
1.1.3.1Draft procedure Tue 11/06/18 Wed 11/07/18 2 100% 2
1.1.3.2Approve procedure Wed 11/07/18 Thu 11/08/18 2 0% 2
1.1.3.3Checklist form Thu 11/08/18 Fri 11/09/18 2 100% 2
1.1.4 WAH Carlos Quispe Sun 11/11/18 Sun 11/18/18 8 75% 5
1.1.4.1Draft procedure Mon 11/12/18 Tue 11/13/18 2 100% 2
1.1.4.2Approve procedure Tue 11/13/18 Wed 11/14/18 2 0% 2
1.1.4.3Checklist form Wed 11/14/18 Thu 11/15/18 2 100% 2
1.1.5 CONFINED SPACES Carlos Quispe Sat 11/17/18 Sat 11/24/18 8 75% 5
1.1.5.1Draft procedure Sun 11/18/18 Mon 11/19/18 2 100% 1
1.1.5.2Approve procedure Mon 11/19/18 Tue 11/20/18 2 0% 2
1.1.5.3Checklist form Tue 11/20/18 Wed 11/21/18 2 100% 2
1.1.6 HOT WORKS Carlos Quispe Fri 11/23/18 Fri 11/30/18 8 75% 6
1.1.6.1Draft procedure Sat 11/24/18 Sun 11/25/18 2 100% 0
1.1.6.2Approve procedure Sun 11/25/18 Mon 11/26/18 2 0% 1
1.1.6.3Checklist form Mon 11/26/18 Tue 11/27/18 2 100% 2
1.1.7 EXCAVATIONS Carlos Quispe Thu 11/29/18 Thu 12/06/18 8 75% 6
1.1.7.1Draft procedure Fri 11/30/18 Sat 12/01/18 2 100% 1
1.1.7.2Approve procedure Sat 12/01/18 Sun 12/02/18 2 0
1.1.7.3Audit checklist form Sun 12/02/18 Mon 12/03/18 2 100% 1
2 DOCUMENTS - -
2.1 PTW Carlos Quispe - 0% -
2.1.1 Theorical training Carlos Quispe - -
0.0.0.1Develop training plan - -
0.0.0.1Training for Superintendets & Supervisors - -
0.0.0.1Training for Permit requester - -
0.0.0.1Training for Permit Issuer - -
0.0.0.1Training for Permit Holder - -
0.0.0.1Competence Test - -
2.1.2 Practical training Carlos Quispe - -
0.0.0.1Develop training plan - -
0.0.0.1Training Supervisors - -
0.0.0.1Training Operators - -
0.0.0.1Training for Permit requester - -
Project Start Date 10/21/2018 (Sunday) Display Week 1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
Project Lead Robert Gordon 22 Oct 2018 29 Oct 2018 5 Nov 2018 12 Nov 2018 19 Nov 2018 26 Nov 2018 3 Dec 2018 10 Dec 2018
22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

WORK
0 TASK LEAD START END DAYS % DONE M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DAYS

0.0.0.1Training for Permit Issuer - -


0.0.0.1Training for Permit Holder - -
0.0.0.1Competence Test - -
2.2 JHA Carlos Quispe - -
2.2.1 Theorical training Carlos Quispe - -
0.0.0.1Develop training plan - -
0.0.0.1Training for Superintendets & Supervisors - -
0.0.0.1Training for Permit requester - -
0.0.0.1Training for Permit Issuer - -
0.0.0.1Training for Permit Holder - -
0.0.0.1Competence Test - -
2.2.2 Practical training Carlos Quispe - -
0.0.0.1Develop training plan - -
0.0.0.1Training Supervisors - -
0.0.0.1Training Operators - -
0.0.0.1Training for Permit requester - -
0.0.0.1Training for Permit Issuer - -
0.0.0.1Training for Permit Holder - -
0.0.0.1Competence Test - -
2.3 LOTO Carlos Quispe - -
2.3.1 Theorical training Carlos Quispe - -
0.0.0.1Develop training plan - -
0.0.0.1Training for Superintendets & Supervisors - -
0.0.0.1Training for Permit requester - -
0.0.0.1Training for Permit Issuer - -
0.0.0.1Training for Permit Holder - -
0.0.0.1Training for isolator - -
0.0.0.1Competence Test - -
2.3.2 Practical training Carlos Quispe - -
0.0.0.1Develop training plan - -
0.0.0.1Training Supervisors - -
0.0.0.1Training Operators - -
0.0.0.1Training for Permit requester - -
0.0.0.1Training for Permit Issuer - -
0.0.0.1Training for Permit Holder - -
0.0.0.1Training for isolator - -
0.0.0.1Competence Test - -
2.4 WAH Carlos Quispe - -
2.4.1 Theorical training Carlos Quispe - -
0.0.0.1Develop training plan - -
0.0.0.1Training for Superintendets & Supervisors - -
0.0.0.1Training for Permit requester - -
0.0.0.1Training for Permit Issuer - -
0.0.0.1Training for Permit Holder - -
0.0.0.1Competence Test - -
2.4.2 Practical training Carlos Quispe - -
0.0.0.1Develop training plan - -
0.0.0.1Training Supervisors - -
0.0.0.1Training Operators - -
0.0.0.1Training for Permit requester - -
0.0.0.1Training for Permit Issuer - -
Project Start Date 10/21/2018 (Sunday) Display Week 1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
Project Lead Robert Gordon 22 Oct 2018 29 Oct 2018 5 Nov 2018 12 Nov 2018 19 Nov 2018 26 Nov 2018 3 Dec 2018 10 Dec 2018
22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

WORK
0 TASK LEAD START END DAYS % DONE M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DAYS

0.0.0.1Training for Permit Holder - -


0.0.0.1Competence Test - -
2.5 CONFINED SPACES Carlos Quispe - -
2.5.1 Theorical training Carlos Quispe - -
0.0.0.1Develop training plan - -
0.0.0.1Training for Superintendets & Supervisors - -
0.0.0.1Training for Permit requester - -
0.0.0.1Training for Permit Issuer - -
0.0.0.1Training for Permit Holder - -
0.0.0.1Competence Test - -
2.5.2 Practical training Carlos Quispe - -
0.0.0.1Develop training plan - -
0.0.0.1Training Supervisors - -
0.0.0.1Training Operators - -
0.0.0.1Training for Permit requester - -
0.0.0.1Training for Permit Issuer - -
0.0.0.1Training for Permit Holder - -
0.0.0.1Competence Test - -
2.6 HOT WORKS Carlos Quispe - -
2.6.1 Theorical training Carlos Quispe - -
0.0.0.1Develop training plan - -
0.0.0.1Training for Superintendets & Supervisors - -
0.0.0.1Training for Permit requester - -
0.0.0.1Training for Permit Issuer - -
0.0.0.1Training for Permit Holder - -
0.0.0.1Competence Test - -
2.7 EXCAVATIONS Carlos Quispe - -
2.7.1 Theorical training Carlos Quispe - -
2.7.1.1Develop training plan - -
2.7.1.2Training for Superintendets & Supervisors - -
2.7.1.3Training for Permit requester - -
2.7.1.4Training for Permit Issuer - -
2.7.1.5Training for Permit Holder - -
3 HARDWARE - LOGISTIC - -
3.1 LOTO - -
3.1.1 LOTO Conteiners Carlos Quispe - -
3.1.1.1 File cabinets - -
3.1.1.2 Stand for LOTO Materials and lock board - -
3.1.1.3 Formats printing - -
3.1.1.4 Loto materials list request for JDE - -
3.1.1.5 PC with desk, drawer and tools - -
3.1.2 LOTO site stations Carlos Quispe - -
3.1.2.1 LOTO stations desing and construction - -

3.1.2.2 installation in each area and coding of the stations - -

3.1.2.3 Implementation with LOTO materials and formats - -


3.1.2.4 Implementation of isolation plan of each system by area - -

3.2 WAH - -
3.2.1 implementation of WAH personal systems. - -
3.2.2 implementation of WAH colective systems. - -
3.2.3 Purchase of WAH signals - -
3.2.4 WAH formats printing - -
3.3 PTW, JHA, HOT WORKS, EXCAVATIONS, CONF, SPACE - -
3.3.1 Printing, numbering and formatting of PTW - -
Gantt Chart Template Pro

Gantt Chart Template Pro is similar to this free version, but


it is more feature-packed. It also comes with other bonus content.

Learn About Gantt Chart Template Pro


https://www.vertex42.com/ExcelTemplates/excel-gantt-chart.html

The following link is a blog post that talks specifically about the
Pro version for Excel Online.

Gantt Chart Template Pro for Excel Online

Benefits and Features of Gantt Chart Template Pro

Simple Color-Coding
The Pro version includes a column for specifying the color of bars in the chart. For example,
you could change the color based on urgency or task lead.

Daily, Weekly, or Monthly View


The Pro version includes a drop-down next to the Display Week that lets you choose to display
the columns in the chart area as days, weeks, or months.

Use Work Days as an Input


By default, the Pro version is set up to have you enter Work Days instead of Calendar Days.
The expanded set of template rows provides more options for defining the Start date, End date,
and Duration of tasks. Define a task based on …
- Start date and End date
- Start date and Work days
- Start date and Calendar days

Easily Create Task Dependencies


Though you can still use your own formulas for creating task dependencies, the Pro version
includes template rows that calculate the Start date based on the WBS number that you enter
in the Predecessor column.

Exclude Holidays from Work Days


List holidays and other specific non-working days that you want to exclude from work days.

Customize Your Work Week


The versions designed for Excel 2010+ use the WORKDAY.INTL() and NETWORKDAYS.INTL()
functions that allow you define the work week as something other than Monday-Friday.

Learn More About Gantt Chart Template Pro

Das könnte Ihnen auch gefallen