FOR
B1MTBE & EGF EPC PROJECT
REVISION HISTORY
TABLE OF CONTENT
PAGE
1. GENERAL ..................................................................................................................... 5
1.2 Definition........................................................................................................................ 5
3. RESPONSIBILITY ......................................................................................................... 7
4. PROCEDURE .............................................................................................................. 11
6. MEETING .................................................................................................................... 19
7.1 INTENT........................................................................................................................ 19
9. MASTERPIECE ........................................................................................................... 21
1. GENERAL
1.1 Purpose
This procedure describes the general quality control and inspection coordination
activities to be performed by Contractor and Subcontractor with Owner and Indonesian
Government (DEPNAKER) involved at the project site during the construction for
Butene-1 and MTBE Project.
1.2 Definition
CONTRACTOR IKPT
Quality Control All those operations and techniques used to fulfill the
CONSTRUCTION QC PROCEDURE
FOR
B1MTBE & EGF EPC PROJECT
Non Conformance (NC) A deviation report of products and/or process from the
specified requirements
Golden Joint (Tie in) System is not pressure tested after tie-in. Such
welded joint shall be inspected by Radiographic or
other accepted non-destructive examination method.
3. RESPONSIBILITY
3.1 CONTRACTOR
Contractor shall coordinate with the Owner and Subcontractor, and Authority if
applicable, in order to maintain required quality level in the contract. Contractor shall
witness and/or monitor the tests and inspections performed by Subcontractor and
evaluate the results.
3.6 SUBCONTRACTOR
(1) The Subcontractor shall be wholly responsible for performing quality control and
inspection activities to attain the required control of the quality on the project and
shall report its result to Contractor.
(2) To implement the quality control activities smoothly and effectively, the
Subcontractor shall establish QC organization and shall have capable and
sufficient numbers of QC personnel.
(3) The Subcontractor’s quality control activities shall be implemented in accordance
with the contract specified requirements.
Reviewing /
Confirming
documentation
Documentation to Registering Site
Preparing / Site System Verification
Verification Site
Verification
Accepted to
HAND OVER
4. PROCEDURE
4.1 INSPECTION ITEMS
Items subject to Field Inspection shall be as per the "INSPECTION AND TEST
POGRAM (ITP) LIST" in Attachment (1) hereto.
The CONTACTOR ITP shall serve as the guideline into further developing the detailed
requirement of the OWNER based on the CONTRACT and governing project
specifications. CONTRACTOR Quality Control group shall initiate the detailed check as
well as coordination among various departments and disciplines from CONTRACTOR
and OWNER in order to capture the overall project quality requirements.
4.2 WITNESSING
(1) The OWNER and CONTRACTOR respectively reserves the right to witness any
and all the INSPECTIONS that the SUBCONTRACTOR shall carry out pursuant
to this PROCEDURE and/or any other document forming a part of the
CONTRACT.
(2) Where CONTRACTOR or the OWNER elects to witness any of the INSPECTION
categories, the SUBCONTRACTOR shall provide the necessary facilities to
accommodate the request.
CONSTRUCTION QC PROCEDURE
FOR
B1MTBE & EGF EPC PROJECT
(3) Where the OWNER has waived the right to witness, CONTRACTOR shall
witness, then Subclause (4) of this Clause and Subclause (4) in Clause 4.3 shall
prevail. The INSPECTION shall be deemed to have been successfully
completed.
(4) INSPECTIONS subject to Grade "A" classification, where the right to witness has
been waived by the OWNER, CONTRACTOR shall witness. If no comments
have been made by the OWNER after examining the inspection report submitted
by CONTRACTOR, then after 2 days the CONTRACTOR shall be permitted to
proceed with the subsequent work sequence.
(5) Without prejudice to the general principle as per Sub-clause (1) of this Clause,
the Field Inspections hereunder are however categorized into the following three
Inspection Grades "A", "B" and "C". These categories shall be used in
conjunction with the Responsibility Matrix as to the specific roles of each involve
parties as defined in the ITP;
a) Inspection Grade "A"
All INSPECTIONS classified Grade "A" as a default shall require the presence of
the OWNER, or his representative, together with CONTACTOR, to witness and
sign for the inspection stage. This notes that the inspection is of paramount
importance and this may or may not be a Hold point.
If the OWNER’s role is marked as Hold and the OWNER or his representative
and CONTRACTOR did not waive the right to witness, such INSPECTIONS shall
not be carried out without the presence of the OWNER, his representative and/or
CONTRACTOR. Please refer to Clause 6.g for further explanation of Hold point.
b) Inspection Grade "B"
It is mandatory that all INSPECTIONS classified Grade "B", shall require the
presence of CONTRACTOR Inspector to witness and sign. These inspection
items may be subject to random inspection by OWNER.
c) Inspection Grade "C"
All other INSPECTIONS may be classified Grade "C". These shall be carried out
by the SUBCONTRACTOR and shall be subject to random inspection by
OWNER and/or CONTRACTOR.
(6) To further identify the specific responsibility of each party involved in the
inspection work, the following codes based on roles shall be used;
CONSTRUCTION QC PROCEDURE
FOR
B1MTBE & EGF EPC PROJECT
a) I - Inspection
Basically, all “I” or Inspection as defined in Section 1.2 of this procedure, are
to be carried-out by the SUBCONTRACTOR. The inspection also includes
testing and examination that are to be carried-out as part of the procedure to
check and verify the conformity of the completed construction work.
Verification and checks made by Vendor Supervisors or Third Party are also
deemed as Inspection and in this respect are also classified as “I” in the
responsibility matrix.
b) W - Witness
c) RW – Random Witness
d) REV – Review
There are inspection items in the ITP that only requires submission of
documents that pertains to tests performed on materials, specimens or
completed construction works. These are reviewed by either OWNER or
CONTRACTOR based on the criticality of the document involved.
CONSTRUCTION QC PROCEDURE
FOR
B1MTBE & EGF EPC PROJECT
e) APP – Approval
f) T – Test
g) H – Hold
There are certain critical inspection stages that need to be fully witnessed by
Owner. This may vary depending on the extent on their involvement in the
project. For such item that requires mandatory presence of Owner’s
representative, these are designated as “Hold” point to indicate that no
inspection shall proceed without their attendance.
Note: All inspections that are classified as Hold point shall be clearly
understood by all parties. Close communication and sharing of information
shall be adhered so as to avoid any misunderstanding in carrying-out the
related tasks. It is advisable to closely communicate with OWNER regarding
this kind of inspection to avoid delay and cancellation which could then
create impact on the ongoing construction works.
CONSTRUCTION QC PROCEDURE
FOR
B1MTBE & EGF EPC PROJECT
(1) The Inspection Notification from the SUBCONTRACTOR to the OWNER and
CONTRACTOR shall be completed on form "FIELD INSPECTION NOTICE
(FIN)" in Attachment (2) hereto.
(2) The FIN shall be completed by the SUBCONTRACTOR and submitted to the
OWNER and CONTRACTOR within a notice period of not less than one (1)
working day.
(3) Notwithstanding the foregoing, where the presence of the officials of any local
authority is called for, the SUBCONTRACTOR shall be required to submit to the
OWNER and CONTRACTOR the Inspection Notification therefore not later than
ten (7) working days prior to the scheduled inspection date.
(4) The FIN under Sub-clause (1) of this Clause shall include the following
particulars:
a. Inspection item(s).
b. Inspection category, either Grade "A", "B" or "C".
c. Date, time, place and expected or scheduled duration of the
INSPECTION.
d. Requirement as to whether or not the presence of officials of the
concerned local authority (ies) is mandatory.
e. Others to be fore-notified, if any.
(5) The SUBCONTRACTOR may, as notified and scheduled, proceed with and
finish the INSPECTION irrespective of whether or not the OWNER and
CONTRACTOR Field Inspector(s) punctually attend at the time and place of the
INSPECTION, unless such a delay is previously communicated to the
SUBCONTRACTOR by the OWNER and CONTRACTOR, by an appropriate
means and in appropriate time.
CONSTRUCTION QC PROCEDURE
FOR
B1MTBE & EGF EPC PROJECT
(2) The SUBCONTRACTOR shall retain copies of all inspection reports for his own
records.
(3) The originals of all inspection reports, test samples and radiographs shall be
retained by the SUBCONTRACTOR Head of Quality Control until the PLANT is
mechanically complete and accepted by the OWNER. At this juncture all quality
documentation packages shall be handed over to the OWNER.
Note: The hand-over of document to OWNER shall also be discussed and
finalized during the project initial stage.
(4) For the handling of FIR (i.e. Numbering, Filling-up, etc.), please refer to Attachment
(8).
(5) In case there are any comments or Punch list that may be resulting to the
observations made during the inspection, these shall be noted in the FIR and
separately registered for monitoring purpose. Please refer to Attachment (8) for
further explanation and related workflow.
hereto. This will be made available to the OWNER and SUBCONTRACTOR upon
reasonable request, throughout construction of the facility.
(2) A The relative information as to the status of each single INSPECTION, classified
as "A","B" or "C" shall, upon completion, be entered into the computer QUALITY
CONTROL DATA BASE Program (QC Base) from which the Field Inspection
Summary Sheet is generated. Each Inspection report entry shall signify that :-
a. The INSPECTION has been duly performed and the status recorded.
b. The INSPECTION has been duly witnessed by the signatory.
c. The inspection report has been duly submitted to, and received by, the signatory.
(3) A complete print out of the FIELD INSPECTION SUMMARY SHEET will be
submitted to the OWNER and CONTRACTOR as part of the Turn-over package,
upon MECHANICAL COMPLETION of the facility.
(4) When any integral yet independent Unit, Section or System of the project is verified
by the relevant Field Inspection Summary as substantially complete, the
SUBCONTRACTOR shall request for Final Inspection by OWNER and
CONTRACTOR. This is a request that OWNER and CONTRACTOR confirm by
signature that such a Unit, Section or System, thereof is complete, and that the
documents submitted to OWNER and CONTRACTOR are the evidence proving that
every INSPECTION involved in the respective work items, which the TECHNICAL
DOCUMENTS require, have all been duly performed in accordance therewith and
successfully completed.
The OWNER and CONTRACTOR shall perform an overall inspection of the PLANT (or
the PERMANENT WORKS) or any completed Unit upon notification from
CONTRACTOR,
6. MEETING
6.1 PRE-INSPECTION MEETING (PIM)
(1) Following an award of any construction contract, and prior to the start of any
construction or fabrication activity, a PIM shall be held between OWNER,
CONTRACTOR and SUBCONTRACTOR and to be chaired by CONTRACTOR
Head of Quality Control.
(2) The main purpose of this meeting is to orient the individuals about the project’s QC
procedure, quality objectives, anticipated authority requirements, Inspection and
Test Program (ITP), etc. It is important to commence with the construction with
sufficient knowledge of the quality that should become inherent characteristics in all
the completed works.
6.2 QC MEETING
(1) Weekly QC Meeting shall be established between OWNER, CONTRACTOR and
SUBCONTRACTOR at a designated time convenient for all the attendees. The QC
meeting is an important venue in discussing Quality concerns, recent Quality Alerts,
Non Conformities, etc.
(2) During peak time wherein many quality issues are raised and not expeditiously
resolved, the meeting may be held more than once a week between subgroups.
7. QUALITY TRAINING
7.1 INTENT
The intent of the training is to induct or educate inspectors, supervisors, foreman and
others of the following specific quality requirements, but not limited to;
(1) General Project Requirements and Procedures.
(2) Test and Inspection items.
(3) Documentation and Workflows.
(4) Specific working practices such as welding, painting, flange joints bolt tightening
torque control, handling of critical materials and equipment, special alloy steel
materials, etc.
CONSTRUCTION QC PROCEDURE
FOR
B1MTBE & EGF EPC PROJECT
7.2 TRAINER
Training will be carried out by the following person;
(1) CONTRACTOR Field Manager, Construction Manager, Supervisor, Quality Control
Manager
(2) Vendor or Manufacture’s Specialists
(3) OWNER’s Operation or Maintenance Specialists
7.3 TRAINEE
Inspectors, Supervisors, Foremen and others as necessary from CONTRACTOR and
SUBCONTRACTORs shall receive training prior to the start of work or during the
course of construction.
8. SITE AUDIT
The CONTRACTOR Quality Control Manager shall set-up an audit program, establish
set of checklists and perform audit with regards to the implementation of Project
Procedures as well as SUBCONTRACTORs quality system. The audit shall cover the
following minimum points;
• Implementation of related QC Procedures
• Documentation and Control
• Material Management
• Schedule Control and Planning
• Fabrication and Welding Procedures
• Testing and Control Procedures
• Control of Site Testing and Measuring Equipment/Instruments
• Relevant Certification Requirements
• HSE Policies
CONSTRUCTION QC PROCEDURE
FOR
B1MTBE & EGF EPC PROJECT
9. MASTERPIECE
The use of Masterpiece may be implemented especially in areas/locations where
Owner quality expectations are strict and high. Masterpiece is an effective tool in
graphically showing the level of quality that is required to be achieved consistently by
Contractor/workers at a given stage of construction works.
Masterpiece is a sample of completed work for a related construction activity and can
be prepared in two options as explained below;
Should a particular project decide to implement the Masterpiece concept, the following
steps can be used as a simple guideline;
• Establish Masterpiece Plan and List
• Prepare Masterpiece (First work of Contractor)
CONSTRUCTION QC PROCEDURE
FOR
B1MTBE & EGF EPC PROJECT
• Quality Slogan – Selection of Quality Slogan that will be used as the theme for the
month. The slogan will be selected from submitted entries from
SUBCONTRACTORs. The slogan shall be posted on site bulletins boards, site
office and construction keys areas.
an obstacle into completing the construction work on schedule. The following tools can
be used to support the Quality objectives of the project in controlling, monitoring and
quantifying various areas of quality function in a systematic manner;
of weld through the NDT reports as well as the resulting trend that can be generated
from the WCS database. The following figures can be used in judging Welders’
performance;
RT Repair Rate (Joint Base): 5%
RT Repair Rate (Film Base): 3%
13. ATTACHMENT