Beruflich Dokumente
Kultur Dokumente
Plant Equipment
Presented by
S Bhattacharya, K R Bairwa,
P Kukde
The Tata Power Co Ltd, Mumbai
CONTENT
Mechanical Parameters
Vibration of Shaft and pedestal
Bearing metal temperature
Turbine Expansions
Axial shift,
Turbine metal temperature
Functional Parameters
Steam pressures and temperatures
Vacuum
Feed Water Parameters
Limit Values of Operating Parameters
OEM recommendation
Steady state running parameters
Revise limit values based on condition monitoring
This forms the basis for deciding alarm & trip values
Pre-overhaul survey of Main Turbine
Objective
• Ascertain present running behavior
• Identify problem areas
• Planning for high value insurance spares
• Define scope of Quality overhaul
• Planned preparation
• Focused approach to minimize outage duration
• Decision making for future overhauls
Pre-overhaul survey of Main Turbine
Studies to be conducted during Pre-Overhaul Survey
• Running hours
• Reports of all previous overhauls along with the
repairs carried out and spares consumed
• Discussions on Past / present problems
• RLA reports
• Present vibration behavior/scan
• Thermo-scan
• Study of past and present operating data
• Heat balance diagram and reports of periodic
enthalpy drop tests
Pre-overhaul survey of Main Turbine
Example:
High IP exhaust steam temperature in Unit 5
Possible causes:
Steam leak through parting plane.
Inlet steam passing into exhaust directly through
angle seal rings
Steam leakage through angle sealing rings of steam
extractions
Faulty RTD
Pre-overhaul survey of Main Turbine
Analysis and Action Taken:
Machine EOH > 1.5 Lakh hours.
Parting plane fasteners replacement planned.
No history of steam leak through angle seal rings.
During turbine fact finding inspection no sign of
leakage observed. Also clearances were within
design limits.
RTD
Problem identified with data acquisition and transfer.
Pre-overhaul survey of Main Turbine
Strategic decision based on past experience:
Background
LP turbine free standing blade failure occured on running machine,
which lead to catastrophic failure of the machine. Being the first incident
of this nature and our unit being the oldest 500MW unit in India, the
study of blade failure detection was undertaken in collaboration with
BARC, Mumbai.
Observations and analysis:
Blade vibrations were recorded twice, before & after shutdown.
LP Circuit
HP Circuit
NRV
Pump 2 Pump 1
Problem
Internal clearances
Increase in clearances beyond limits Damage to internals
Wear Impeller / Diffuser
Rubbing
Axial float setting
Setting during assembly Pump charecteristics
Pump operating in unstable zone Rotor fault
Interstage leakages Design
Gasket failure Change due to internal damage Measurement error
Looseness
Mechanical Electrical
Possible Causes
Electrical fault
Rotor fault
z Motor of pump #2 swapped with motor of pump #1
Measurement error
z RPM measurements carried out
Operational Problem
- Pump flow variation
No System fluctuation , accumulators found
healthy, and no hunting in governing system.
Possible Causes
Mechanical Problems
- Increase in internal clearances
- Problem with Axial float setting
- Damage to internals
Pump overhauled and performance tested at OEM
facility (partial test with LP stage blocked).
No damage observed on internals, gasket failure or
looseness in the pump
Possible Causes
Mechanical Problems
- Pump characteristics
In-situ pump flow measurements carried out. Flow
hunting observed in HP circuit.
2 39-41 10 – 15 152-192
Pump Characteristics
400
350
300
250
Head(m)
200
150
100
50
0
0 20 40 60 80 100 120 140
Flow
HP Impeller modification
It was observed that the pump operating point is in
unstable zone
Diameter increased by 10 mm to change the pump
hydraulics
Pump behavior after modification
Pump 1 2
Internal clearances
Increase in clearances beyond limits Damage to internals
Wear Impeller / Diffuser
Rubbing
Axial float setting
Setting during assembly Pump charecteristics
Pump operating in unstable zone Rotor fault
Interstage leakages Design
Gasket failure Change due to internal damage Measurement error
Looseness
Mechanical Electrical
THANK YOU