Beruflich Dokumente
Kultur Dokumente
♦ The kiln feed system should be run in a recirculation operation and calibrated
♦ Test run the dust evacuation system including elevators, screws, pumps etc.
♦ Test run all cooler drives and inspect for tracks after running. Continue to run the
system for at least 12 hours to ensure its mechanical integrity.
♦ The following equipment should also be run and checked: Clinker Roll crusher,
Vent Fan, Cooler Fans, and all downstream clinker handling equipment.
(I.e.: drag conveyors, belts, pan conveyors, gates etc.) Ensure that fan dampers or
variable speed motors can operate at full range.
♦ Ensure the calibration of all pressure and flow transmitters for the cooler fans.
♦ Test run the I.D. fan and test for proper rotation, controls from the field and
CCR/DCS as well as check for leaks.
1.4. Coal Conveying system
♦ Test run of coal conveying system should be taken Viz: calibration of Rotoscale
to be done
1.6. Pre-heater System (These items to be done well before start up)
♦ Verify all hoses and connections are in place for the fuel and air supply systems
♦ All compressed air line valves in their proper positions for operation
♦ Test run burner axial, swirl and transport air systems and check filters
♦ Verify all Cyclone Flap chutes are clear by dropping mill ball/fire ball through
cyclone and chutes
♦ Verify all Cyclone tipping valves are working properly. Open and close manually.
♦ Ensure the proper direction or rotation of all fans, screws, conveyors, clinker Roll
crushers. Auxiliary kiln drive motor function
♦ The proper installation of refractory cannot be over emphasized as it plays a key role
in the longevity of the lining. During a major turnaround it would be well for plants to
consider hiring an experienced refractory installation specialist to supervise the
ongoing lining replacement or ensure that the installer is familiar with the various
installation techniques that are available.
It is essential that plants have a preheating schedule determined prior to the start up. The
start-up program, which mainly determines the kiln temperature increase per unit time
and the timing of the introduction of raw feed, must consider a number of factors such
as the type of refractory material, design of the kiln system, mechanical systems etc.
The following points should be recorded during the preheating of pyro- system
2.1.1. Preheater/Precalciner
The purpose of a turning schedule is to ensure slow, uniform heating of the kiln and its
refractories. Turning schedules are based on an increase in temperature over time. A
good turning schedule will allow for the expansion of the refractory and kiln shell so that
the brick remain in place and the shell expands uniformly along its longitudinal axis.
As a compromise, the kiln should be periodically turned i.e.: rotated a fraction of a turn,
During the initial phase until the sintering zone temperature reaches approximately
900°C (1650 °F). After this phase, the kiln can be rotated continuously in a normal
manner through the auxiliary drive.
2.3. Kiln Preheat Schedule
The following is a guideline for preheating Kiln refractory brick linings after
900
x START OF MATERIAL FEED ACCORDING TO
Kiln gas temperature at inlet area
800
x KILN TYPE AND OPERATING PROCESS
1200*
700
600
900*
500
400
600*
300
200
300* 100
0
0 3 6 9 12 15 18 21 24 27 30 33 36 39 42
Note:* If the kiln hood becomes smoky and the flame loose then increase the draft
slightly. If the flame moves away from the burner tip it might be too much draft or too
much primary air. Change one of them and see what happens.
7. Start Clinker transport System. Cooler ESP transport System, Bull Nose Cooling fan,
cooling fans of Roll crusher, Roll crusher, Cooling Fan recuperation zone (1-6fans)
8. Start Cooler ID fan and maintain hood draft around -5 mmwg.
9. Start remaining cooler fans with min. speed
10 Start Cooler drive at 1 spm speed. (maintain minimum chamber pressure)
11 Put PID loop in auto mode at set point of -5 mmwg and adjust Cooler ESP fan speed
to maintain the Hood draft.
12 Rotate Kiln continuously after Kiln inlet Temperature reaching 750 ̊C
13 Increase the Fuel in Main Firing burner
14 Maintain Primary air fan pressure at 1400 to 1500 mmwg.
15 After reaching workable temperature at kiln inlet around 1050 ̊ C
16 Change to kiln main drive from Auxiliary drive.
17 Put Kiln Coal ~ 9.0 tph
18 Make Preheater Fan speed 350 rpm and open PH Fan damper 100%.
19 Cooler Fans 1 ~1 100 rpm, 2 -3~ 1000 rpm, rest at 900 rpm.
20 Make Kiln Coal ~ 12 t/h
21 After PH Fan inlet pressure reaching above 100 mmwg, start kiln feed at 140t/h.
22 Start Calciner firing at 2.0 tph coal and increase to maintain around 860-870 ̊C at
Cyclone 1th Gas temperature.
23 Open tertiary air damper to 30 % (Adjust based on kiln inlet & P/H Exit Oxygen
content).
24 Increase the main drive speed to 0.7 rpm. Based on kiln conditions.
25 Start Cooler ESP High tension and rapping.
26 Increase Cooler fan’s speed gradually as the Clinker bed starts increasing over the
cooler grates.
27 Maintain Compartment 2 Chamber pressure around 550 mmwg
28 Increase Kiln Speed, Feed, fuel and Fan Flows based on the Pyro system conditions.
29. For Kiln inlet firing system Pre conditions: kiln inlet analyzer to be ready, kiln inlet
Temperature to be below 1200 ̊C and kiln inlet maintain o2 2- 3 %.
POLFLAME
• Normal operation
For normal nominal operation with a coal supply rate of approx. 21- 25 tph following
Swirl: 20°
Divergence: 5°
Primary air flow rate: approx. 8500-9000 Nm3/h (pressure indication 250– 300 mbar)
The above initial settings result in the following operating figure. Primary air rate
approx.12% related to the total primary air Primary air ratio approx. 7.5% related to the
nozzle air .Specific axial moment of approx. 7 N/MW, calculated with nozzle air, cooling air
and conveying air and coal Specific axial moment of approx. 5 N/MW, calculated with
nozzle air Swirl factor approx. 0.23
For further optimization of Poly track cooler please do refer Poly track manual.
a). Make sure the emergency generator starts up The generator will normally start up
automatically and
Supply power for emergency panel.
b). Start the emergency compressor. This will supply compressed air for the spray lubrication
c). Start kiln auxiliary and kiln barring. In order to be able to the start the kiln auxiliary
group.....
d). A power failure will stop the primary air fan. A stop of the primary air fan will
automatically start the emergency air fan for cooling of the burner pipe.
The following items concerning the kiln sustem are operational on emergency
power.
Kiln feed t/h 473 142 179 215 252 289 326 362 399 436 473
Clinker production t/24 h 7000 2100 2650 3190 3730 4280 4830 5360 5910 6460 7000
% 100 30,0% 37,8% 45,6% 53,3% 61,1% 68,9% 76,7% 84,4% 92,2% 100,0
Desig Fan
n s
3 3
fan 1 m /h m /h mb
84500 100 63270 64220 65170 66120 67070 68020 68970 69920 70870 71830
3
fan 2 m /h 78000 100 55850 57010 58170 59330 60490 61650 62810 63970 65130 66300
3
fan 3 m /h 74000 95 50560 51930 53300 54670 56040 57410 58780 60150 61520 62900
3
fan 4 m /h 70500 90 45870 47430 48990 50550 52110 53670 55230 56790 58350 59930
3
fan 5 m /h 67000 80 41400 43130 44860 46590 48320 50050 51780 53510 55240 56950
3
fan 6 m /h 63500 70 37160 39030 40900 42770 44640 46510 48380 50250 52120 53980
3
fan 7 m /h 60500 65 33430 35430 37430 39430 41430 43430 45430 47430 49430 51430
3
fan 8 m /h 56500 60 29370 31440 33510 35580 37650 39720 41790 43860 45930 48030
3
fan 9 m /h 53000 55 25820 27960 30100 32240 34380 36520 38660 40800 42940 45050
3
fan 10 m /h 95500 50 41840 46210 50580 54950 59320 63690 68060 72430 76800 81180
3
fan 11 m /h 81500 40 30380 34700 39020 43340 47660 51980 56300 60620 64940 69280
3
Total cooling air m /h 784500 45495 47849 50203 52557 54911 57265 59619 619730 643270 66686
3
Spec. Total cooling air m /kg cli. 2,69 5,20 4,33 3,78 3,38 3,08 2,85 2,67 2,52 2,39 2,29
3
Spec. Total cooling air Nm /kg cli. 2,31 4,46 3,72 3,24 2,90 2,64 2,44 2,29 2,16 2,05 1,96
Note: Please note that this is only basic guide lines for start up and doesn’t include start
up of every individual drive in the pyro processing system.