WPC PS-01

EPCC LIGHT RAIL TRANSIT (LRT) JABODEBEK


POWER SUPPLY SYSTEM PROJECT

TIMELINE CHART OF COMPLETION


CUT OFF : 24 APRIL 2019
OVERVIEW LINE 1

OVERVIEW LINTAS PELAYANAN 1

STATION STATION STATION STATION

TPSS KP RAMBUTAN

TPSS HARJAMUKTI
TPSS CIRACAS 1

TPSS CIRACAS 2
TPSS CAWANG

TPSS CILILITAN

TPSS TMII
U-SHAPE
long span 1

long span 2
turn out 1

turn out 2

turn out 3

turn out 4

turn out 5

turn out 6
Note:
1. TPSS 2. Cable
= Finish pekerjaan internal TPSS / Station A = Cable sudah di pulling
= Sedang berlangsung pekerjaan internal TPSS / Station B = Cable belum dipulling
= MV Cable
= LV, & Control Cable
= DC Cable to 3rd Rail

EPCC LRT JABODEBEK POWER SUPPLY SYSTEM | EPC DEPARTMENT | APRIL 2019
TIMELINE SERVICE LINE 1
DESCRIPTION / DATE 15-Apr-19 30-Apr-19 15-May-19 31-May-19 15-Jun-19 30-Jun-19
FINISH KONTRUKSI
TPSS CAWANG
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
TPSS CILILITAN
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
TPSS TAMAN MINI FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
STATION TAMAN MINI
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
TPSS KP RAMBUTAN
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
STATION KP RAMBUTAN
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
TPSS CIRACAS 1
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
STATION CIRACAS
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
TPSS CIRACAS 2
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
TPSS HARJAMUKTI
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
STATION HARJAMUKTI
FINISH P.A.T FINISH S.I.T FINISH S.A.T

EPCC LRT JABODEBEK POWER SUPPLY SYSTEM | EPC DEPARTMENT | APRIL 2019
DISTRUBTION LINE 1

NO LOCATION DISTRUBTION

- Turn out Cawang belum ready by civil


1 TPSS CAWANG - Longspan Cililitan belum tersambung dengan
Ushape, & tray dari railway belum terinstal
- Pekerjaan glanding cable ke dalam panel berada
2 TPSS CILILITAN
di confined space area
3 TPSS TMII - Turn out TMII belum ready by civil
- Longspan JORR cable tray belum terinstal
4 TPSS KP RAMBUTAN
- Turn out Kp Rambutan belum ready by civil
5 TPSS CIRACAS 1 - Turn out Ciracas belum ready by civil
6 TPSS CIRACAS 2 -
7 TPSS HARJAMUKTI -
- 2 Ruangan belum ada dinding kareana berada di
8 STATION LINE 1
sisi end wall station

EPCC LRT JABODEBEK POWER SUPPLY SYSTEM | EPC DEPARTMENT | APRIL 2019
TIMELINE SERVICE LINE 3
DESCRIPTION / DATE 30-Apr-19 31-May-19 30-Jun-19 31-Jul-19 31-Aug-19 30-Sep-19 31-Oct-19
FINISH KONTRUKSI
TPSS HALIM
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
TPSS HALIM 2
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
TPSS JATIWARINGIN FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
TPSS JATIBENING BARU
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
STATION JATIBENING BARU
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
TPSS CIKUNIR 1
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
STATION CIKUNIR 1
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
TPSS CIKUNIR 2
FINISH P.A.T FINISH S.I.T FINISH S.A.T

HANDOVER AREA FINISH KONTRUKSI


DSS CIKUNIR 2
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
TPSS BEKASI BARAT
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
STATION BEKASI BARAT
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
TPSS BEKASI
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
TPSS JATIMULYA
FINISH P.A.T FINISH S.I.T FINISH S.A.T

FINISH KONTRUKSI
STATION JATIMULYA
FINISH P.A.T FINISH S.I.T FINISH S.A.T

DESCRIPTION / DATE 31-Jul-20 30-Sep-20 31-Oct-20 30-Nov-20 31-Dec-20 31-Jan-21 28-Feb-21

HANDOVER AREA FINISH KONTRUKSI


DSS OCC
FINISH P.A.T FINISH S.I.T FINISH S.A.T
HANDOVER AREA FINISH KONTRUKSI
TPSS DEPO
FINISH P.A.T FINISH S.I.T FINISH S.A.T

* Note : target handover base on forecast EPC Team

EPCC LRT JABODEBEK POWER SUPPLY SYSTEM | EPC DEPARTMENT | APRIL 2019
TIMELINE SERVICE LINE 2

DESCRIPTION / DATE 30-Sep-19 31-Oct-19 30-Nov-19 31-Dec-19 31-Jan-20 28-Feb-20


HANDOVER AREA FINISH KONTRUKSI
DSS CAWANG
FINISH P.A.T FINISH S.I.T FINISH S.A.T

HANDO FINISH KONTRUKSI


TPSS CIKOKO
FINISH P.A.T FINISH S.I.T FINISH S.A.T

HANDO FINISH KONTRUKSI


DSS CIKOKO 2
FINISH P.A.T FINISH S.I.T FINISH S.A.T

HANDOVER AREA FINISH KONTRUKSI


TPSS PANCORAN
FINISH P.A.T FINISH S.I.T FINISH S.A.T
HANDOVER AREA FINISH KONTRUKSI
TPSS KUNINGAN
FINISH P.A.T FINISH S.I.T FINISH S.A.T

HANDO FINISH KONTRUKSI


DSS RASUNA SAID
FINISH P.A.T FINISH S.I.T FINISH S.A.T

HANDO FINISH KONTRUKSI


TPSS SETIABUDI
FINISH P.A.T FINISH S.I.T FINISH S.A.T

DESCRIPTION / DATE 31-May-20 30-Jun-20 31-Jul-20 31-Aug-20 30-Sep-20 31-Oct-20


HANDOVER AREA FINISH KONTRUKSI
TPSS DUKUH ATAS
FINISH P.A.T FINISH S.I.T FINISH S.A.T

* Note : target handover base on MOM/ENG/LRT/INTERFACE/IV/2019 02 April 2019

EPCC LRT JABODEBEK POWER SUPPLY SYSTEM | EPC DEPARTMENT | APRIL 2019
Mengirimkan
Bertambahnyasurat perpanjangan
biaya umum Proyekkontrak kepada
sampai Employer
dengan Februari 2020
untuk penambahan waktu pelaksanaan sampai 28 Februari
sebesar Rp. 18.000.000.000, & biaya klaim Sub-Contractor
2020
Wifgasindo sampai dengan Februari 2020 sebesar Rp. 10.800.000.000

EPCC LRT JABODEBEK POWER SUPPLY SYSTEM | EPC DEPARTMENT | APRIL 2019