TPSS KP RAMBUTAN
TPSS HARJAMUKTI
TPSS CIRACAS 1
TPSS CIRACAS 2
TPSS CAWANG
TPSS CILILITAN
TPSS TMII
U-SHAPE
long span 1
long span 2
turn out 1
turn out 2
turn out 3
turn out 4
turn out 5
turn out 6
Note:
1. TPSS 2. Cable
= Finish pekerjaan internal TPSS / Station A = Cable sudah di pulling
= Sedang berlangsung pekerjaan internal TPSS / Station B = Cable belum dipulling
= MV Cable
= LV, & Control Cable
= DC Cable to 3rd Rail
EPCC LRT JABODEBEK POWER SUPPLY SYSTEM | EPC DEPARTMENT | APRIL 2019
TIMELINE SERVICE LINE 1
DESCRIPTION / DATE 15-Apr-19 30-Apr-19 15-May-19 31-May-19 15-Jun-19 30-Jun-19
FINISH KONTRUKSI
TPSS CAWANG
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
TPSS CILILITAN
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
TPSS TAMAN MINI FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
STATION TAMAN MINI
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
TPSS KP RAMBUTAN
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
STATION KP RAMBUTAN
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
TPSS CIRACAS 1
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
STATION CIRACAS
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
TPSS CIRACAS 2
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
TPSS HARJAMUKTI
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
STATION HARJAMUKTI
FINISH P.A.T FINISH S.I.T FINISH S.A.T
EPCC LRT JABODEBEK POWER SUPPLY SYSTEM | EPC DEPARTMENT | APRIL 2019
DISTRUBTION LINE 1
NO LOCATION DISTRUBTION
EPCC LRT JABODEBEK POWER SUPPLY SYSTEM | EPC DEPARTMENT | APRIL 2019
TIMELINE SERVICE LINE 3
DESCRIPTION / DATE 30-Apr-19 31-May-19 30-Jun-19 31-Jul-19 31-Aug-19 30-Sep-19 31-Oct-19
FINISH KONTRUKSI
TPSS HALIM
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
TPSS HALIM 2
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
TPSS JATIWARINGIN FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
TPSS JATIBENING BARU
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
STATION JATIBENING BARU
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
TPSS CIKUNIR 1
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
STATION CIKUNIR 1
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
TPSS CIKUNIR 2
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
TPSS BEKASI BARAT
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
STATION BEKASI BARAT
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
TPSS BEKASI
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
TPSS JATIMULYA
FINISH P.A.T FINISH S.I.T FINISH S.A.T
FINISH KONTRUKSI
STATION JATIMULYA
FINISH P.A.T FINISH S.I.T FINISH S.A.T
EPCC LRT JABODEBEK POWER SUPPLY SYSTEM | EPC DEPARTMENT | APRIL 2019
TIMELINE SERVICE LINE 2
EPCC LRT JABODEBEK POWER SUPPLY SYSTEM | EPC DEPARTMENT | APRIL 2019
Mengirimkan
Bertambahnyasurat perpanjangan
biaya umum Proyekkontrak kepada
sampai Employer
dengan Februari 2020
untuk penambahan waktu pelaksanaan sampai 28 Februari
sebesar Rp. 18.000.000.000, & biaya klaim Sub-Contractor
2020
Wifgasindo sampai dengan Februari 2020 sebesar Rp. 10.800.000.000
EPCC LRT JABODEBEK POWER SUPPLY SYSTEM | EPC DEPARTMENT | APRIL 2019