Sie sind auf Seite 1von 183

Optimization of Roadside Drainage Systems: A

Comparative Analysis of Rectangular Lined Ditch and


Underdrain System using RCP

by

Jefferson Bill G. Bisnar


Kierwin S. De Dios
Patricia B. Profitana

In Partial Fulfillment of the Requirements for the Degree


Bachelor of Science in Civil Engineering

Mapua Institute of Technology


September 2014
ACKNOWLEDGEMENT

First and foremost, the group would like to show their gratitude to their thesis adviser, and the

School of Civil, Environmental and Geological Engineering's department coordinator, Engr.

Juan Paulo Nazareno and Engr. Divina Gonzales for the guidance that they have provided during

the duration of the study. During the group's data gathering process, important figures have

provided means for use to be able to come up with sound results. The people who made the

aforementioned feat possible are Engr. Rodolfo Mendoza Jr. from Maynila Water Services Inc.,

Department of Public Works and Highways' information center contact, Ms. Pilori, and NCR's

Regional Director, Reynaldo G. Tagudando. Finally, we would like to thank our parents for their

unending support and God Almighty for the life that He has given us.

ii
TABLE OF CONTENTS

TITLE PAGE

APPROVAL PAGE i

ACKNOWLEDGEMENT ii

TABLE OF CONTENTS iii

LIST OF TABLES iv

LIST OF FIGURES v

ABSTRACT vi

Chapter 1: INTRODUCTION 1

Chapter 2: REVIEW OF LITERATURE 3

Chapter 3: Comparison between Rectangular 13


Lined Ditch and Underdrain System using RCP

Abstact 13

Introduction 13

Methodology 14

Results and Discussion 24

Conclusion 57

References 57

Chapter 4: CONCLUSION 58

Chapter 5: RECOMMENDATION 61

REFERENCES 62

APPENDICES 64

iii
LIST OF TABLES

Table 2.a RIDF of NAIA, Philppines using 17


Improved Sherman Formula
Table 2.b Methodology of Japan using Scaling 18
Method
Table 2.c RIDF of NAIA, Philippines using 18
Log-Normal
Table 2.d RIDF Curve of Philippines using 19
Pearson type III
Table 2.e Rainfall intensity (mm/hr) for 10-min 20
duration by Pearson - III
Table 3.1 Cross-sectional Area and Hydraulic 33
Radius Data
Table 3.2 Cross-sectional Area and Velocity 36
based from Chezy Formula using Bazin's
Constant Data
Table 3.3 Cross-sectional Area and Velocity 39
based from Chezy Formula using Kutter's
Constant data
Table 3.4 Cross-sectional Area and Velocity 42
using Manning's Formula data
Table 3.5 Cross-sectional Area and Velocity 45
using Crimp and Burge's Formula data
Table 3.6 Cross-sectional Area and the 47
respective dimensions data
Table 3.7 Summary of Velocities for 50
Rectangular Lined Ditch
Table 3.8 Summary of Velocities for 51
Underdrain System using RCP
Table 3.9 Cross-sectional Area and Peak 53
Velocity data
Table 3.10 Cost Comparison Data 55

iv
LIST OF FIGURES

Figure 3.1.1 Planning and Designing Chart 24


Figure 3.1.2 Manufacturing/ Materials Source 26
Chart
Figure 3.1.3 Construction Procedure Chart 27
Figure 3.1.4 Time of Construction Chart 29
Figure 3.1.5 Manpower Required Chart 30
Figure 3.1.6 Maintenance Chart 32
Figure 3.2.1 Cross-Sectional Area vs Hyrdaulic 33
Radius
Figure 3.2.2 Cross-Sectional Area vs Velocity 36
Based from Chezy Formula using Bazin's
Constant
Figure 3.2.3 Cross-Sectional Area vs Velocity 39
Based from Chezy Formula using Kutter's
Constant
Figure 3.2.4 Cross-Sectional Area vs Velocity 42
Based from Manning's Formula
Figure 3.2.5 Cross-Sectional Area vs Velocity 45
Based from Crimp and Burge's Formula
Figure 3.2.6 Cross-Sectional Area vs Peak 49
Velocity
Figure 3.2.7 Cost Analysis Comparison 55

v
ABSTRACT
Flooding during the rainy season along roadsides speaks to the inefficiency and inadequacy of
the existing drainage system. In order to become part of the solution, the researchers explored
methods from the engineering field to evaluate Rectangular Lined Ditches and Underdrain
Systems using RCP. The researchers shall dig into various parameters, such as hydrological
concepts, empirical formulas, planning, construction methods, manufacturing and resources, and
costing in order to ascertain a specific type of channel and determine an optimized choice.
Surveys from professionals in the field in both private and public sectors show that ease in
planning, manufacturing, constructing and maintaining a drainage network is really dependent on
the scale of the project. As for the correlation aspect of the research, it appears that the values
vary depending on the cross-sectional area. This also goes for the comparisons done for the cost
aspect of the research. Finally, it must be noted that despite the computations done, the
applicability of a certain type of drainage network remain a significant factor to consider.

Keywords: Correlation, Rectangular Line Ditch, Underdrain Systems

7
Chapter 1

INTRODUCTION

The Philippines and flood waters have always had this longstanding affair. In the past, this

problem was only confined to a limited number of areas but as years passed, it has become a

much bigger problem; one that cannot be ignored anymore. The effects of flooding have

expanded from a simple inconvenience to loss of lives, livelihood, and lifelines. The researchers

would like to take a look at the engineering point of view of the matter and explore other

solutions. This entails determining whether the pipe system and pipe capacity are adequate in

operating efficiently during the wet season considering the fact that recently, rainfall is more

intense and spaced between short periods of time. It also implies comparing different types of

channels, both open and closed. In addition, the researchers would also like to ascertain whether

it can mitigate the amount of inflow to the said drainage system.

The main objective of this research is to contrast two types of drainage system, the

Rectangular Lined Ditch, a type of open channel system, and the Underdrain Systems using

Reinforced Concrete Pipe (RCP), which is a type of closed channel system. The researchers shall

explore three (3) avenues for comparison; cost-related aspects, theoretical aspects, and a

correlation of all important parameters related to designing a certain drainage network, which

shall be expounded in the following chapters.

The resulting comparisons made also aims to determine a better system of drainage

network in order to mitigate, if not alleviate flooding in a cheaper and smarter way.

Furthermore, this study aims to mitigate flooding in order to reduce the damage on

property, inconvenience, loss and endangerment of lives through civil engineering solutions.

8
The significance of this study lies in its technical and social impacts. Since Cavite is seen to

be heavily urbanized in the coming years, providing a sustainable and effective drainage network

is proved to be advantageous. Decreasing the possibility of flooding can cause positive impact on

the lives, livelihood and lifeline of the people residing in a certain area. Transportation and

communication will not be interrupted by the negative effects of flooding. In the long run, flood

mitigation can limit disasters from happening which in turn, can limit damage to property. This

can also serve as a reference on which type of channel to be used when designing and

constructing a drainage system based on various factors and different parameters. Moreover, with

the correlation of the parameters, one can set another variable and be able to use this study for

other places that call and require for a better drainage system.

This study shall only cover comparison between Rectangular Lined Ditch (for open) and

Underdrain Systems using RCP (for closed). The parameters that the researchers will explore

shall cover the ease in planning, the resources to be considered, the construction procedure, time

of completion, manpower required and maintenance. It shall also compare the cost difference

between the two types of channels as well as the applicability of the drainage network. Moreover,

the researchers shall create a correlation graph in which the parameters in designing a drainage

network, such as wetted perimeter, critical discharge and the like. Finally, the researchers shall

only consider the drainage network applicable and suitable for Niog Road, Bacoor City, Cavite.

9
Chapter 2

REVIEW OF RELATED LITERATURE

The Review of Related Literature focuses on the concepts that will be used on this study.

It will tackle important points from Drainage Design, Rainfall Intensity, Storm and Weather

effects that are relevant to the completion of the study. The following points were also supported

with necessary statements from various articles.

2.1 Drainage System Design and its Background

Drainage system is an important aspect of urban and rural systems in all kinds of places.

Drainage system has unprecedented number of uses ranging from collecting sewage to storm

water runoffs. Urbanization is undoubtedly the main reason behind it all. According to Grigg,

Hiller & Riordan (1978), urbanization has a huge impact on the modernization of a specific area

by turning it from a natural and agricultural environment to a residential and commercial

environment. The transition will cause the alteration in the storm water runoff nature of the said

urbanizing watershed that will lead to increased storm water damages such as floods.

Due to excessive change in surroundings, some of the existing sewer and drainages

become left behind. Some of the old drainages may risk contaminating the water supply due to

reasons such as infiltration and excessive inflow. Because of this, the wastewater collection

system might be compromised and there is a need of evaluation whether the existing sewer pipes

are still capable of doing the job that it was designed to do. According to a document from

United States Environmental Protection Agency (2007), there is a need to treat excessive

infiltration and inflow to prevent backups and system overflows as well as challenging peak-flow

treatment at wastewater pants. Another problem that will arise is the deterioration of wastewater

10
collection that will cause infiltration of groundwater and export recharge of groundwater from

watersheds if not taken into focus. Thus, a good combination of well-designed drainages and

impervious roads will be the key in reducing the excessive flood flow during rainy season.

Designing drainage systems considers multiple factors that tackle basic hydrological

aspects with a touch on road factors. It must satisfy criteria such as allowing of minimum

disturbance of the natural drainage pattern and draining of the surface from water in order to

prevent the excessive collection of water which will cause problems such as floods and erosion.

Marsalek & Watt (1984) stated that designing drainage system will be dependent on the location

of the area where the drainage system will be constructed. It is recommended that there be a

study on the region by looking on the respective data such as rainfall data, hydrograph models,

supplemented by specifications of the computational procedure and normal antecedent conditions.

Cimorelli et al. (2013) also implied that optimal design of rural drainage networks must be based

on the coupling of a genetic algorithm with suitable hydrologic and hydraulic models that further

look on the evaluation of water depth and discharge through the network, rainfall-runoff

transformation and flood wave propagation through channels. In the Philippines, there are

multiple regions with varying data regarding rainfall intensities.

In designing and constructing of drainages, the weather aspect must have a great focus.

Since the whole word is undergoing Climate Change, perhaps there is a need to consider

exaggerated weather scenarios in the design of new drainage system. Duchesne & Mailhot,

(2010) reported that the effects of climate changes must be included into the design consideration

of drainage systems. These projections for the design must be provided by the various climate

models with the emphasis that intense rainfall will increase in the near future because of the

acceleration on greenhouse gas concentrations. There is a need to look into the rainfall

11
projections of a certain area and expected level of lifetime and performance of the drainage

system. As stated on Abdellatif, Atherton, Alkhaddar & Osman (2013), it is good to have long-

lasting urban drainage plans for future management of urban drainage system. It is very helpful to

design systems using this kind of approach.

2.2 Weather Effects and Climate Change

Excessive floods can be traced on high volume of rainfall coming from huge storms.

These storms happen due to disturbance in the climate. Since the Philippines is near the Pacific

Ocean, there will always be the possibility that the country will encounter many storms,

especially during the rainy season (June - September). But as of late, the number of storms as

well as their strength is being observed to increase and one can assume climate change is a factor.

As reported by Abdellatif, Atherton, Alkhaddar & Osman (2013), the issue of climate change has

been increasing and its effects have already been observed around the world with further changes

in climate being projected to take place in the future. König, Linde, Mark, & Svensson, (2008)

concluded that the Climate Change may affect the change the precipitation of some countries. In

addition to that, having an extreme summer condition will have a payoff during the rainy season

because there will be an increase in the rainfall events and its intensities. This will be the primary

reason for overflowing sewers that will cause floods in urban areas. According to Berggren

(2008), the sudden changes in the climatic conditions will drastically affect the urban drainage

systems because of the fact that the drainage system is related to the weather phenomenon and

were built for the purpose of coping up with the weather occurring. On the other hand,

Teegavarapu (2012) implied that extreme flood conditions are not necessarily brought by the

short-duration extreme rainfall events. The long-duration rainfall event shall still be held

responsible for extreme flooding events.

12
During the past years the country has been ravaged by various weather phenomena such as

Ondoy in 2009 and two Habagat cases in 2012 and 2013. These phenomena brought massive

rainfall that caused floods all over Metro Manila and neighboring provinces including Cavite.

Analyzing the data from these three weather phenomena, the highest accumulated rainfall ranges

from 550 to 1120 mm of rain in a 3 to 5 day period. These phenomena caused huge problems on

property and lives. The damages were massive especially in Ondoy that caused an 11 billion peso

loss on the country‟s property. Extreme damages to property can also be seen on other countries

that experienced similar weather phenomena in nature just like Hurricane Katrina and Sandy from

the United States. Since Bacoor City is located just outside Metro Manila, it is also subjected to

these damages as it is known it is a flood prone area in the province of Cavite. Damages to

property were mostly caused by floods thus, the flooding must be mitigated via drainage systems.

Habagat 2013
Habagat 2012
Tropical Storm (enhanced by
(enhanced by
Ondoy (Ketsana) Tropical Storm
Typhoon Haikui)
Maring)

Dates Sept 24-27, 2009 Aug 6-8, 2012 Aug 17-21, 2013

556.1 mm of rain 1,007.4 mm of rain 1,120.2 mm of rain

(4-day period) (3-day period) (5-day period)

measured in Science measured in Science measured in Sangley

Garden, Garden, Point, Cavite

13
Highest Measured Quezon City Quezon City

Accumulated Rainfall

934,285 families or
993,227 families or 689,527 families or
4,236,151
4,901,763 persons in 3,096,392 persons in
persons in
2,018 barangays, 2,124 barangays,
2,634 barangays,
172 municipalities, 160 municipalities,
175 municipalities,
16 cities, and 37 cities, and
36 cities, and
26 provinces in 18 provinces in
Affected Population 17 provinces in
12 regions 6 regions
6 regions

Table 1: Data for Tropical Storm Ondoy, Habagat 2012 and Habagat 2013

Source: http://www.rappler.com/newsbreak/39948-by-the-numbers-ondoy-habagat-2012-2013

2.3 Rainfall Intensity and Return Period

Rainfall is one of the main contributors of floods. According to the article form

Environment Solutions (2014), floods are not only the most frequent natural disaster but also the

disaster that produces the greatest economic and humanitarian impact such as number of people

and number of infrastructure affected. Floods are synonymous with the amount of rainfall on a

specific area. Meaning, the larger the rainfall on an area, the higher the tendency of extreme

floods. Blendermann (1979) stated that before designing the storm-water drainage or control

system it is required to consider the nature of the incoming rainfall on the chosen area of interest.

This data is called the Rainfall Intensity. Rainfall Intensity refers to the measurement of the

14
amount of rain that falls over time. The intensity of rain is measured in the height of the water

layer covering the ground in a period of time thus it implies that if the rain stays where it falls, it

would form a layer of a certain height. Usually every country has the means to measure the

rainfall intensity of a specific area. In the case of our country, the PAGASA is the foundation that

provides it. Blendermann also added that, since there are many rainfall intensity data available, it

is challenging on the part of engineers to design the storm-water drainages.

Floods are also described in terms of “return period”. Return Period is commonly known

as an estimate of the likelihood of a natural calamity. Clarke, Hultstrand & Parzybok, (2011)

reported that describing floods in return periods is the more frequent approach in contrast to the

usage of rainfall intensity data. In computing the “return period”, multiple data must be

considered such as pre-existing flood frequency statistics and peak discharge of a flood in a

specific area of location. Sometimes flood frequency statistics is used as an approach into these

kind of situation. But, the main setback of this approach is that it is only applicable in places near

the rivers and streams while the rainfall intensity approach is applicable in every places as long

the data of rainfall intensity is available.

Storm Drainage Hydraulics

Introduction

A storm drainage system is basically composed of the following elements: street inlets,

storm sewers, natural and man-made channels, culverts, detention basins and outlet structures.

These networks are designed to provide a discharge capacity that will be able to carry the design

flow at self-cleaning velocities while protecting the integrity of the drainage elements. However,

15
for storm sewers, calculations regarding the hydraulic grade line, normal and critical depth, total

energy grade line and location of hydraulic jumps, surcharge or out-of-bunk flows.

In the design and analysis of a storm sewer network, one must go about it according to the

fundamental principles of natural movement in open channels, closed conduits and other special

hydraulic structure.

Flow and Classification

Flow in a storm drainage system can be classified in a number of ways:

 Laminar vs. Turbulent

 Steady vs. Unsteady

 Uniform vs. Non-uniform

 Gradually Varied vs. Rapidly Varied

 Open Channel vs. Closed Conduit

Uniform vs. Non-uniform Flow

For uniform flow, the velocity, depth and discharge are constant with distance along the

channel or conduit. Parameters such as channel slope, energy or friction slope and water surface

must all be equal in magnitude. Uniform flow occurs as non-pressure or free surface flow in a

prismatic conduit flowing partially full. It can also occur in a storm sewer flowing full if minor

losses due to contractions, expansions and bends are considered negligible. It is usually applied

over short distances within a gradually varied flow, which includes gutter flow, flow in storm

chains and flood ways.

16
Non-uniform flow, by contrast, is characterized by changing depth and velocity with

distance along the channel or sewer.

Open Channel vs. Closed Conduit Flow

Like that of a natural stream, or man-made channel, open channel flow has a free surface.

The slope of the channel will be classified as hydraulically mild, critical or steep, depending on

whether this slope is less than, equal to or greater than the critical slope computed for the channel

on the basis of its critical depth, discharge and roughness.

A closed conduit, on the other hand, may flow full or partially full. It is dependent on whether the

runoff event is larger or smaller than the design values. Storm sewers, nevertheless, are designed

to flow full or partially full. However, in specific instances, where ground elevations are adequate,

a limited surcharge above the pipe crown may be permitted. Full flow in a conduit is confined

without a free surface and is sometimes referred to as pipe flow or pressure.

Gravity forces still govern, but the additional pressure head of any surcharge above the pipe

crown must be taken into account.

17
CHAPTER 3

COMPARISON OF RECTANGULAR LINED DITCH AND UNDERDRAIN SYSTEM

USING RCP

Abstract

Climate change is becoming more and more apparent due to the frequency of the extreme

weather condition the country has been forced to face. One of the implications of this

phenomenon is the aggravating effect it has: flooding. The country has seen strong storms such

as Ondoy, Habagat 2012 and Habagat 2013 and has lost many lives and millions of property. In

order to alleviate these circumstances, the researchers shall investigate two kinds of channels,

namely, Rectangular Lined Ditch and Underdrain Systems using Reinforced Concrete Pipe (RCP)

.With hydrology and hydraulics being the main aspect of the study, the researchers shall identify

whether which channel system is more efficient and effective. The study shall also explore and

use different parameters to expand the comparison and to determine which type of drainage

network is suitable and better. The results of this study can be used for future rehabilitation and

improvement purposes as well as disaster prevention planning.

Introduction

In the industry, hydrological studies are often performed in order to evaluate whether a

certain area is prone to flooding because of its implications to property as well as various aspects

of daily living. Since the Philippines is a tropical country, the wet season is unavoidable; hence,

flooding is expected in some parts of the country. This study is more of a comparative one. It

shall inquire on the planning process, resources, construction procedure, time of completion,

manpower required and maintenance of a certain type channel when used in a drainage network.

18
The study shall also cover hydraulic concepts, such as the use of empirical formulas in order to

evaluate the pipe‟s capacity and discharge. Finally, this study will also tackle the different cost

implications when it comes to using either type of channel and social impacts and application.

Methodology

Analytical Framework

Data
Gathering

Analytical Cost
Computat Analysi Survey
ion
s

Rainfal
l
Intensi
ty Analysis Tabulati
of on of
velocity Results
obtained
from RLD

Conclusion

Figure 3.1 Analytical Framework

19
Research Design

This research entitled „Optimization of Roadside Drainage Systems: A Comparative

Analysis of Rectangular Lined Ditch and Underdrain System using RCP‟ will be approached as a

qualitative research that will endeavor to amass data in relation to the economic, theoretical and

technical aspects of drainage systems. The information that shall be gathered will include the

advantages and disadvantages of either a Rectangular Line Ditch or Underdrain System using

RCP. Data shall also include a topographic survey of the area, identifying elevations. Moreover,

hydrological parameters will also be considered in this research and correlated. In addition, the

researchers chose the qualitative approach in order to verify and compare whether which type of

channel is capable of handling a significant amount of storm water and is efficient in transporting

water towards a respective outfall.

This study will make use of a descriptive and exploratory research design because it aims

to accumulate data regarding the current situation where they take in consideration the present

practices used in the industry in planning, constructing and maintaining a drainage system. Also,

it aims to make a comparative analysis and assess the Rectangular Line Ditch and Underdrain

System using RCP in terms of adequacy and its efficiency of as well as its efficiency during the

typhoon season and extreme weather conditions with heavy rainfall and storms with long

duration. Finally, the researchers shall make use of the recent data for unit cost in constructing a

20
specific type of drainage network and work with the differentiation and interpretation of that data.

Figure 3.1.a. Rectangular Line Ditch

Figure 3.1.b. Underdrain Pipe Using RCP

21
Data Collection

The comparative analysis between open channel and pipes will use different hydrological

factors and site parameters. Hydraulic factors of the channel such as discharge, channel type, type

of flow breadth of surface of water, depth of channel, and energy gradient will take part in this

study. The cost and efficiency of these two types of channels will also be assessed for further

comparison. Other parameters such as the ease of planning, the availability of resources, the

construction procedure, time of completion, manpower required and maintenance shall also play a

pivotal role in the assessment of which type of channel for a drainage system is better and more

advantageous.

In order to gather information, the researchers shall avail of the services and data provided

by the Department of Public Works and Highways (DPWH) for the cost estimates as well as the

information about various procedures for planning and construction. A survey was made in order

to gather firsthand information to be used in this study from both the public and private sector.

Data and services from National Mapping and Resource Information Authority (NAMRIA) such

as maps were also used in this study.

The researchers gathered the data of analyses of Philippine rainfall intensity duration

frequency with respect to different methodology of different countries such as methodology

People‟s Republic of China, Japan, Republic of Korea, Philippines and Vietnam through

UNESCO. The participating countries provided their country‟s rainfall data to the study done by

UNESCO. The group considered three return periods, specifically two year, five year and, 10 year

return period.

22
China preferred the method of Improved Sherman Formula for calculating rainfall

intensity duration data. The Philippines provided data from eight sites from the country, including

data from NAIA, Philippines. This data was considered for it is the nearest to Bacoor, Cavite. The

considered “p” were 0.5, 0.2, and 0.1 for two year, five year, and 10 year-return period. There was

a sudden change in the slope at T=180 min, thus there are 2 scaling method with the given data.

Table 2.a. RIDF of NAIA, Philppines using Improved Sherman Formula

23
In the case of Japan, one of the methods they use for analyzing the RIDF of Philippines Is

scaling method. This is the only setback in this data is that the data used for Philippines is from

Puerto because it is the nearest site from Bacoor, Cavite.

Table 2.b. Methodology of Japan using Scaling Method

The methodology of Republic of Korea for the rainfall data of Philippines is Log-Normal.

Table 2.c. RIDF of NAIA, Philippines using Log-Normal

24
Table 2.d. RIDF Curve of Philippines using Pearson type III

25
Table 2.e. Rainfall intensity (mm/hr) for 10-min duration by Pearson – III.

26
27
Rainfall Intensity of 10 year Return
Period
Vietnam- Log-Pearson III
Vietnam-Pearson III
Republic of Korea
Japan
People’s Republic of China

0 50 100 150 200 250 300


People’s
Republic of Vietnam- Vietnam- Log-
Republic of Japan
Korea Pearson III Pearson III
China
10 min 130.94 167.92 252.93 227.7 229
30 min 140 84.07 134.62 148.4 144.8
60 min 98 54.329 90.43 98.1 107.7

Rainfall Intensity of 2 Year Return Period


Vietnam- Log-Pearson III
Vietnam-Pearson III
Philippines
Republic of Korea
Japan
People’s Republic of China

0 20 40 60 80 100 120 140 160 180


People’s Vietnam-
Republic of Vietnam-
Republic of Japan Philippines Log-Pearson
Korea Pearson III
China III
10 min 135 104.22 168.87 60 120.3 128.1
30 min 67 52.18 89.88 42 76.9 80.7
60 min 44 33.72 60.38 30 51.8 56.8

28
Rainfall Instensity of 5 year return period
Vietnam- Log-Pearson III

Vietnam-Pearson III

Republic of Korea

Japan

People’s Republic of China

Australia

0 50 100 150 200 250 300


People’s
Republic of Vietnam- Vietnam- Log-
Australia Republic of Japan
Korea Pearson III Pearson III
China
10 min 35.84 190 142.55 252.93 227.7 229
30 min 70.95 110 71.36 134.62 148.4 144.8
60 min 95.83 77 46.12 90.43 98.1 107.7

29
Results and Discussion

Theoretical Aspect

This aspect of the research aims to contrast the Rectangular Lined Ditch and Circular

Underdrain system using RCP (Reinforced Concrete Pipes). This comparison observes multiple

aspects such as Planning, Manufacturing/Resources, Construction Procedure, Time of

Construction, Manpower required and Maintenance.

The researchers conducted a survey with a questionnaire concentrating on the six

parameters that were stated earlier. There were a set of questions for each of the parameter in

which there is a main question whose results were illustrated on the pie charts that will be shown

on the later parts. The other questions served as supporting components needed in order to

support the result shown by the main questions. Please see the appendix for the content of the

questionnaire.

Table 2: Questionnaire Results

Results

S1 S2 S3 S4 S5 S6 S7 S8 S9 S10

1 a a a a A a a b b b

2 b a a a A others a b b b

3 a b b b A others a b b b

4 a b b b A others b b b b

5 b a b b A b b b b b

30
6 a b a a A a a b b a

7 a a a a A a a a a a

and a and a and

8 c c c c NA a c c c a

9 a a a a A a a b a b

II

a and

1 a a b a A a b a a a

2 b b b b B b a b b b

3 a b b a A a a b NA b

III

General

1 a a b a A a a b b b

2 a b a others NA others a a a a

3 NA NA b b A b b a a a

4 c c c c C c c c c c

5 b b b b A b b b b b

6 b b b b B b b b b b

RLD

7 c c a c C c others a a a

8 a a,b c,d b,a a,b b,a b,a a,b a,b a,b,c

9 b b b a A b a c c c

31
10 b b a b A b b b b b

UDS

11 e e,f,g e,f,g e,f NA e,f,g others c,d,e c,d,e c,d,e

12 a a b b A a others b b a

13 c a NA a NA others others a a a

14 b,a a,b c,d b,a a,b a,b a,b a,b b,c a,b

15 a b b a A b a c c c

16 b b b b A b b b b b

IV

1 a b NA others NA c c c c b

2 a a a a A a a a a a

3 NA NA NA NA others others a,b,c d,c,b NA a,b,c

4 NA NA NA NA NA others c,d,e d,c,b NA a,b,c

1 a a b a A others b b b b

2 b b b b A b b b b b

3 others NA NA a,b NA others NA b,c,d NA b,c,d

VI

1 a a a a A a a b a a

2 a a b a A a a b b a

3 a b b b A b NA a b b

4 a NA a b A b a b b b

32
This is the result of the questionnaire from the survey that the group conducted. It shows

the breakdown of answers from each of the sample. The results were divided into six parts

represented by the Roman numeral and the answers that can be found include; a, b, c and

others/NA. The rows colored with green represents the main questions that were interpreted in the

pie charts while the rows colored with yellow represents the questions whose answers involved

ranking of the choices.

Table 3: Summary of the Questionnaire Results

Summary

I a b c Others/NA

1 7 3

2 5 4 1

3 3 6 1

4 2 7 1

5 2 8

6 7 3

7 10

8 5 4 1

9 8 2

II

1 9 1

2 1 9

3 5 4 1

33
III

General

1 6 4

2 6 1 3

3 4 4 2

4 10

5 1 9

6 10

RLD

7 4 5 1

8 a,b

9 3 4 3

10 2 8

UDS

11 e,f,g

12 5 4 1

13 5 1 4

14 a,b,c

15 4 3 3

16 1 9

IV

1 1 2 4 3

2 10

34
3 a,b,c 7

4 c,d 7

1 4 5 1

2 1 9

3 b,c,d 7

VI

1 9 1

2 7 3

3 3 6 1

4 4 5 1

This table shows the summary of the results of the survey. For the respective numbers, the

table shows a tally of the results based on the choices available. The choices include a, b, c and

others/NA. The row with a green colored numbering represents the row whose results were

represented by a pie chart. The blue colored portions represents the highest results of the choices

while the yellow colored portions represents the summary of results for questions whose answers

involved a ranking.

Planning Aspect

The following chart shows the comparison of Rectangular Lined Ditch and Underdrain

Systems using RCP in terms of Planning/Designing Aspect particularly the system which is easier

to design;

35
Planning/Designing

30%

Rectangular Lined Ditch


Underdrain System using RCP

70%

Figure 1: Planning/Designing Chart

Ten engineers responded on the survey that the group conducted. Based on the results,

70% of the respondents answered that Rectangular Lined Ditch is easier to design compared to

the 30% that answered Underdrain Systems. The answers came by considering various aspects

such as runoff capacity and cross-sectional area.

In terms of Planning Aspect, the Open Channel Ditches in general are the easiest to design

because of the simplicity of it. Since Rectangular Lined Ditch falls in this category, it is

considered that it is easy to plan and design which only involves dimension. In addition to that,

Rectangular Lined Ditch offers a large volume of intake which is a contributor on the designing

process.

On the other hand, the Underdrain Systems are harder to design. The Underdrain system

usually uses RCP or Reinforced Concrete Pipes in which its dimensions are considered in

36
designing of the system. Also, additional data such as elevation and slope are needed to consider.

Aside from the dimensions, there is also a need of designing the Inlets, Catch Basins, Cross Drain

Systems involved. Basically, the designing process involves the design of the dimensions and

other appurtenances or the whole pipe system in general. According to the data acquired,

Underdrain Systems are the good choice for urban setting.

When designing Drainage Systems, aside from AutoCAD, most of the agencies use

program such as HECRAS, Civil 3D and SewerCAD. According to them, they conduct seminars

in the field of design. For designing, the common practice, involves inspection of the site for data

gathering of dimensions and field conditions.

Materials/Resources

The following chart shows the comparison of Rectangular Lined Ditch and Underdrain

Systems using RCP in terms of the simplicity of materials used for constructing the system;

Manufacturing/Materials

13%

Rectangular Lined Ditch


48% Underdrain System using RCP
Other/No Anwer
39%

37
Figure 2: Manufacturing/Materials Source chart

Ten engineers responded on the survey that the group conducted. Based on the results,

48% of the respondents answered that Rectangular Lined Ditch has simpler materials, 38% that

answered Underdrain Systems and 14% answered other concept or they cannot answer at all.

Rectangular Lined Ditch is basically an Open Ditch with reinforcement in order to protect

the trench from collapsing during extreme weather conditions. The Rectangular Lined Ditch is

classified into two namely: Concrete Lined Ditch and Masonry Lined Ditch. Basically the whole

system uses a cast-in-place approach meaning the whole components were constructed on site.

Underdrain Systems uses Reinforced Concrete Pipe (RCP) which is pre-cast concrete pipe

that comes in different sizes. Side drains are usually smaller compared to cross drains. Aside from

the pipes, this system needs to complete the remaining parts of the system such as catch basins,

covers, manholes and other appurtenances. The appurtenances are usually constructed in site thus,

cast in place.

Construction Procedure

The following chart shows the comparison of Rectangular Lined Ditch and Underdrain

Systems using RCP in terms of the simplicity of the construction procedure used of the system;

38
Construction Procedure

40%
Rectangular Lined Ditch
Underdrain System using RCP
60%

Figure 3: Construction Procedure chart

Ten engineers responded to the survey that the group conducted. Based on the results,

60% of the respondents answered that Rectangular Lined Ditch has simpler construction

procedure compared to the 40% that answered Underdrain Systems.

Rectangular Lined Ditch construction procedure involves the following steps; 1)

Plotting/Staking 2) Road Construction 3) Excavation and Construction of side drains 4)

Strengthening 5) Finishing. It should be noted that the road construction must be executed first

because the drainage elevation will depend on the elevation of the road constructed. In general,

Rectangular Lined Ditches have a simple construction procedure because the formworks are easy

to construct and to shape. According to the results of the survey, the Rectangular Lined Ditch uses

10 mm Ф and 12 mm Ф rebars for reinforcements and Class A concrete mix for concrete.

On the contrary, construction of Underdrain Systems includes the following procedures;

1) Excavate 2) Preparation of gradient and bedding 3) Laying out of pipes 4) Backfill 5)


39
Construction of Appurtenances 6) Finishing. Constructing Underdrain Systems have a complex

procedure because aside of the laying out of pipes there is additional construction work in for the

appurtenances such as catch basins, manhole covers and inlets. According to the results of the

survey, the construction of Underdrain Systems uses RCP of 36, 42 and 48 inch Ф in size. The

results also show that Fine Sand Bedding are usually used as the bedding material and the slope

used ranges from 4% to 8%. The system typically uses 10 mm Ф and 12 mm Ф rebars for

reinforcements and Class A concrete mix for concrete.

Time of Construction

The following chart shows the comparison of Rectangular Lined Ditch and Underdrain

Systems using RCP in terms of the shorter time duration of the construction of the system;

Time of Construction

10%
30% Rectangular Lined Ditch
20%
Underdrain System using RCP
Depending on the dimension
Other/No Answer

40%

Figure 4: Time of Construction chart

40
Ten engineers responded on the survey that the group conducted. Based on the results,

10% of the respondents answered that Rectangular Lined Ditch has shorter construction time,

20% answered Underdrain Systems, 40% of the respondents answered that it depends on the

specifications of the project and lastly, 30% answered other things such as explanation of other

concepts or they cannot answer the question given.

The time of construction depends on the plan or the coverage of the project. At first, the

group assumed that Rectangular Lined Ditch have relatively faster construction time because of

the simplicity of the construction procedure and Underdrain System using RCP has longer

construction time because of the aside from the laying out of pipes, appurtenances are also

constructed. But it doesn‟t seem to be the case. The nature of the project such as the dimensions

plays an impact on determining which of the systems has shorter construction time. In order to

properly and effectively compare the two systems, the dimension of the cross section as well as

length of the drainage system must be given.

Because of this fact, there is no way to determine the exact timeframe of construction of

both systems. The questionnaire originally asked for that kind of data but almost everyone who

answered the survey cannot answer the question citing that the dimension and specifications must

be given first in order for them to give an answer. Majority of the respondents answer summer as

the ideal time for construction because there are no obstacles such as rain which can negatively

impact the construction of the project.

Manpower Required

The following chart shows the comparison of Rectangular Lined Ditch and Underdrain

Systems using RCP in terms of lesser manpower involved in the construction of the system;

41
Manpower Required

13%

39% Rectangular Lined Ditch


Underdrain System using RCP
Other Answers

48%

Figure 5: Manpower required chart

Ten engineers responded on the survey that the group conducted. Based on the results,

38% of the respondents answered that Rectangular Lined Ditch has requires less manpower

required, 48% that answered Underdrain Systems and 14% answered other answers or no answer

at all.

At first glance, the group assumed that Rectangular Lined Ditch uses less manpower and

more equipment because of the fact that ditches can be constructed by excavating trenches. At the

same time, the group assumed that Underdrain Systems uses more manpower because aside from

the laying out of pipes, the construction of appurtenances requires more manpower. But this

assumption is not always the case. Comparing the two systems, Underdrain System uses heavy

equipment in contrast with manpower which is supported with the chart above. Heavy equipment

such as trucks and mobile cranes are used during the construction procedure.

42
The survey originally plans to ask the projected manpower required in order to construct a

specific project. But the samples cannot answer the question citing that the dimensions and the

extent of the project must be determined in order to answer that question.

Maintenance

The following chart shows the comparison of Rectangular Lined Ditch and Underdrain

Systems using RCP in terms of the easier maintenance of the system;

Maintenance

10%

Rectangular Lined Ditch


Underdrain System using RCP

90%

Figure 6: Maintenance chart

Ten engineers responded to the survey that the group conducted. Based on the results,

90% of the respondents answered that Rectangular Lined Ditch is easier to maintain compared to

the 10% that answered Underdrain Systems.

In terms of Maintenance, Rectangular Lined Ditch or Open Channel in general have an

easy maintenance procedure. It involves the removal of the wastes and obstructions by manual

43
means such as the use of shovel of heavy equipment. According to the survey, manual shoveling

is the more commonly used method for maintenance of Rectangular Lined Ditches.

On the other hand, Underdrain Systems or Closed Channel Drains in general are harder to

maintain because it is covered or installed underneath the road. It involves cleaning the systems

through the manholes constructed or using a cleaning apparatus. According to the survey, pump

equipment is the more commonly used method for maintenance of Underdrain System using

RCP.

Analysis of Velocity with the use of different parameters

Comparison of Equivalent Cross-Sectional Area versus Hydraulic Radius

Comparison of Hydraulic Radius


1.2
Hydraulic Radius for
y = 0.0717x + 0.2054 Underdrain System
1
R² = 0.9458
Hydraulic RAdius

0.8
Hydraulic Radius for
0.6 Rectangular Line Ditch
0.4
y = 0.0243x + 0.27 Linear (Hydraulic
0.2 R² = 0.5432 Radius for Underdrain
0 System)
0 5 10 15 Linear (Hydraulic
Equivalent Cross-Sectional Area Radius for Rectangular
Line Ditch)

Figure 1: Cross-Sectional Area versus Hydraulic Radius comparison graph

This graph shows the result of Equivalent Cross-Sectional Area versus Hydraulic Radius. In this

graph, the coefficient of determination is computed and shown. The coefficient of determination or R

squared is a number that is used to indicate how well the data is fit for a statistical model. According to the

graph shown, the Rectangular Lined Ditch shows an R squared of 0.5432 while the Underdrain System

44
shows an R squared of 0.9458. Analyzing the results, the Underdrain System shows a strong correlation

meaning that Hydraulic Radius of the data is highly dependent on the Cross-Sectional Area. On the other

hand, the Rectangular Lined Ditch shows a weak correlation meaning the Hydraulic Radius is not highly

dependent on the Cross-Sectional Area and might be highly dependent on other parameters.

Table 4: Cross-sectional Area and Hydraulic Radius Data

Equivalent Cross- sectional Hydraulic Radius for Hydraulic Radius for Rectangular Line

Area Underdrain System Ditch

0.0314159 0.05 0.029558675

0.070685775 0.075 0.061930556

0.1256636 0.1 0.100424254

0.196349375 0.125 0.140984815

0.2827431 0.15 0.180610407

0.384844775 0.175 0.217464569

0.5026544 0.2 0.250661843

0.636171975 0.225 0.279962888

0.7853975 0.25 0.305507635

0.950330975 0.275 0.327625553

1.1309724 0.3 0.34671721

1.327321775 0.325 0.363187752

45
1.5393791 0.35 0.37741367

1.767144375 0.375 0.389729122

2.0106176 0.4 0.400422908

2.269798775 0.425 0.409740736

2.5446879 0.45 0.417889778

2.835284975 0.475 0.425043886

3.14159 0.5 0.431348669

3.463602975 0.525 0.436926074

3.8013239 0.55 0.44187836

4.154752775 0.575 0.446291455

4.5238896 0.6 0.45023776

4.908734375 0.625 0.453778466

5.3092871 0.65 0.45696546

5.725547775 0.675 0.459842891

6.1575164 0.7 0.462448459

6.605192975 0.725 0.464814467

7.0685775 0.75 0.466968694

7.547669975 0.775 0.468935108

46
8.0424704 0.8 0.470734461

8.552978775 0.825 0.47238478

9.0791951 0.85 0.473901774

9.621119375 0.875 0.475299175

10.1787516 0.9 0.476589024

10.75209178 0.925 0.477781909

11.3411399 0.95 0.478887168

11.94589598 0.975 0.479913057

12.56636 1 0.480866898

This is the data that shows the Hydraulic Radius of the Rectangular Lined Ditch and Underdrain

System using RCP obtained from an equivalent Cross-Sectional Area. It shows that the cross sectional area

came from the pipe diameter which was already given. After obtaining the respective Hydraulic Radius for

the two systems, the group obtained the peak result of the two. Analyzing the results, the cross-sectional

area of 0.125 to 2.010, from 0.4 to 1.6 m Ф respectively, shows that the Rectangular Lined Ditch has a

higher Hydraulic Radius thus, the Rectangular Lined Ditch is the effective system to use when the

Hydraulic Radius is the parameter to be considered. On the other hand, the rest of the cross-sectional area

shows that Underdrain system using RCP have the higher Hydraulic Radius thus, it is the effective system

to use when the Hydraulic Radius is to be considered.

47
Comparison of Equivalent Cross-Sectional Area versus Velocity based from Chezy Formula using

Bazin’s Constant

Comparison of Velocity based from


Chezy Formula using Bazin's Constant

5
Velocity from
4 y = 0.2387x + 1.6265
Underdrain Pipe
R² = 0.864
Velocity

3 Velocity from
y = 0.1018x + 1.8181
2 Rectangular Line Ditch
R² = 0.4627
1 Linear (Velocity from
0 Underdrain Pipe)
0 5 10 15 Linear (Velocity from
Equivalent Cross-sectional Area Rectangular Line Ditch)

Figure 2: Cross-Sectional Area versus Velocity based from Chezy Formula using Bazin’s Constant comparison graph

This graph shows the result of Equivalent Cross-Sectional Area versus Velocity based from Chezy

formula using Bazin‟s constant. In this graph, the coefficient of determination is computed and shown. The

coefficient of determination or R squared is a number that is used to indicate how well the data is fit for a

statistical model. According to the graph shown, the Rectangular Lined Ditch shows an R squared of

0.4627 while the Underdrain System shows an R squared of 0.864. Analyzing the results, the Underdrain

System shows a strong correlation meaning that Hydraulic Radius of the data is highly dependent on the

Cross-sectional Area. On the other hand, the Rectangular Lined Ditch shows a weak correlation meaning

the Velocity is not highly dependent on the Cross-Sectional Area and might be highly dependent on other

parameters.

48
Table 5: Cross-sectional Area and Velocity based from Chezy Formula using Bazin's Constant Data

Equivalent Cross- sectional Velocity from Underdrain Pipe based Velocity from Rectangular

Area from Chezy Formula using Bazin's Line Ditch based from Chezy

Constant Formula using Bazin's

Constant

0.0314159 0.621257797 0.424416663

0.070685775 0.824000506 0.721997226

0.1256636 1.000972311 1.003807183

0.196349375 1.160314797 1.25512968

0.2827431 1.306562138 1.471885003

0.384844775 1.442562572 1.655273191

0.5026544 1.570249784 1.808848975

0.636171975 1.691010413 1.936902022

0.7853975 1.805880231 2.043629708

0.950330975 1.915657834 2.132775116

1.1309724 2.020974761 2.207516875

1.327321775 2.122340923 2.270481735

1.5393791 2.220175226 2.323808057

1.767144375 2.314826911 2.369223484

49
2.0106176 2.40659084 2.408119818

2.269798775 2.495718706 2.441618487

2.5446879 2.582427431 2.470624993

2.835284975 2.666905568 2.495872979

3.14159 2.749318253 2.517959356

3.463602975 2.829811102 2.537372069

3.8013239 2.908513307 2.554511979

4.154752775 2.985540124 2.56971008

4.5238896 3.0609949 2.583241079

4.908734375 3.134970732 2.595334119

5.3092871 3.207551837 2.606181288

5.725547775 3.278814703 2.615944388

6.1575164 3.348829046 2.624760349

6.605192975 3.417658624 2.632745579

7.0685775 3.48536193 2.639999465

7.547669975 3.551992777 2.646607224

8.0424704 3.617600815 2.652642211

8.552978775 3.682231964 2.658167819

50
9.0791951 3.745928796 2.663239029

9.621119375 3.808730872 2.667903702

10.1787516 3.870675027 2.672203636

10.75209178 3.931795631 2.676175458

11.3411399 3.992124811 2.67985136

11.94589598 4.051692655 2.683259725

12.56636 4.110527384 2.686425646

This is the data that shows the Velocities based on Chezy Formula using Bazin‟s constant of the

Rectangular Lined Ditch and Underdrain System using RCP obtained from an equivalent Cross-Sectional

Area. It shows that the cross sectional area came from the pipe diameter. After obtaining the respective

Velocities for the two systems, the group obtained the peak result of the two. Analyzing the results, the

cross-sectional area of 0.125 to 2.010, from 0.4 to 1.6 m Ф respectively, shows that Rectangular Lined

Ditch a higher velocity thus, this system is the effective system to use when the Velocity based on Chezy

Formula using Bazin‟s constant is the parameter to be considered. On the other hand, the rest of the cross-

sectional area shows that Underdrain system using RCP has the higher velocity thus, it is the effective

system to use when the Velocity based on Chezy Formula using Bazin‟s constant is to be considered.

51
Comparison of Equivalent Cross-Sectional Area versus Velocity based from Chezy Formula using

Kutter’s Constant

Comparison of Velocity based from Chezy


Formula using Kutter's Constant
5
4.5 y = 0.257x + 1.523
R² = 0.875
4
3.5 Velocity from Underdrain
y = 0.107x + 1.7327 Pipe
3 R² = 0.4745
Velocity

2.5 Velocity from Rectangular


Line Ditch
2
Linear (Velocity from
1.5
Underdrain Pipe)
1
Linear (Velocity from
0.5 Rectangular Line Ditch)
0
0 5 10 15
Equivalent Cross-sectional Area

Figure 3: Cross-Sectional Area versus Velocity based from Chezy Formula using Kutter’s Constant comparison graph

This graph shows the result of Equivalent Cross-Sectional Area versus Velocity based from Chezy

formula using Kutter‟s constant. In this graph, the coefficient of determination is computed and shown.

The coefficient of determination or R squared is a number that is used to indicate how well the data is fit

for a statistical model. According to the graph shown, the Rectangular Lined Ditch shows an R squared of

0.4745 while the Underdrain System shows an R squared of 0.875. Analyzing the results, the Underdrain

System shows a strong correlation meaning that the Velocity based from Chezy formula using Kutter‟s

constant of the data is highly dependent on the Cross-sectional Area. On the other hand, the Rectangular

Lined Ditch shows a weak correlation meaning that the Velocity based from Chezy formula using Kutter‟s

constant is not highly dependent on the Cross-Sectional Area and might be highly dependent on other

parameters.

52
Table 6: Cross-sectional Area and Velocity based from Chezy Formula using Kutter's Constant data

Equivalent Cross- sectional Velocity from Underdrain Pipe Velocity from Rectangular Line

Area based from Chezy Formula Ditch based from Chezy Formula

using Kutter's Constant using Kutter's Constant

0.0314159 0.519654965 0.340445613

0.070685775 0.711894496 0.61434281

0.1256636 0.884534218 0.88733086

0.196349375 1.04306863 1.138587467

0.2827431 1.190734251 1.35978481

0.384844775 1.329651124 1.549567988

0.5026544 1.461307003 1.710077299

0.636171975 1.586798093 1.844878088

0.7853975 1.706962122 1.957835783

0.950330975 1.822457748 2.052573754

1.1309724 1.933814793 2.132259644

1.327321775 2.041467504 2.199560634

1.5393791 2.145777422 2.256676254

1.767144375 2.247049596 2.305400284

53
2.0106176 2.345544381 2.347188004

2.269798775 2.44148622 2.383218374

2.5446879 2.535070298 2.414447449

2.835284975 2.626467687 2.441652514

3.14159 2.715829365 2.465467786

3.463602975 2.803289412 2.486412926

3.8013239 2.88896757 2.504915694

4.154752775 2.972971327 2.52132989

4.5238896 3.055397619 2.535949569

4.908734375 3.136334242 2.549020319

5.3092871 3.215861026 2.560748235

5.725547775 3.294050818 2.571307084

6.1575164 3.370970319 2.580844043

6.605192975 3.446680794 2.589484321

7.0685775 3.521238672 2.597334895

7.547669975 3.594696076 2.60448754

8.0424704 3.667101265 2.611021298

8.552978775 3.738499035 2.61700451

54
9.0791951 3.808931055 2.622496475

9.621119375 3.878436165 2.62754883

10.1787516 3.947050646 2.632206689

10.75209178 4.014808445 2.636509597

11.3411399 4.081741387 2.640492322

11.94589598 4.147879351 2.644185525

12.56636 4.213250442 2.64761632

This is the data that shows the Velocities based on Chezy Formula using Kutter‟s constant of the

Rectangular Lined Ditch and Underdrain System using RCP obtained from an equivalent Cross-Sectional

Area. It shows that the cross sectional area came from the pipe diameter. After obtaining the respective

Velocities for the two systems, the group obtained the peak result of the two. Analyzing the results, the

cross-sectional area of 0.125 to 2.010, from 0.4 to 1.6 m Ф respectively, shows that Rectangular Lined

Ditch has the higher velocity thus, it is the effective system to use when the Velocity based on Chezy

Formula using Kutter‟s constant is the parameter to be considered. On the other hand, the rest of the cross-

sectional area shows that Underdrain system using RCP has a higher velocity thus, it is the effective

system to use when the Velocity based on Chezy Formula using Kutter‟s constant is to be considered.

Comparison of Equivalent Cross-Sectional Area versus Velocity based from Manning’s Formula

55
Comparison of Velocity based from
Manning's Formula
5

4 Velocity from
y = 0.2568x + 1.4913
R² = 0.8913 Underdrain Pipe using
Velocity

3
Manning's Formula
2 y = 0.1028x + 1.7046
R² = 0.4842 Velocity from
1
Rectangular Ditch
0 using Manning's
0 5 10 15 Formula
Equivalent Cross-sectional Area

Figure 4: Cross-Sectional Area versus Velocity based from Manning’s Formula comparison graph

This graph shows the result of Equivalent Cross-Sectional Area versus Velocity based from

Manning‟s Formula. In this graph, the coefficient of determination is computed and shown. The coefficient

of determination or R squared is a number that is used to indicate how well the data is fit for a statistical

model. According to the graph shown, the Rectangular Lined Ditch shows an R squared of 0.4842 while

the Underdrain System shows an R squared of 0.8913. Analyzing the results, the Underdrain System

shows a strong correlation meaning that Velocity based from Manning‟s Formula of the data is highly

dependent on the Cross-sectional Area. On the other hand, the Rectangular Lined Ditch shows a weak

correlation meaning that the Velocity based from Manning‟s Formula is not highly dependent on the

Cross-Sectional Area and might be highly dependent on other parameters.

Table 7: Cross-sectional Area and Velocity using Manning's Formula data

Equivalent Cross- Velocity from Underdrain Pipe using Velocity from Rectangular Ditch using

sectional Area Manning's Formula Manning's Formula

0.0314159 0.571826061 0.402785584

56
0.070685775 0.749304114 0.659508801

0.1256636 0.907717291 0.910282828

0.196349375 1.053312611 1.141297414

0.2827431 1.189446139 1.346208896

0.384844775 1.318183813 1.523618652

0.5026544 1.440911383 1.674979236

0.636171975 1.558615367 1.803090749

0.7853975 1.672029546 1.91116707

0.950330975 1.781718424 2.002330609

1.1309724 1.888128053 2.079381653

1.327321775 1.99161864 2.144723964

1.5393791 2.092486371 2.200369885

1.767144375 2.190978522 2.247980371

2.0106176 2.287304245 2.288916159

2.269798775 2.381642446 2.324288519

2.5446879 2.474147673 2.355004675

2.835284975 2.564954594 2.381806398

3.14159 2.65418146 2.405301839

57
3.463602975 2.741932824 2.425991362

3.8013239 2.828301701 2.444288309

4.154752775 2.913371304 2.460535617

4.5238896 2.997216458 2.475019083

4.908734375 3.079904757 2.487977968

5.3092871 3.161497525 2.49961348

5.725547775 3.242050611 2.510095584

6.1575164 3.321615066 2.519568477

6.605192975 3.400237709 2.528155017

7.0685775 3.477961611 2.535960311

7.547669975 3.554826508 2.543074641

8.0424704 3.630869164 2.549575851

8.552978775 3.706123672 2.555531309

9.0791951 3.780621724 2.560999525

9.621119375 3.85439285 2.566031492

10.1787516 3.927464619 2.570671794

10.75209178 3.999862819 2.574959539

11.3411399 4.071611621 2.578929134

58
11.94589598 4.142733716 2.582610937

12.56636 4.213250442 2.586031812

This is the data that shows the Velocities based on Manning‟s Formula of the Rectangular Lined

Ditch and Underdrain System using RCP obtained from an equivalent Cross-Sectional Area. It shows that

the cross sectional area came from the pipe diameter. After obtaining the respective Velocities for the two

systems, the group obtained the peak result of the two. Analyzing the results, the cross-sectional area of

0.125 to 2.010, from 0.4 to 1.6 m Ф respectively, shows that Rectangular Lined Ditch has the higher

velocity thus, it is the effective system to use when the Velocity based on Manning‟s Formula is the

parameter to be considered. On the other hand, the rest of the cross-sectional area shows that Underdrain

system using RCP has the higher velocity thus, it is the effective system to use when the Velocity based

Manning‟s Formula is to be considered.

59
Comparison of Equivalent Cross-Sectional Area versus Velocity based from Crimp and

Burge’s Formula

Comparison of Velocity based from


Crimp and Burge's Formula
6
5 y = 0.2787x + 1.6182
R² = 0.8913 Velocity from
4 Underdrain using
Velocity

3 Crimp and Burge's


Formula
2 y = 0.1116x + 1.8497
R² = 0.4842 Velocity from
1 Rectangular Ditch
0 using Crimp and
0 5 10 15 Burge's Formula
Equivalent Cross-sectional Area

Figure 5: Cross-Sectional Area versus Velocity based from Crimp and Burge’s Formula comparison graph

This graph shows the result of Equivalent Cross-Sectional Area versus Velocity based from Crimp

and Burge‟s Formula. In this graph, the coefficient of determination is computed and shown. The

coefficient of determination or R squared is a number that is used to indicate how well the data is fit for a

statistical model. According to the graph shown, the Rectangular Lined Ditch shows an R squared of

0.4842 while the Underdrain System shows an R squared of 0.8913. Analyzing the results, the Underdrain

System shows a strong correlation meaning that the Velocity based from Crimp and Burge‟s Formula of

the data is highly dependent on the Cross-sectional Area. On the other hand, the Rectangular Lined Ditch

shows a weak correlation meaning that the Velocity based from Crimp and Burge‟s Formula is not highly

dependent on the Cross-Sectional Area and might be highly dependent on other parameters.

60
Table 8: Cross-sectional Area and Velocity using Crimp and Burge's Formula data

Equivalent Cross- Velocity from Underdrain using Velocity from Rectangular Ditch using

sectional Area Crimp and Burge's Formula Crimp and Burge's Formula

0.0314159 0.620494177 0.437066666

0.070685775 0.813077388 0.715639595

0.1256636 0.98497311 0.987756999

0.196349375 1.142960047 1.238433237

0.2827431 1.2906799 1.460784735

0.384844775 1.430374437 1.653293835

0.5026544 1.563547351 1.817536719

0.636171975 1.691269121 1.956551802

0.7853975 1.814335981 2.073826499

0.950330975 1.933360479 2.172748967

1.1309724 2.048826632 2.256357826

1.327321775 2.161125303 2.327261421

1.5393791 2.270577886 2.387643366

1.767144375 2.377452704 2.43930598

2.0106176 2.481976709 2.483725813

61
2.269798775 2.584344034 2.522108714

2.5446879 2.684722382 2.555439123

2.835284975 2.78325788 2.584521941

3.14159 2.880078844 2.610017079

3.463602975 2.975298727 2.632467487

3.8013239 3.069018459 2.652321687

4.154752775 3.161328335 2.669951803

4.5238896 3.25230955 2.685667957

4.908734375 3.342035451 2.699729772

5.3092871 3.430572579 2.712355584

5.725547775 3.517981539 2.723729819

6.1575164 3.604317725 2.73400895

6.605192975 3.68963194 2.74332629

7.0685775 3.773970923 2.751795893

7.547669975 3.857377793 2.759515724

8.0424704 3.939892439 2.766570252

8.552978775 4.021551857 2.773032578

9.0791951 4.102390439 2.778966195

62
9.621119375 4.182440226 2.784426432

10.1787516 4.261731133 2.78946167

10.75209178 4.340291144 2.794114345

11.3411399 4.418146486 2.798421792

11.94589598 4.495321782 2.802416954

12.56636 4.571840187 2.806128979

This is the data that shows the Velocities based from Crimp and Burge‟s Formula of the

Rectangular Lined Ditch and Underdrain System using RCP obtained from an equivalent Cross-Sectional

Area. It shows that the cross sectional area came from the pipe diameter. After obtaining the respective

Velocities for the two systems, the group obtained the peak result of the two. Analyzing the results, the

cross-sectional area of 0.125 to 2.010, from 0.4 to 1.6 m Ф respectively, shows that Rectangular Lined

Ditch has the higher velocity thus, it is the effective system to use when the Velocity based from Crimp

and Burge‟s Formula is the parameter to be considered. On the other hand, the rest of the cross-sectional

area shows that Underdrain system using RCP has the higher velocity thus, it is the effective system to use

when the Velocity based from Crimp and Burge‟s Formula is to be considered.

Dimensions of Rectangular Lined Ditch and Underdrain Systems

Table 9: Cross-sectional Area and the respective dimensions data

Equivalent Cross- Diameter for Underdrain Height for Rectangular Lined Ditch (Considering that

sectional Area Pipe base is 1 m constant)

0.0314159 0.2 0.0314159

63
0.070685775 0.3 0.070685775

0.1256636 0.4 0.1256636

0.196349375 0.5 0.196349375

0.2827431 0.6 0.2827431

0.384844775 0.7 0.384844775

0.5026544 0.8 0.5026544

0.636171975 0.9 0.636171975

0.7853975 1 0.7853975

0.950330975 1.1 0.950330975

1.1309724 1.2 1.1309724

1.327321775 1.3 1.327321775

1.5393791 1.4 1.5393791

1.767144375 1.5 1.767144375

2.0106176 1.6 2.0106176

2.269798775 1.7 2.269798775

2.5446879 1.8 2.5446879

2.835284975 1.9 2.835284975

3.14159 2 3.14159

64
3.463602975 2.1 3.463602975

3.8013239 2.2 3.8013239

4.154752775 2.3 4.154752775

4.5238896 2.4 4.5238896

4.908734375 2.5 4.908734375

5.3092871 2.6 5.3092871

5.725547775 2.7 5.725547775

6.1575164 2.8 6.1575164

6.605192975 2.9 6.605192975

7.0685775 3 7.0685775

7.547669975 3.1 7.547669975

8.0424704 3.2 8.0424704

8.552978775 3.3 8.552978775

9.0791951 3.4 9.0791951

9.621119375 3.5 9.621119375

10.1787516 3.6 10.1787516

10.75209178 3.7 10.75209178

11.3411399 3.8 11.3411399

65
11.94589598 3.9 11.94589598

12.56636 4 12.56636

This is the data that shows the respective cross-sectional area along with the respective dimension

for Underdrain System using RCP and Rectangular Lined Ditch. For Underdrain systems, the diameter is

shown while the height is shown for Rectangular Lined Ditch. The diameter of Underdrain system is the

basis for the other data. The diameter given are the usual sizes used in the industry for designing storm

drainages. The Equivalent Cross-sectional Area was obtained from the said diameter list while the Height

of the Rectangular Lined Ditch was obtained from the computed Cross-Sectional Area. The group obtained

the peak dimension between the two sets meaning, the peak dimension must be used in designing the

respective system.

Comparison of Equivalent Cross-Sectional Area versus Velocity based from Crimp and Burge’s

Formula

Comparison of Optimum Velocity

6
y = 0.2781x + 1.6229
5
R² = 0.8923 Peak Velocity of
PEak Velocity

4 Rectangular Line Ditch

3 Peak Veloocity of
Underdrain Pipe
2 y = 0.1112x + 1.8528
Linear (Peak Velocity of
R² = 0.4848
1 Rectangular Line Ditch)

0 Linear (Peak Veloocity of


0 5 10 15 Underdrain Pipe)

Cross-sectional Area

Figure 6: Cross-sectional Area versus Peak Velocity comparison graph

66
This graph shows the result of Equivalent Cross-Sectional Area versus Peak Velocity obtained

from the different methods discussed earlier. The group obtained the peak velocity of Rectangular Lined

Ditch from the given procedure and the same method was done to obtain the Peak Velocity of the

Underdrain System using RCP. The two velocities were compared and then the peak velocity was

obtained. In this graph, the coefficient of determination is computed and shown. The coefficient of

determination or R squared is a number that is used to indicate how well the data is fit for a statistical

model. According to the graph shown, the Rectangular Lined Ditch shows an R squared of 0.4848 while

the Underdrain System shows an R squared of 0.8923. Analyzing the results, the Underdrain System

shows a strong correlation meaning that the Peak of the data is highly dependent on the Cross-sectional

Area. On the other hand, the Rectangular Lined Ditch shows a weak correlation meaning that the Peak

Velocity is not highly dependent on the Cross-Sectional Area and might be highly dependent on other

parameters.

Table 10: Summary of Velocities for Rectangular Lined Ditch

Equivalent Equivalent height Velocity for Velocity for Velocity Velocity from

Cross- for Rectangular Chezy from Chezy from From Crimp and

sectional Line Ditch (base is kutter's Bazin's Manning's Burge's

Area 1m constant) Constant Constant Formula Formula

0.0314159 0.0314159 0.340445613 0.424416663 0.402786 0.437067

0.070685775 0.070685775 0.61434281 0.721997226 0.659509 0.71564

0.1256636 0.1256636 0.88733086 1.003807183 0.910283 0.987757

0.196349375 0.196349375 1.138587467 1.25512968 1.141297 1.238433

0.2827431 0.2827431 1.35978481 1.471885003 1.346209 1.460785

67
0.384844775 0.384844775 1.549567988 1.655273191 1.523619 1.653294

0.5026544 0.5026544 1.710077299 1.808848975 1.674979 1.817537

0.636171975 0.636171975 1.844878088 1.936902022 1.803091 1.956552

0.7853975 0.7853975 1.957835783 2.043629708 1.911167 2.073826

0.950330975 0.950330975 2.052573754 2.132775116 2.002331 2.172749

1.1309724 1.1309724 2.132259644 2.207516875 2.079382 2.256358

1.327321775 1.327321775 2.199560634 2.270481735 2.144724 2.327261

1.5393791 1.5393791 2.256676254 2.323808057 2.20037 2.387643

1.767144375 1.767144375 2.305400284 2.369223484 2.24798 2.439306

2.0106176 2.0106176 2.347188004 2.408119818 2.288916 2.483726

2.269798775 2.269798775 2.383218374 2.441618487 2.324289 2.522109

2.5446879 2.5446879 2.414447449 2.470624993 2.355005 2.555439

2.835284975 2.835284975 2.441652514 2.495872979 2.381806 2.584522

3.14159 3.14159 2.465467786 2.517959356 2.405302 2.610017

3.463602975 3.463602975 2.486412926 2.537372069 2.425991 2.632467

3.8013239 3.8013239 2.504915694 2.554511979 2.444288 2.652322

4.154752775 4.154752775 2.52132989 2.56971008 2.460536 2.669952

4.5238896 4.5238896 2.535949569 2.583241079 2.475019 2.685668

68
4.908734375 4.908734375 2.549020319 2.595334119 2.487978 2.69973

5.3092871 5.3092871 2.560748235 2.606181288 2.499613 2.712356

5.725547775 5.725547775 2.571307084 2.615944388 2.510096 2.72373

6.1575164 6.1575164 2.580844043 2.624760349 2.519568 2.734009

6.605192975 6.605192975 2.589484321 2.632745579 2.528155 2.743326

7.0685775 7.0685775 2.597334895 2.639999465 2.53596 2.751796

7.547669975 7.547669975 2.60448754 2.646607224 2.543075 2.759516

8.0424704 8.0424704 2.611021298 2.652642211 2.549576 2.76657

8.552978775 8.552978775 2.61700451 2.658167819 2.555531 2.773033

9.0791951 9.0791951 2.622496475 2.663239029 2.561 2.778966

9.621119375 9.621119375 2.62754883 2.667903702 2.566031 2.784426

10.1787516 10.1787516 2.632206689 2.672203636 2.570672 2.789462

10.75209178 10.75209178 2.636509597 2.676175458 2.57496 2.794114

11.3411399 11.3411399 2.640492322 2.67985136 2.578929 2.798422

11.94589598 11.94589598 2.644185525 2.683259725 2.582611 2.802417

12.56636 12.56636 2.64761632 2.686425646 2.586032 2.806129

69
Table 11: Summary of Velocities for Underdrain System using RCP

Diamete Velocity for Chezy from Velocity for Chezy Velocity From Velocity from

r (m) kutter's Constant from Bazin's Constant Mannings Crimp and

Bruge's Formula

0.1 0.296515146 0.374536416 0.360227846 0.390886838

0.2 0.519654965 0.621257797 0.571826061 0.620494177

0.3 0.711894496 0.824000506 0.749304114 0.813077388

0.4 0.884534218 1.000972311 0.907717291 0.98497311

0.5 1.04306863 1.160314797 1.053312611 1.142960047

0.6 1.190734251 1.306562138 1.189446139 1.2906799

0.7 1.329651124 1.442562572 1.318183813 1.430374437

0.8 1.461307003 1.570249784 1.440911383 1.563547351

0.9 1.586798093 1.691010413 1.558615367 1.691269121

1 1.706962122 1.805880231 1.672029546 1.814335981

1.1 1.822457748 1.915657834 1.781718424 1.933360479

1.2 1.933814793 2.020974761 1.888128053 2.048826632

1.3 2.041467504 2.122340923 1.99161864 2.161125303

1.4 2.145777422 2.220175226 2.092486371 2.270577886

70
1.5 2.247049596 2.314826911 2.190978522 2.377452704

1.6 2.345544381 2.40659084 2.287304245 2.481976709

1.7 2.44148622 2.495718706 2.381642446 2.584344034

1.8 2.535070298 2.582427431 2.474147673 2.684722382

1.9 2.626467687 2.666905568 2.564954594 2.78325788

2 2.715829365 2.749318253 2.65418146 2.880078844

2.1 2.803289412 2.829811102 2.741932824 2.975298727

2.2 2.88896757 2.908513307 2.828301701 3.069018459

2.3 2.972971327 2.985540124 2.913371304 3.161328335

2.4 3.055397619 3.0609949 2.997216458 3.25230955

2.5 3.136334242 3.134970732 3.079904757 3.342035451

2.6 3.215861026 3.207551837 3.161497525 3.430572579

2.7 3.294050818 3.278814703 3.242050611 3.517981539

2.8 3.370970319 3.348829046 3.321615066 3.604317725

2.9 3.446680794 3.417658624 3.400237709 3.68963194

3 3.521238672 3.48536193 3.477961611 3.773970923

3.1 3.594696076 3.551992777 3.554826508 3.857377793

3.2 3.667101265 3.617600815 3.630869164 3.939892439

71
3.3 3.738499035 3.682231964 3.706123672 4.021551857

3.4 3.808931055 3.745928796 3.780621724 4.102390439

3.5 3.878436165 3.808730872 3.85439285 4.182440226

3.6 3.947050646 3.870675027 3.927464619 4.261731133

3.7 4.014808445 3.931795631 3.999862819 4.340291144

3.8 4.081741387 3.992124811 4.071611621 4.418146486

3.9 4.147879351 4.051692655 4.142733716 4.495321782

4 4.213250442 4.110527384 4.213250442 4.571840187

Table 12: Cross-sectional Area and Peak Velocity data

Peak Velocity of Rectangular Lined

Equivalent Area Ditch Peak Velocity of Underdrain Pipe

0.0314159 0.437066666 0.621257797

0.070685775 0.721997226 0.824000506

0.1256636 1.003807183 1.000972311

0.196349375 1.25512968 1.160314797

0.2827431 1.471885003 1.306562138

0.384844775 1.655273191 1.442562572

0.5026544 1.817536719 1.570249784

0.636171975 1.956551802 1.691269121

0.7853975 2.073826499 1.814335981

72
0.950330975 2.172748967 1.933360479

1.1309724 2.256357826 2.048826632

1.327321775 2.327261421 2.161125303

1.5393791 2.387643366 2.270577886

1.767144375 2.43930598 2.377452704

2.0106176 2.483725813 2.481976709

2.269798775 2.522108714 2.584344034

2.5446879 2.555439123 2.684722382

2.835284975 2.584521941 2.78325788

3.14159 2.610017079 2.880078844

3.463602975 2.632467487 2.975298727

3.8013239 2.652321687 3.069018459

4.154752775 2.669951803 3.161328335

4.5238896 2.685667957 3.25230955

4.908734375 2.699729772 3.342035451

5.3092871 2.712355584 3.430572579

5.725547775 2.723729819 3.517981539

6.1575164 2.73400895 3.604317725

6.605192975 2.74332629 3.68963194

7.0685775 2.751795893 3.773970923

7.547669975 2.759515724 3.857377793

8.0424704 2.766570252 3.939892439

8.552978775 2.773032578 4.021551857

9.0791951 2.778966195 4.102390439

9.621119375 2.784426432 4.182440226

73
10.1787516 2.78946167 4.261731133

10.75209178 2.794114345 4.340291144

11.3411399 2.798421792 4.418146486

11.94589598 2.802416954 4.495321782

12.56636 2.806128979 4.571840187

This table is shows the Peak Velocity of the Rectangular Lined Ditch and Underdrain System

using RCP obtained from the respective Cross-sectional Area. As explained earlier, the Peak Velocity were

obtained using the different methods discussed earlier namely; 1) Chezy Formula using Bazin‟s constant 2)

Chezy Formula using Kutter‟s constant 3) Manning‟s Formula 4) Crimp and Burge‟s Formula. There is a

different set for Rectangular Lined Ditch and there is a different set for Underdrain System using RCP. As

shown in the data, the Equivalent Area value of 0.125 to 2.010 shows that Rectangular Lined Ditch is the

effective system to be used when the peak velocity is to be considered. Meanwhile, the rest of the data

shows that Underdrain System is the best fit when the peak velocity is to be considered.

74
Cost Analysis

This is the component of the study in which the Rectangular Lined Ditch and the Underdrain

System using RCP will be compared with the method of Cost Analysis. The data of Unit Cost

came from the DPWH Bureau of Design NCR Office.

Cost Analysis of Rectangular Line Ditch


and Underdrain Pipe
20000
Direct Cost from differetnt factors

18000 y = 1372.8x + 1199.6


16000 R² = 0.9996
14000 Underdrain Pipe
12000
10000 Rectanguar Iine Ditch
8000
6000 y = 747.78x + 2570.2 Linear (Underdrain Pipe)
4000 R² = 0.9458
2000 Linear (Rectanguar Iine
0 Ditch)
0 5 10 15
Equivalent Cross-sectional Area

Figure 7: Cost Analysis comparison graph

This graph shows the Cost Analysis of Rectangular Lined Ditch and Underdrain System

using RCP by showing the result of the Equivalent Cross-sectional Area versus Direct Cost. In

this graph, the coefficient of determination is computed and shown. The coefficient of

determination or R squared is a number that is used to indicate how well the data is fit for a

statistical model. In order for the R squared to have a “strong” correlation, the value must be

greater than 0.8 while the “weak” correlation shows a value of less than 0.5.

75
According to the graph shown, the Rectangular Lined Ditch shows an R squared of 0.9996

while the Underdrain System shows an R squared of 0.9458. Analyzing the results, both system

has a strong correlation for having values nearing 1. Thus, it obviously states that as the

dimensions increase, the cost increases as well.

Table 13: Cost Comparison Data

Underdrain System Using RCP Rectangular Lined Ditch (in


Equivalent Area
(in Philippine Peso) Philippine Peso)

0.0314159 948.7705377 1342.890302

0.070685775 1209.581407 1394.827775

0.1256636 1470.392276 1467.540237

0.196349375 1731.203145 1561.027687

0.2827431 1992.014014 1675.290127

0.384844775 2252.824883 1810.327557

0.5026544 2513.635753 1966.139975

0.636171975 2774.446622 2142.727382

0.7853975 3035.257491 2340.089779

0.950330975 3296.06836 2558.227164

1.1309724 3556.879229 2797.139539

1.327321775 3817.690098 3056.826902

1.5393791 4078.500967 3337.289255

1.767144375 4339.311837 3638.526597

2.0106176 4600.122706 3960.538928

76
2.269798775 4860.933575 4303.326248

2.5446879 5121.744444 4666.888557

2.835284975 5382.555313 5051.225855

3.14159 5643.366182 5456.338143

3.463602975 5904.177051 5882.225419

3.8013239 6164.987921 6328.887685

4.154752775 6425.79879 6796.324939

4.5238896 6686.609659 7284.537183

4.908734375 6947.420528 7793.524416

5.3092871 7208.231397 8323.286638

5.725547775 7469.042266 8873.823849

6.1575164 7729.853135 9463.267762

6.605192975 7990.664005 10106.887

7.0685775 8251.474874 10773.08937

7.547669975 8512.285743 11461.87487

8.0424704 8773.096612 12173.24351

8.552978775 9033.907481 12907.19527

9.0791951 9294.71835 13663.73017

9.621119375 9555.529219 14442.8482

10.1787516 9816.340089 15244.54935

10.75209178 10077.15096 16068.83364

11.3411399 10337.96183 16915.70106

11.94589598 10598.7727 17785.15162

77
12.56636 10859.58357 18677.1853

This table shows the Comparison of Cost between the Rectangular Lined Ditch and

Underdrain System using RCP. The equivalent area starting from 0.125 to 3.463 shows that

Rectangular Lined Ditch has the lesser cost between the two systems, thus Rectangular Lined

Ditch is the best system to be used. On the other hand, the rest of the data shows that the

Underdrain System using RCP has the lesser cost, thus, that system is best to use for that range.

78
In order to further the research, the group has conducted interviews from different, yet

relevant divisions from the Department of Public Works and Highways‟ main office. From the

Bureau of Design- Water Projects Division, the researchers were able to interview 2 engineers:

Engr. Crissa Rica V. Espiritu and Engr. Matthew G. Velasco. From the Bureau of Design –

Highways Division: Engr. Edwin G.Azurin. According to the results of the interview, it is easier

to design a Rectangular Lined Ditch, however, it must be noted that Underdrain Systems using

RCP are more efficient. Each type of network has their own set of advantages.

Rectangular Lined Ditch

Advantages Disadvantages

Less Transportation Cost – Easy Maintenance Requires more time to construct

Construction errors and mistakes can easily be May meet problems due to acquisition of right

detected of way

There are a variety of bed linings that can be

used

Underdrain Systems using RCP

Advantages Disadvantages

Dimensions are readily available in the market Leakages are difficult to manage

Easy to install High maintenance cost

Less time to install Joining RCP‟s take exert effort

Quantities on site may not be the same as per

plan since it is concealed underneath

79
The planning process involves identifying the topography of the area, estimating the amount of

flow, and accounting for the future development in the area. A hydrologic analysis which consists

of (a) delineation of catchment area and (b) use of either Rational Method or Unit Hydrograph

Method is also used. Finally, a hydraulic analysis is performed by use of either Manning‟s

formula or Chezy‟s equation. Unknown topography and a mountainous terrain are factors

considered to make the planning process more challenging. More difficulties arise as one

considers financial matters, availability of materials, political intervention, site conditions and

acquisition of right- of-way. The DPWH uses what they call the “Blue Book” which contains

planning and designing flood control structure and the Design Guide, Criteria Standards Vol II.

Underdrain Systems using RCP usually uses pre-cast concrete and the Rectangular Lined Ditch

uses the conventional cast-in-place concrete. Again, the standards used for these materials can be

found in the Blue Book. In terms of construction, it is easier to construct a Rectangular Line Ditch

because it only involves an excavation, and from there one can start the construction of the actual

ditch. Factors that make the construction coincide with those in factors considered in planning:

irregular topography, and the location of the site. Other factors to be considered are the

availability of the materials going to be used in construction, and the existing pipelines (e.g. gas,

sewer and water supply) .

Rectangular Line Ditches commonly use 10mm Φ bars for rebars, class A concrete mix, a

concrete mixer, a backhoe, a rebar cutter, and a plate compactor. However, it must be noted that

the diameter for the rebars vary depending on the structural capacity of the ditch. Underdrain

Systems using RCP, on the other hand, commonly uses 0.60 m, 0. 90m, 1.12m and 1.50m Φ

Reinforced Concrete Pipe diameter and 10mm Φ, 12mm Φ and 18mm Φ rebar dimensions. It

utilizes a concrete mixer and a plate compactor, and uses early strength concrete. A Rectangular

80
Lined Ditch can be constructed in 5 days per linear meter while the RCP can be constructed in 10

days per linear meter.

In terms of manpower, the Rectangular Lined Ditch uses less manpower as it has lesser

excavation works. The two systems rely heavily on equipment. When asked to give an estimate

number of manpower required for the two systems, it appears that the Lined Ditch uses at least 4

laborers/ linear meter and the RCP uses 7 laborers/linear meter.

As for the maintenance of the systems, the Lined Ditch has an advantage because of its

accessibility. Drainage networks are usually maintained through de-clogging. One factor to be

considered when maintaining drainage networks is where to put all the silts and waste.

Finally, from the interviews conducted, most engineers say that the Lined Ditch is more

applicable for rural settings and the RCP for urban settings. As Niog, Bacoor, Cavite is seen to be

heavily urbanized in the future, the researches therefore consider the RCP fitting for it.

81
Chapter 4

CONCLUSION

For this study, „Optimization of Roadside Drainage Systems: A Comparative Analysis of

Rectangular Lined Ditch and Underdrain System using RCP‟, the researchers have attempted to

explore the question: “Are open channels better than closed conduits?” In search of a sound

answer that is backed by meticulous research, the group has explored various avenues in

determination of proper and relevant parameters. In view of the objective of this research, this

was to determine the most efficient drainage network between Rectangular Lined Ditch (for open)

and Underdrain Systems using RCP (for closed) with flood mitigation in mind. The parameters

used included the velocity, planning, and the unit cost for every possible item and equipment

needed during construction, the ease of construction, the time required for completion, manpower

required and the applicability of the network due to the geography of the area in question. In this

study, the researchers have considered Niog Road in Bacoor City, Cavite. As time goes by and the

economy booms, Cavite is seen to be heavily urbanized in the coming years, what with its land

value increasing, land use and space is becoming more and more crucial. The aforementioned

issue was also addressed in this study.

In order to achieve the required results for this study, the group has conducted surveys and

interviews with various departments in both private and public sectors such as the Department of

Public Works and Highways and Maynilad Water Services Incorporated. Furthermore, the

researchers did a correlation of different relevant parameters and plotted them in order to

represent the data better. Finally, this research has also obtained unit costs from different agencies

to better compare the two drainage networks.

82
From the survey and interview conducted, the following data have been concluded: In terms of

planning, it appears that the Rectangular Lined Ditch is more advantageous due to its simplicity

and because it uses lesser land area than the Underdrain System. However, rhe Underdrain

System using RCP has more runoff capacity and its cross sectional dimensions are more suitable

and advantageous. Also, when it comes to the applicability depending on the geography and land

use, it seems that Underdrain Systems using RCP are more beneficial especially for urban area.

In designing drainage systems, most of the respondents use company and agency standards as

their common practice when it comes to the standards. They inspect the site for data gathering for

the dimensions and the field conditions. During the designing process most respondents use

AutoCAD as their software. In addition, companies and agencies provide seminars and

workshops on designing roadside drainages.

For the resources and manufacturing of materials, Rectangular Line Ditches uses simpler

materials through conventional cast-in-place components while the Underdrain System using

RCP use pre-cast components.

On construction and installation procedures, generally, Rectangular Lined Ditches have simpler

construction methodology. However, it must be noted that despite the ease in procedure, the

dimension still matters when it comes to the time needed to complete the construction. As for the

manpower required, it can be concluded that construction needs 20-60 people depending on the

scale of project. Finally, when it comes to maintaining these drainage networks, it appears that the

Rectangular Lined Ditches are much easier to preserve.

83
On to the results from the correlation of various parameters and the usage of different empirical

formulas, it can be ascertained that for the cross-sectional area of 0.125 to 2.010 shows that

Rectangular Lined Ditch is the effective system to use. On the other hand, the rest of the cross-

sectional area shows that Underdrain system using RCP is the effective system to use. The results

are the same for all the comparisons and correlations made. Finally, The equivalent area starting

from 0.125 to 3.463 shows that Rectangular Lined Ditch has the lesser cost between the two

systems, thus Rectangular Lined Ditch is the best system to be used. On the other hand, the rest of

data shows that the Underdrain System using RCP has the lesser cost, thus, that system is best to

use for that range.

84
Chapter 5

RECOMMENDATION

In the pursuit of having compared two different types of channels, open channels and closed

conduit in terms of various formulas for flow, diameter and cost, the group has arrived to a

conclusion. Rectangular Lined Ditch is better when one compares and contrasts a number of

parameters to come up with an optimized option. It also recommended exploring other

parameters, such as rainfall intensity using various methodologies and considering a certain

amount of flow. The researchers advocate for the exploration of a different type of open channel

and closed conduit. One example for the open channel would be a trapezoidal line ditch which is

rarely utilized due to its level of difficulty when to it comes to design and construction. For the

Closed Conduit, a line ditch with cover can be considered as well as it is accessible. However,

one must consider the applicability, which depends on the location (urban or rural). Finally, a

different angle on the determination of results might be viewed when the concepts are applied

using experimentation.

85
REFERENCES

Abdellatif, Atherton, Alkhaddar & Osman (2013). Linking Climate Change to Water Sector: A

Case Study of Urban Drainage System. Retrieved from http://www.climate-impacts-

2013.org/files/cwi_abdellatif.pdf

A. König, J. J. Linde, O. Mark, & G. Svensson, (2008). Analyses and Adaptation of Climate

Change Impacts on Urban Drainage Systems. 11th International Conference on Urban

Drainage, Edinburgh, Scotland, UK, 2008

B. Clarke, D. M. Hultstrand & T.W. Parzybok, (2011). Average Recurrence Interval of

Extreme Rainfall in Real-time. Retrieved from http://www.earthzine.org/2011/04/19/average-

recurrence-interval-of-extreme-rainfall-in-real-time/

Blendermann (1979). Controlled Storm Water Drainage. 200 Madison Avenue New York:

Industrial Press Inc.

T. Daniell & G. Tabios III (2008). Asian Pacific FRIEND Rainfall Intensity Duration

Frequency (IDF) Analysis for the Asia Pacific Region. Retrieved from

http://unesdoc.unesco.org/images/0018/001802/180223E.pdf

Cimorelli et al (2013). Optimal Design of Rural Drainage Networks. J. Irrig. Drain

Eng., 139(2), 137–144. Retrieved from http://ascelibrary.org/doi/abs/10.1061/(ASCE)IR.1943-

4774.0000526

86
Environment Solutions (2014). Complete Confidence in One Solution Unmatched Protection

Unparalleled Technology. Retrieved from

http://www.solterraph.com/Environment%20Solutions%20Brochure.pdf

Grigg, Hiller & Riordan (1978). Development of a Drainage and Flood Control Management

Program for Urbanizing Communities-Part II. Retrieved from

http://www.cwi.colostate.edu/publications/cr/86.pdf

J. Marsalek & W. E. Watt (1984). Design storms for urban drainage design. Canadian Journal

of Civil Engineering, 1984, 11(3): 574-584, 10.1139/l84-075. Retrieved from

http://www.nrcresearchpress.com/doi/abs/10.1139/l84-075

K. Berggren (2008). Indicators for urban drainage system-assessment of climate change

impacts. 11th International Conference on Urban Drainage, Edinburgh, Scotland, UK, 2008

R.S.V Teegavarapu (2012). Floods in a Changing Climate: Extreme Precipitation. Retrieved

from

http://books.google.com.ph/books?id=KJa6tEGMzwQC&pg=PA3&dq=floods+rainfall&hl=en&s

a=X&ei=AtkOU4jHAoqjigedsYDwAw&ved=0CDUQ6AEwAw#v=onepage&q=floods%20rainf

all&f=false

87
S. Duchesne & A. Mailhot, (2010). Design Criteria of Urban Drainage Infrastructures under

Climate Change. J. Water Resour. Plann. Manage. 136(2), 201–208.

United States Environmental Protection Agency (2007) Condition Assessment of Collection

Systems. Science BRIEF. Retrieved from http://nepis.epa.gov/Adobe/PDF/60000GYY.pdf

United States Environmental Protection Agency (2007). Condition Assessment of Collection

Systems. Science BRIEF. Retrieved from http://nepis.epa.gov/Adobe/PDF/60000GYY.pdf

88
APPENDICES

89
APPENDIX A

DPWH GENERAL NOTES AND UNIT COST

90
GENERAL NOTES

1. STANDARD SPECIFICATION

All works shall comply with DPWH standard specification for highways, bridges, and airports
revised 2013 special provision and supplemental specifications pertaining to this project.
Conditions of contract (Int‟l) for works of civil engineers construction, 2nd Edition, prepared by
F.I.D.I.C. shall also govern.

2. DIMENSIONS

Unless otherwise specified, all dimensions which include stationing, distances between control
points and elevations are measured in meters.

3. ALIGNMENT AND GRADE

No alteration or change in alignment and grade shall be made unless existing field condition so
warrant and only upon written order by the engineers and approved by the proper authority
concerned.

4. REMOVAL OF EXISTING STRUCTURES AND OBSTRUCTIONS


a. All works shall comply with clause 39 “Requirements and Conditions of Contracts”,
Volume-1 of the standard specifications for public works and highways, 2004.
b. Portion of existing utilities, such as water mains, irrigation channels, telephone post and
trunk line etc., that may cause obstructions to the construction of this project shall be
relocated by the entity or owner concerned, extreme precaution must be exercised.
Damaged thereof shall be the account of the contractor.
5. SUB-GRADE, SUB-BASE AND BASE
a. Unsuitable sub – grade material shall be excavated below the ground surface to the
required width and depth, the area to be excavated shall be backfilled with approved
material.
b. No embankment materials shall be placed until the foundation is stable.
6. CONCRETE AND CONCRETE PAVEMENT
a. All concrete to be used in this project shall be class “A” unless otherwise indicated.
b. No admixtures or additives will be allowed for all concrete works without prior approval
from the secretary of department of public works and highways or his duly representative.
c. Traffic shall be required to reduce speed when passing the vicinity of the newly laid
concrete pavement until such time that it has obtained the fourteen (14) days required
strength.
7. DRAINAGE
a. Exact location, slope, out falls and invert elevations of drainage structures shall be
checked in the field by the engineer, minor adjustment may be made by the approval of the
engineer to suit actual field condition.
b. Existing drainage structure, or part thereof removed by the contractor that are still
serviceable shall be unread over to the government and shall be deposited at a place within

91
the project site designated by the engineer without any extra compensation, extreme
precaution shall be exercised by the contractor not to damage these materials during the
removal and handling.

8. CONSTRUCTION STAKES
a. The contractor will be responsible for the true and proper setting-out of the work or
improvement and for correctness of position, level, slope and continuous profile grade in
road work. He will set construction stakes, establishing lines, slope and continuous profile
work and other line and bench mark for bridge work, grade in road protective and
necessary structures and appurtenances culvert work, as are deemed necessary from the
reference date to be furnished by the engineer in writing.
b. The checking of construction stakes by the engineer shall not in any way relieve the
contractor of his responsibility for the correctness thereof and the contractor shall carefully
protect and preserve all bench mark, pegs and other things used in setting out the work.
c. In the case of “change or change in condition” which involves any changes in stake out,
the contractor shall cooperate with the engineer and facilitate the prompt re-establishment
of the field for the alternative or adjusted work.

9. STANDARD DRAWING

The necessary drawing contained in the DPWH Standard Drawing for road shall be utilized for the
project unless otherwise a more detailed structural drawing.

10. QUANTITY

Quantity of various work items involved are subject to decrease or increase depending on the
actual field condition.

92
EQUIPMENT REQUIREMENT AND COST

EQUIPMENT REQUIREMENTS
Unit Description
4 Dumptruck
1 Payloader (1.50 cu. m.)
3 Backhoe (0.80 cu. m.)
1 Backhoe w/ Pavement Breaker ((0.80 cu. m.)
2 Water truck (1000 gal)
2 Submersible Pump
1 Road Roller
1 Road Grader
1 Crane (45T)
1 Vibro Hammer
1 Generator Set (876-1000KVA)
1 Plate Compactor

MANPOWER REQUIREMENTS
1 – Project Engineer
1 – Project Inspector
1 – Materials Engineer
1 – Safety Officer

ESTIMATED DIRECT COST (EST)


Item No. Unit Unit Cost
101(3a) Removal of Existing sq. m. 119.28
Concrete Pavement
103(1a) Structure Excavation cu. m. 115.11
(Ordinary Soil)
104(a) Embankment (Sand) cu. m. 831.65
104(b) Embankment (Selected cu. m. 609.15
Borrow)
200 Aggregate Subbase cu. m. 636.15
Course
311 (3)a.4 PCCP (t=0.23m; 14 days sq.m. 940.06
– 3500 psi)
404a Reinforcing Steel Bar, kg 46.67
Grade 60
405a Stuctural Concrete Class cu. m. 5,207.00
“A”
502(3) RCMH (Utility pcs. 56,702.00
Manhole)
SPL-1 Dewatering/Sandbagging l.s. 149,651.85
SPL-2 Structural Steel Sheet l.m. 784.92
Pile, Driven
SPL-3 Structural Steel Sheet l.m. 383.83
Pile, Extract

93
SPL-4 Rental of Structural Steel kg 10.00
Sheet Pile
SPL-5 Construction Safety and l.s. 288,176.46
Health
SPL-6 Traffic Management l.s. 429,905.60
SPL-7 Temporary Work l.s. 200,000.00
Closure
SPL-8 Rental of Field Office mo. 20,750.00
for Engineers
SPL-9 Mobilization/ l.s. 178,984.00
Demobilization

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description: 101(3a) Removal of Existing Concrete Pavement


Unit of Measurement: sq. m.
Output per Hour: 40.00
Designation No. of Person No. of Hourly Amount
Hours Rate
A. Labor
a. Construction Foreman 1 1 122.45 122.45
b. Laborer 2 1 69.33 138.66
Subtotal for A 261.11
Name and Capacity No. of Units No. of Hourly Amount
Hours Rate
Equipment
B. a. Backhoe w/ Pavement Breaker (0.80 1 1 2,074.95 2,074.95
cu.m.)
b. Payloader(1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
c. Dump Truck (10 cu.m.) 1 0.445 1,352.00 601.91
Minor Tools (10% of Labor) 26.11 26.11
Subtotal for B 4,435.97

C. Total (A+B) 4,697.08


D. Output per Hour = 40.00 sq.m.
E. Direct Unit Cost (C+D) 117.43

F. Name and Specification


Materials

G. Direct Unit Cost (E+F) 117.43


H. Overhead, Contingencies & of G 10.57

94
Miscellaneous (OCM)
I. Contractor's Profit (CP) of G 9.39
J. Value Added Tax (VAT) of (G+H+I) 16.49

K. Total Unit Cost (G + H + I 153.88


+J)

Item No. / Description: 104(a) Embankment (Filling Materials, Sand)


Unit of Measurement: cu. m.
Output per Hour: 50.00
Designation No. of Person No. of Hourly Amount
Hours Rate
A. Labor
a. Construction Foreman 1 0.9 122.45 110.21
b. Laborer 2 0.8 69.33 110.93
Subtotal for A 221.13
Name and Capacity No. of Units No. of Hourly Amount
Hours Rate
Equipment
B. a. Water Truck (1000 gal.) 1 0.3 1,065.00 332.70
b. Vibrator Roller 1 0.82 1,507.00 1,235.74
c. Motorized Grader 1 0.82 2,173.00 1,781.86

Subtotal for B 3,340.30

C. Total (A+B) 3,561.43


D. Output per Hour = 50.00 cu.m.
E. Direct Unit Cost (C+D) 71.23

F. Name and Specification Unit Quantity Unit Amount


Cost
Materials
a. Fine Aggregates (Filling Materials) cu.m. 1.15 650 747.5

Subtotal for F 747.5


G. Direct Unit Cost (E+F) 818.73
H. Overhead, Contingencies & of G 73.69
Miscellaneous (OCM)
I. Contractor's Profit (CP) of G 65.5
J. Value Added Tax (VAT) of (G+H+I) 114.95

K. Total Unit Cost (G + H + I 1,072.86


+J)

95
Item No. / Description: 104(b) Embankment (Selected Borrow)
Unit of Measurement: cu. m.
Output per Hour: 50.00
Designation No. of Person No. of Hourly Amount
Hours Rate
A. Labor
a. Construction Foreman 1 1 122.45 122.45
b. Laborer 2 0.85 69.33 117.86
Subtotal for A 240.31
Name and Capacity No. of Units No. of Hourly Amount
Hours Rate
Equipment
B. a. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
b. Vibrator Roller (10 m.t.) 1 0.79 1,507.00 1,190.53
c. Motorized Grader, G107A 1 0.79 2,173.00 1,716.67

Subtotal for B 3,173.45

C. Total (A+B) 3,413.76


D. Output per Hour = 50.00 cu.m.
E. Direct Unit Cost (C+D) 68.27522

F. Name and Specification Unit Quantity Unit Amount


Cost
Materials
a. Selected Borrow (w/ 25% Shrinkage cu.m. 1.25 420 525
Factor)

Subtotal for F 525


G. Direct Unit Cost (E+F) 593.28
H. Overhead, Contingencies & Miscellaneous of G 53.97
(OCM)
I. Contractor's Profit (CP) of G 47.97
J. Value Added Tax (VAT) of (G+H+I) 84.19

K. Total Unit Cost (G + H + I +J) 779.41

96
Item No. / Description: 311(3)a.4 PCCP, t=230 mm. thk. (3500 psi, 14 days)
Unit of Measurement: sq. m.
Output per Hour: 70.00
Designation No. of Person No. of Hourly Amount
Hours Rate
A. Labor
a. Construction Foreman 1 0.75 122.45 91.84
b. Laborer 12 0.406 69.33 337.78
c. Skilled Laborer 6 0.75 82.97 373.37

Subtotal for A 802.98


B. Name and Capacity No. of Units No. of Hourly Amount
Hours Rate
Equipment
a. Concrete Vibrator 2 0.25 148.88 74.44
b. Concrete Screeder (5.5 Hp) 1 0.8 545.00 436.00
c. Concrete Saw, Blade φ 14" (7.5Hp) 1 0.8 167.38 133.90
d. Bar Cutter, Single Phase, 25mm 1 0.8 219.75 175.80
e. Water Truck 1000 gals (All Makes) 1 0.35 1,065.00 372.75

C. Subtotal for B 1,192.89


D. 70
E. Total (A+B) 1,995.87
Output per Hour = 50.00 cu.m.
F. Direct Unit Cost (C+D) 28.51

Name and Specification Unit Quantity Unit Amount


Cost
Materials
a. Reinforcing Steel Bar kg. 0.39 36 14.04
b. Curing Compound lit. 0.29 70 20.30

c. Asphalt Sealant lit. 0.12 55 6.60

d. Steel Forms Rental l.m. 0.46 100 46


e. Ready Mix Concrete cu.m. 0.23 3,500 805
f. Concrete Saw (Diamond Blade) pc. 0.00015 8,000 1.2
g. Pipe Sleeve, 2" dia. l.m. 0.007 237.5 1.66
h. Grease/Tar lit. 0.01 245 2.45

Subtotal for F 897.25


G. Direct Unit Cost (E+F) 925.76

97
H. Overhead, Contingencies & Miscellaneous of G 83.29
(OCM)
I. Contractor's Profit (CP) of G 74.04
J. Value Added Tax (VAT) of (G+H+I) 129.94
K. Total Unit Cost (G + H + I +J) 1,213.03

98
Item No. / Description: 4-04a Reinforcing Steel Bar, Grade 60
Unit of Measurement: kg.
Output per Hour: 180.00
Designation No. of Person No. of Hourly Amount
Hours Rate
A. Labor
a. Construction Foreman 1 1 0 0.00
b. Laborer 4 0.9 69.33 249.59
c. Skilled Laborer 2 1 82.97 165.94

Subtotal for A 415.53


B. Name and Capacity No. of Units No. of Hourly Amount
Hours Rate
Equipment
a.Cargo Truck (10 T, 2740 Hp) All Models 1 0.17 1,012.00 172.04
b. Bar Cutter 1 0.5 219.75 109.88
c. Bar Bender 1 0.5 351.50 175.75
C. Subtotal for B 457.67
D. 70
E. Total (A+B) 873.19
Output per Hour = 50.00 cu.m.
F. Direct Unit Cost (C+D) 4.85
D.
E. Name and Specification Unit Quantity Unit Amount
Cost
Materials
F. a. Tie Wire (2% of RSB) kg. 0.021 57 1.20
b. Reinforcing Steel Bar, Grade 60 kg. 1.05 38 39.90

Subtotal for F 41.10


G. Direct Unit Cost (E+F) 45.95
H. Overhead, Contingencies & Miscellaneous of G 4.14
(OCM)
I. Contractor's Profit (CP) of G 3.68
J. Value Added Tax (VAT) of (G+H+I) 6.45
K. Total Unit Cost (G + H + I +J) 60.21

99
Item No. / Description: 4-05a Structural Concrete Class “A”
Unit of Measurement: cu.m.
Output per Hour: 1.40
Designation No. of Person No. of Hourly Amount
Hours Rate
A. Labor
a. Construction Foreman 1 1 122.45 122.45
b. Laborer 4 1 69.33 277.32
c. Skilled Laborer 2 1 82.97 165.94
Installation / Removal of Formworks
a. Skilled Laborer 2 1 82.97 165.94
b. Laborer 4 1 69.33 277.32
Subtotal for A 1008.97
B. Name and Capacity No. of Units No. of Hourly Amount
Hours Rate
Equipment
a. Concrete Vibrator 1 1 148.88 148.88
b. Water Truck (1000 gal.) All Makes 1 0.144 1,065.00 153.36
c. One Bagger Mixer 1 0.5 172.00 86.00
Subtotal for B 388.24
C. Total (A+B) 1,397.21
D. Output per Hour = 1.40 cu.m.
E. Direct Unit Cost (C/D) 981.3
F.
Name and Specification Unit Quantity Unit Amount
Cost
Materials

a. Lumber, Good - 4 uses bd.ft. 70 40.00 700.00

b. Plywood (1/2" x 4' x8') - 4 uses pc. 1.6 750.00 300.00


c. Assorted CWN (1kg./100 bd. ft. of kg. 0.7 70.00 49.00
Lumber)
d. Cement bags 9.5 218.00 2071.00
e. Sand cu.m. 0.5 650.00 325.00
f. Gravel cu.m. 1 700.00 700.00
Subtotal for F 4145.00
G. Direct Unit Cost (E+F) 5126.30
H. Overhead, Contingencies & Miscellaneous of G 461.37
(OCM)
I. Contractor's Profit (CP) of G 410.10
J. Value Added Tax (VAT) of (G+H+I) 719.73
K. Total Unit Cost (G + H + I +J) 6,717.50

100
Item No. / Description: 502(3a) RC Manhole (Utility Manhole)
Unit of Measurement: each
Output per Hour: 1.00
Designation No. of Person No. of Hourly Amount
Hours Rate
A. Labor
a. Construction Foreman 1 10 122.45 1224.50
b. Laborer 4 9.7 69.33 2690.00
c. Skilled Laborer 2 10 82.97 1659.40
Subtotal for A 5573.90
B. Name and Capacity No. of Units No. of Hourly Amount
Hours Rate
Equipment
a. One Bagger Mixer 1 0.757 172.00 130.20
b. Water Truck (1000 gal) 1 0.45 1,065.00 479.25
c. Bar Cutter 1 0.45 219.75 98.89
d. Bar Bender 1 0.45 351.50 158.18
e. Concrete Vibrator 1 0.73 148.88 108.68
f. Welding Machine 1 0.73 391.00 285.43
Minor Tools (10% Labor) 551.84 551.84
Subtotal for B 1,812.47
C. Total (A+B) 7,386.37
D. Output = 1 each/day
E. Direct Unit Cost (C/D) 7,386.37
F.
Name and Specification Unit Quantity Unit Cost Amount
Materials
a. Cement bags 29 218.00 6322.00
b. Sand cu.m. 1.582 650.00 1028.30
c. Gravel cu.m. 3.164 700.00 2214.80
d. Reinforcing Steel Bar kg 385.9 36.00 13892.40

e. #16 GI Tie Wire (2% RSB) kg 7.72 70.00 540.40

f. Steel Casing (Angle Bar) kg 57.08 46.00 2625.68


g. Welding Rod (1kg/2000 kg of Steel) kg 0.029 90 2.61
h. 1/4" Ordinary Plywood - 2 uses pc 9.16 330 1511.40
i. Coco Lumber - 2 uses bd. Ft. 129.63 20 1296.30
j. Assorted CWN (1kg. / 1000 bd. ft. of kg 1.296 70 45.36
Lumber)
k. Steel Grating (Webforge) pc 1 18,053.20 18053.20
l. U-bolt ( 20mm dia. X 800mm) pc 2 430 860.00

101
Subtotal for F 48392.45
G. Direct Unit Cost (E+F) 55778.82
H. Overhead, Contingencies & of G 5024.15
Miscellaneous (OCM)
I. Contractor's Profit (CP) of G 4465.91
J. Value Added Tax (VAT) of (G+H+I) 7837.68
K. Total Unit Cost (G + H + I +J) 73,106.56

102
Item No. / Description: SPL – 1 Dewatering/Sandbagging
Unit of Measurement: l.s.
Output per Hour: 1.00
Designation No. of Person No. of Hourly Amount
Hours Rate
A. Labor
for dewatering
a. Construction Foreman 1 59 122.45 7224.55
b. Laborer 2 59 69.33 8180.94
for sandbagging
a. Construction Foreman 1 30 122.45 3673.50
b. Laborer 4 30 69.33 8319.60
Subtotal for A 27398.59
B. Name and Capacity No. of Units No. of Hourly Amount
Hours Rate
Equipment
a. Submersible Pump (Diesel Model, 2 52.019 216.88 22,563.24
1200 lpm, 5Hp)
Minor Tools (5% Labor) 1 1 1,369.93 1,369.93
Vol. of concrete = 1,079.00 cu. m. / 1.40
cu.m.
Subtotal for B 23,933.17
C. Total (A+B) 51,331.76
D. Output per hr. = 1.00 sq.m.
E. Direct Unit Cost (C/D) 51,331.76
F.
Name and Specification Unit Quantity Unit Cost Amount
Materials
a. Sand cu.m. 120 650.00 78000.00

b. Sand (0.10 cu.m. / sack) pcs. 1200 15.00 18000.00

Subtotal for F 96000.00


G. Direct Unit Cost (E+F) 147331.76
H. Overhead, Contingencies & of G 13259.86
Miscellaneous (OCM)
I. Contractor's Profit (CP) of G 11786.54
J. Value Added Tax (VAT) of (G+H+I) 20685.38
K. Total Unit Cost (G + H + I +J) 193,063.54

103
Item No. / Description: SPL – 2 Structural Steel Sheet Pile, Driven
Unit of Measurement: l.m.
Output per Hour: 10.00
Designation No. of Person No. of Hourly Amount
Hours Rate
A. Labor
a. Construction Foreman 1 1 0 0.00
b. Laborer 6 1 69.33 415.98
c. Skilled Laborer 6 1 82.97 497.82
Subtotal for A 913.80
B. Name and Capacity No. of Units No. of Hourly Amount
Hours Rate
Equipment
a. Crane (45T) 1 1 1,772.00 1,772.00
b. Vibro Hammer 1 1 3,069.00 3,069.00
c. Generator Set (876-1000 KVA) 1 1 1,296.67 1,296.67
d. Welding Machine 1 1 391.00 391.00
e. Cutting Outfit 1 0.514 45.45 23.36
Subtotal for B 6,552.03
C. Total (A+B) 7,465.83
D. Output per hr. = 10.00 sq.m.
E. Direct Unit Cost (C/D) 746.58
F.
Name and Specification Unit Quantity Unit Cost Amount
Materials
a. Welding Rod kg. 0.024 90.00 2.16
b. Oxy/Acetylene set 0.0096 2500.00 24.00
Subtotal for F 26.16
G. Direct Unit Cost (E+F) 772.74

H. Overhead, Contingencies & of G 69.55


Miscellaneous (OCM)
I. Contractor's Profit (CP) of G 61.82
J. Value Added Tax (VAT) of (G+H+I) 108.49
K. Total Unit Cost (G + H + I +J) 1,012.60

104
Item No. / Description: SPL –3 Structural Steel Sheet Pile, Extract
Unit of Measurement: l.m.
Output per Hour: 20.00
Designation No. of Person No. of Hourly Amount
Hours Rate
A. Labor
a. Construction Foreman 1 1 122.45 122.45
b. Laborer 6 0.9 69.33 374.38
c. Skilled Laborer 6 0.9 82.97 448.04
Subtotal for A 944.87
B. Name and Capacity No. of Units No. of Hourly Amount
Hours Rate
Equipment
a. Crane (45T) 1 1 1,772.00 1,772.00
b. Vibro Hammer 1 1 3,069.00 3,069.00
c. Generator Set (876-1000 KVA) 1 0.96 1,296.67 1,244.80
d. Cutting Outfit 1 1 45.45 45.45
Subtotal for B 6,131.25
C. Total (A+B) 7,076.12
D. Output per hr. = 10.00 sq.m.
E. Direct Unit Cost (C/D) 353.87
F.
Name and Specification Unit Quantity Unit Cost Amount
Materials
a. Oxy/Acetylene set 0.0096 2500.00 24.00
Subtotal for F 24.00
G. Direct Unit Cost (E+F) 377.87
H. Overhead, Contingencies & of G 34.01
Miscellaneous (OCM)
I. Contractor's Profit (CP) of G 30.23

J. Value Added Tax (VAT) of (G+H+I) 53.05


K. Total Unit Cost (G + H + I +J) 495.16

105
Item No. / Description: SPL –4 Rental of Structural Steel Sheet Pile
Unit of Measurement: kg
Output per Hour: 1.00
Designation No. of Person No. of Hourly Amount
Hours Rate
A. Labor

Subtotal for A 0.00


B. Name and Capacity No. of Units No. of Hourly Amount
Hours Rate
Equipment

Subtotal for B 0.00


C. Total (A+B) 0.00
D. Output per hr. = 10.00 sq.m.
E. Direct Unit Cost (C/D) 0.00
F.
Name and Specification Unit Quantity Unit Cost Amount
Materials
a. Structural Steel Sheet Pile (Rental) l.m. 1 10.00 10.00
Subtotal for F 10.00
G. Direct Unit Cost (E+F) 10.00
H. Overhead, Contingencies & of G 0.9
Miscellaneous (OCM)
I. Contractor's Profit (CP) of G 0.80

J. Value Added Tax (VAT) of (G+H+I) 1.4


K. Total Unit Cost (G + H + I +J) 13.10

106
Item No. / Description: SPL –5 Construction Safety and Health
Unit of Measurement: l.s.
Output per Hour:

Designation No. of Person No. of Hourly Amount


Hours Rate
A. Labor
a. Safety Officer 1 304.664 122.45 37306.11
b. First Aider 1 1205 82.97 99978.85

Subtotal for A 137284.96


B. Name and Capacity No. of Units No. of Hourly Amount
Hours Rate
Equipment

Subtotal for B 0.00


C. Total (A+B) 137,284.96
D.
E. Direct Unit Cost (C/D) 137,284.96
F.
Name and Specification Unit Quantity Unit Cost Amount
Materials
a. Safety Shoes (Different Sizes) man-days 3900 2.77 10803.00
b. Safety Helmet/ Hard Hat (Free Size) man-days 3900 0.25 975.00
c. Working Gloves (free size) man-days 3900 7.67 29913.00
d. Rubber Boots man-days 1950 2.77 5401.50
e. Rain Coats man-days 1950 0.34 663.00
f. Safety Dust Mask man-days 1560 63.25 98670.00
Subtotal for F 146425.50
G. Direct Unit Cost (E+F) 283710.46
H. Overhead, Contingencies & of G 0
Miscellaneous (OCM)
I. Contractor's Profit (CP) of G 22696.84

J. Value Added Tax (VAT) of (G+H+I) 36,768.88

K. Total Unit Cost (G + H + I +J) 343,176.18

107
Item No. / Description: SPL –6 Traffic Management
Unit of Measurement: l.s.
Output per Hour: 1.00
Designation No. of Person No. of Hourly Amount
Hours Rate
A. Labor
a. Traffic Aide (3 shifts) 3 1407.9711 69.33 292843.91
Subtotal for A 292843.91
B. Name and Capacity No. of Units No. of Hourly Amount
Hours Rate
Equipment

Subtotal for B 0.00


C. Total (A+B) 292,843.91
D.
E. Direct Unit Cost (C/D) 292,843.91
F.
Name and Specification Unit Quantity Unit Cost Amount
Materials
Accessories for the Traffic Enforcer
a. Yellow Vest w/ Reflectorized pc 3 1500.00 4500.00
Markings
b. Raincoats pc 3 300.00 900.00
c. Sign Paddles (Red & Green) pc 3 2000.00 6000.00
d. Red Light pc 3 3000.00 9000.00

Traffic Signs and Barricades/Barrier


a.Construction Signs - 0.80mx0.60m GI pc 2 8000.00 16000.00
Plate G16, Mounted on GI Pipe and
Concrete Base
b. Regulatory Signs - 12"x40" pc 2 5000.00 10000.00
c. Regulatory Signs - 16"x40" pc 2 5000.00 10000.00

d. Notice/Advisory Signs pc 2 5000.00 10000.00


(9120x1200mm plywood)
e. Plastic Traffic Barriers (Rental) pc 10 1000.00 10000.00
f. Concrete New Jersey Barriers pc 10 1500.00 15000.00
(Rental)
g. Traffic Rope Light (Rental) pc 10 400.00 4000.00
h. Traffic Safety Cones (Rental) pc 10 500.00 5000.00
i. Flashing Arrow Signs (Rental) pc 2 15000.00 30000.00

Subtotal for F 130400.00

108
G. Direct Unit Cost (E+F) 423243.91
H. Overhead, Contingencies & of G 0
Miscellaneous (OCM)
I. Contractor's Profit (CP) of G 33859.51
J. Value Added Tax (VAT) of (G+H+I) 54,852.41
K. Total Unit Cost (G + H + I 511,955.83
+J)

109
Item No. / Description: SPL –7 Temporary Work Enclosure
Unit of Measurement: l.s.
Output per Hour: 1.00

Designation No. of Person No. of Hourly Amount


Hours Rate
A. Labor

Subtotal for A 0.00


B. Name and Capacity No. of Units No. of Hourly Amount
Hours Rate
Equipment

Subtotal for B 0.00


C. Total (A+B) 0.00
D.
E. Direct Unit Cost (C/D) 0.00
F. Name and Specification Unit Quantity Unit Cost Amount
Materials
a. Temporary Vertical Enclosure (Blue l.s. 1 196900.13 196900.13
Sheet) (Rental)
Subtotal for F 196900.13
G. Direct Unit Cost (E+F) 196900.13
H. Overhead, Contingencies & of G 0
Miscellaneous (OCM)
I. Contractor's Profit (CP) of G 15752.01
J. Value Added Tax (VAT) of (G+H+I) 25,518.26
K. Total Unit Cost (G + H + I 238,170.40
+J)

110
APPENDIX B

ARTICLE TYPE PAPER

111
Optimization of Roadside Drainage Systems: A Comparative
Analysis of Rectangular Lined Ditch and Underdrain System
using RCP

Jefferson Bill G. Bisnar, Kierwin S. De Dios, Patricia B. Profitana

Adviser: Engr. Juan Paulo Nazareno

MAPUA INSTITUTE OF TECHNOLOGY

School of Civil, Environmental and Geological Engineering

bisnar_jeff@yahoo.com
dedioskierwin_06@yahoo.com
patriciaprofitana@yahoo.com

(+ 63) 9274644682
(+ 63) 9055828547
(+ 63) 9065444308

September 2014

112
Abstract

Flooding during the rainy season along roadsides speaks to the inefficiency and inadequacy of the
existing drainage system. In order to become part of the solution, the researchers explored
methods from the engineering field to evaluate Rectangular Lined Ditches and Underdrain
Systems using RCP. The researchers shall dig into various parameters, such as hydrological
concepts, empirical formulas, planning, construction methods, manufacturing and resources, and
costing in order to ascertain a specific type of channel and determine an optimized choice.
Surveys from professionals in the field in both private and public sectors show that ease in
planning, manufacturing, constructing and maintaining a drainage network is really dependent on
the scale of the project. As for the correlation aspect of the research, it appears that the values
vary depending on the cross-sectional area. This also goes for the comparisons done for the cost
aspect of the research. Finally, it must be noted that despite the computations done, the
applicability of a certain type of drainage network remain a significant factor to consider.

Keywords: Rectangular Lined Ditches, Underdrain Systems

Acronyms/Abbreviations

RCP Reinforced Concrete Pipe

113
1 Introduction
The Philippines and flood waters have always had this longstanding affair. In the past, this
problem was only confined to a limited number of areas but as years passed, it has become a
much bigger problem; one that cannot be ignored anymore. The effects of flooding have
expanded from a simple inconvenience to loss of lives, livelihood, and lifelines.
1.1 Background and problem motivation
The researchers would like to take a look at the engineering point of view of the matter and
explore other solutions. This entails determining whether the pipe system and pipe capacity are
adequate in operating efficiently during the wet season considering the fact that recently, rainfall
is more intense and spaced between short periods of time. It also implies comparing different
types of channels, both open and closed. In addition, the researchers would also like to ascertain
whether it can mitigate the amount of inflow to the said drainage system.

1.2 Overall aim


The main objective of this research is to contrast two types of drainage system, the Rectangular
Lined Ditch, a type of open channel system, and the Underdrain Systems using Reinforced
Concrete Pipe (RCP), which is a type of closed channel system. The researchers shall explore
three (3) avenues for comparison; cost-related aspects, theoretical aspects, and a correlation of all
important parameters related to designing a certain drainage network, which shall be expounded
in the following chapters.

1.3 Scope
This study shall only cover comparison between Rectangular Lined Ditch (for open) and
Underdrain Systems using RCP (for closed). The parameters that the researchers will explore
shall cover the ease in planning, the resources to be considered, the construction procedure, time
of completion, manpower required and maintenance. It shall also compare the cost difference
between the two types of channels as well as the applicability of the drainage network. Moreover,
the researchers shall create a correlation graph in which the parameters in designing a drainage
network, such as wetted perimeter, critical discharge and the like. Finally, the researchers shall
only consider the drainage network applicable and suitable for Niog Road, Bacoor City, Cavite.

1.4 Concrete and verifiable goals

The specific goals of the study are to:

1. Identify a more efficient drainage network using different empirical formulas.


2. Identify a more cost effective drainage network using cost analyses from the
Department of Public Works and Highways as basis
3. Identify a more efficient drainage work using planning, materials and resources,
construction, time of completion and manpower as parameters for comparison.

114
2 Review of Related work
This section presents some significant past related works which would aid in the
comparison of parameters regarding the study.

2.1 Drainage System Design and its Background

Drainage system is an important aspect of urban and rural systems in all kinds of places.
Drainage system has unprecedented number of uses ranging from collecting sewage to storm
water runoffs. Urbanization is undoubtedly the main reason behind it all. Urbanization has a
huge impact on the modernization of a specific area by turning it from a natural and agricultural
environment to a residential and commercial environment.1 The transition will cause the alteration
in the storm water runoff nature of the said urbanizing watershed that will lead to increased storm
water damages such as floods.

2.2 Weather Effects and Climate Change

Excessive floods can be traced on high volume of rainfall coming from huge storms.
These storms happen due to disturbance in the climate. Since the Philippines is near the Pacific
Ocean, there will always be the possibility that the country will encounter many storms,
especially during the rainy season (June - September). But as of late, the number of storms as
well as their strength is being observed to increase and one can assume climate change is a factor.
The issue of climate change has been increasing and its effects have already been observed
around the world with further changes in climate being projected to take place in the future.2
Also, it is concluded that the Climate Change may affect the change the precipitation of some
countries.3 In addition to that, having an extreme summer condition will have a payoff during the
rainy season because there will be an increase in the rainfall events and its intensities. This will
be the primary reason for overflowing sewers that will cause floods in urban areas. The sudden
changes in the climatic conditions will drastically affect the urban drainage systems because of
the fact that the drainage system is related to the weather phenomenon and were built for the

1
Grigg, Hiller & Riordan (1978). Development of a Drainage and Flood Control Management
Program for Urbanizing Communities-Part II. Retrieved from
http://www.cwi.colostate.edu/publications/cr/86.pdf
2
Abdellatif, Atherton, Alkhaddar & Osman (2013). Linking Climate Change to Water Sector: A
Case Study of Urban Drainage System. Retrieved from http://www.climate-impacts-
2013.org/files/cwi_abdellatif.pdf
3
A. König, J. J. Linde, O. Mark, & G. Svensson, (2008). Analyses and Adaptation of Climate
Change Impacts on Urban Drainage Systems. 11th International Conference on Urban Drainage,
Edinburgh, Scotland, UK, 2008
115
purpose of coping up with the weather occurring.4 On the other hand, it was implied that extreme
flood conditions are not necessarily brought by the short-duration extreme rainfall events. The
long-duration rainfall event shall still be held responsible for extreme flooding events.5

2.3 Rainfall Intensity and Return Period

Rainfall is one of the main contributors of floods. Floods are not only the most frequent
natural disaster but also the disaster that produces the greatest economic and humanitarian impact
such as number of people and number of infrastructure affected.6 Floods are synonymous with
the amount of rainfall on a specific area. Meaning, the larger the rainfall on an area, the higher
the tendency of extreme floods. It is stated that before designing the storm-water drainage or
control system it is required to consider the nature of the incoming rainfall on the chosen area of
interest. 7 This data is called the Rainfall Intensity. Rainfall Intensity refers to the measurement
of the amount of rain that falls over time. The intensity of rain is measured in the height of the
water layer covering the ground in a period of time thus it implies that if the rain stays where it
falls, it would form a layer of a certain height. Usually every country has the means to measure
the rainfall intensity of a specific area. In the case of our country, the PAGASA is the foundation
that provides it. Since there are many rainfall intensity data available, it is challenging on the part
of engineers to design the storm-water drainages.

3 Methodology
This research entitled „Optimization of Roadside Drainage Systems: A Comparative Analysis of
Rectangular Lined Ditch and Underdrain System using RCP‟ will be approached as a qualitative

4
K. Berggren (2008). Indicators for urban drainage system-assessment of climate change impacts.
11th International Conference on Urban Drainage, Edinburgh, Scotland, UK, 2008
5
R.S.V Teegavarapu (2012). Floods in a Changing Climate: Extreme Precipitation. Retrieved
from
http://books.google.com.ph/books?id=KJa6tEGMzwQC&pg=PA3&dq=floods+rainfall&hl=en&s
a=X&ei=AtkOU4jHAoqjigedsYDwAw&ved=0CDUQ6AEwAw#v=onepage&q=floods%20rainf
all&f=false
6
Environment Solutions (2014). Complete Confidence in One Solution Unmatched Protection
Unparalleled Technology. Retrieved from
http://www.solterraph.com/Environment%20Solutions%20Brochure.pdf
7
Blendermann (1979). Controlled Storm Water Drainage. 200 Madison Avenue New York:
Industrial Press Inc.
116
research that will endeavor to amass data in relation to the economic, theoretical and technical
aspects of drainage systems. The information that shall be gathered will include the advantages
and disadvantages of either a Rectangular Line Ditch or Underdrain System using RCP. Data
shall also include a topographic survey of the area, identifying elevations. Moreover, hydrological
parameters will also be considered in this research and correlated. In addition, the researchers
chose the qualitative approach in order to verify and compare whether which type of channel is
capable of handling a significant amount of storm water and is efficient in transporting water
towards a respective outfall.

Data Gathering

Cost
Analytical
Analysis Survey
Computation

Rainfall
Intensity

Analysis of
Tabulation
velocity
of Results
obtained
from RLD
and UDS

Conclusion

8 Analytical Framework
4Results
and Discussion

117
This is the result of the questionnaire from the survey that the group conducted. It shows the

breakdown of answers from each of the sample. The results were divided into six parts

represented by the Roman numeral and the answers that can be found include; a, b, c and

others/NA. The rows colored with green represents the main questions that were interpreted in the

pie charts while the rows colored with yellow represents the questions whose answers involved

ranking of the choices.

Table 14: Summary of the Questionnaire Results

Summary

I a b c Others/NA

1 7 3

2 5 4 1

3 3 6 1

4 2 7 1

5 2 8

6 7 3

7 10

8 5 4 1

9 8 2

II

1 9 1

2 1 9

3 5 4 1

118
III

General

1 6 4

2 6 1 3

3 4 4 2

4 10

5 1 9

6 10

RLD

7 4 5 1

8 a,b

9 3 4 3

10 2 8

UDS

11 e,f,g

12 5 4 1

13 5 1 4

14 a,b,c

15 4 3 3

16 1 9

IV

1 1 2 4 3

2 10

119
3 a,b,c 7

4 c,d 7

1 4 5 1

2 1 9

3 b,c,d 7

VI

1 9 1

2 7 3

3 3 6 1

4 4 5 1

This table shows the summary of the results of the survey. For the respective numbers, the

table shows a tally of the results based on the choices available. The choices include a, b, c and

others/NA. The row with a green colored numbering represents the row whose results were

represented by a pie chart. The blue colored portions represents the highest results of the choices

while the yellow colored portions represents the summary of results for questions whose answers

involved a ranking.

Cost Analysis

This is the component of the study in which the Rectangular Lined Ditch and the Underdrain
System using RCP will be compared with the method of Cost Analysis. The data of Unit Cost

120
came from the DPWH Bureau of Design NCR Office.

Cost Analysis of Rectangular Line Ditch


and Underdrain Pipe
20000
Direct Cost from differetnt factors

18000 y = 1372.8x + 1199.6


16000 R² = 0.9996
14000 Underdrain Pipe
12000
10000 Rectanguar Iine Ditch
8000
6000 y = 747.78x + 2570.2 Linear (Underdrain Pipe)
4000 R² = 0.9458
2000 Linear (Rectanguar Iine
0 Ditch)
0 5 10 15
Equivalent Cross-sectional Area

Figure 9: Cost Analysis comparison graph

This graph shows the Cost Analysis of Rectangular Lined Ditch and Underdrain System using
RCP by showing the result of the Equivalent Cross-sectional Area versus Direct Cost. In this
graph, the coefficient of determination is computed and shown. The coefficient of determination
or R squared is a number that is used to indicate how well the data is fit for a statistical model. In
order for the R squared to have a “strong” correlation, the value must be greater than 0.8 while the
“weak” correlation shows a value of less than 0.5.

According to the graph shown, the Rectangular Lined Ditch shows an R squared of 0.9996 while
the Underdrain System shows an R squared of 0.9458. Analyzing the results, both system has a
strong correlation for having values nearing 1. Thus, it obviously states that as the dimensions
increase, the cost increases as well.

Table 15: Cost Comparison Data

Underdrain System Using RCP Rectangular Lined Ditch (in


Equivalent Area
(in Philippine Peso) Philippine Peso)

0.0314159 948.7705377 1342.890302

0.070685775 1209.581407 1394.827775

121
0.1256636 1470.392276 1467.540237

0.196349375 1731.203145 1561.027687

0.2827431 1992.014014 1675.290127

0.384844775 2252.824883 1810.327557

0.5026544 2513.635753 1966.139975

0.636171975 2774.446622 2142.727382

0.7853975 3035.257491 2340.089779

0.950330975 3296.06836 2558.227164

1.1309724 3556.879229 2797.139539

1.327321775 3817.690098 3056.826902

1.5393791 4078.500967 3337.289255

1.767144375 4339.311837 3638.526597

2.0106176 4600.122706 3960.538928

2.269798775 4860.933575 4303.326248

2.5446879 5121.744444 4666.888557

2.835284975 5382.555313 5051.225855

3.14159 5643.366182 5456.338143

3.463602975 5904.177051 5882.225419

3.8013239 6164.987921 6328.887685

4.154752775 6425.79879 6796.324939

4.5238896 6686.609659 7284.537183

4.908734375 6947.420528 7793.524416

5.3092871 7208.231397 8323.286638

5.725547775 7469.042266 8873.823849

122
6.1575164 7729.853135 9463.267762

6.605192975 7990.664005 10106.887

7.0685775 8251.474874 10773.08937

7.547669975 8512.285743 11461.87487

8.0424704 8773.096612 12173.24351

8.552978775 9033.907481 12907.19527

9.0791951 9294.71835 13663.73017

9.621119375 9555.529219 14442.8482

10.1787516 9816.340089 15244.54935

10.75209178 10077.15096 16068.83364

11.3411399 10337.96183 16915.70106

11.94589598 10598.7727 17785.15162

12.56636 10859.58357 18677.1853

This table shows the Comparison of Cost between the Rectangular Lined Ditch and
Underdrain System using RCP. The equivalent area starting from 0.125 to 3.463 shows that
Rectangular Lined Ditch has the lesser cost between the two systems, thus Rectangular Lined
Ditch is the best system to be used. On the other hand, the rest of the data shows that the
Underdrain System using RCP has the lesser cost, thus, that system is best to use for that range.

In order to further the research, the group has conducted interviews from different, yet relevant
divisions from the Department of Public Works and Highways‟ main office. From the Bureau of
Design- Water Projects Division, the researchers were able to interview 2 engineers: Engr. Crissa
Rica V. Espiritu and Engr. Matthew G. Velasco. From the Bureau of Design – Highways
Division: Engr. Edwin G.Azurin. According to the results of the interview, it is easier to design a
Rectangular Lined Ditch, however, it must be noted that Underdrain Systems using RCP are more
efficient. Each type of network has their own set of advantages.

123
Rectangular Lined Ditch

Advantages Disadvantages

Less Transportation Cost – Easy Maintenance Requires more time to construct

Construction errors and mistakes can easily be May meet problems due to acquisition of right
detected of way

There are a variety of bed linings that can be


used

Underdrain Systems using RCP

Advantages Disadvantages

Dimensions are readily available in the market Leakages are difficult to manage

Easy to install High maintenance cost

Less time to install Joining RCP‟s take exert effort

Quantities on site may not be the same as per


plan since it is concealed underneath

The planning process involves identifying the topography of the area, estimating the amount of
flow, and accounting for the future development in the area. A hydrologic analysis which consists
of (a) delineation of catchment area and (b) use of either Rational Method or Unit Hydrograph
Method is also used. Finally, a hydraulic analysis is performed by use of either Manning‟s
formula or Chezy‟s equation. Unknown topography and a mountainous terrain are factors
considered to make the planning process more challenging. More difficulties arise as one
considers financial matters, availability of materials, political intervention, site conditions and
acquisition of right- of-way. The DPWH uses what they call the “Blue Book” which contains
planning and designing flood control structure and the Design Guide, Criteria Standards Vol II.

Underdrain Systems using RCP usually uses pre-cast concrete and the Rectangular Lined Ditch
uses the conventional cast-in-place concrete. Again, the standards used for these materials can be
found in the Blue Book. In terms of construction, it is easier to construct a Rectangular Line Ditch
because it only involves an excavation, and from there one can start the construction of the actual
ditch. Factors that make the construction coincide with those in factors considered in planning:
irregular topography, and the location of the site. Other factors to be considered are the

124
availability of the materials going to be used in construction, and the existing pipelines (e.g. gas,
sewer and water supply) .

Rectangular Line Ditches commonly use 10mm Φ bars for rebars, class A concrete mix, a
concrete mixer, a backhoe, a rebar cutter, and a plate compactor. However, it must be noted that
the diameter for the rebars vary depending on the structural capacity of the ditch. Underdrain
Systems using RCP, on the other hand, commonly uses 0.60 m, 0. 90m, 1.12m and 1.50m Φ
Reinforced Concrete Pipe diameter and 10mm Φ, 12mm Φ and 18mm Φ rebar dimensions. It
utilizes a concrete mixer and a plate compactor, and uses early strength concrete. A Rectangular
Lined Ditch can be constructed in 5 days per linear meter while the RCP can be constructed in 10
days per linear meter.

In terms of manpower, the Rectangular Lined Ditch uses less manpower as it has lesser
excavation works. The two systems rely heavily on equipment. When asked to give an estimate
number of manpower required for the two systems, it appears that the Lined Ditch uses at least 4
laborers/ linear meter and the RCP uses 7 laborers/linear meter.

As for the maintenance of the systems, the Lined Ditch has an advantage because of its
accessibility. Drainage networks are usually maintained through de-clogging. One factor to be
considered when maintaining drainage networks is where to put all the silts and waste.

Finally, from the interviews conducted, most engineers say that the Lined Ditch is more
applicable for rural settings and the RCP for urban settings. As Niog, Bacoor, Cavite is seen to be
heavily urbanized in the future, the researches therefore consider the RCP fitting for it.

5 Conclusions
1. From the survey and interview conducted, the following data have been concluded: In
terms of planning, it appears that the Rectangular Lined Ditch is more advantageous due
to its simplicity and because it uses lesser land area than the Underdrain System.
However, rhe Underdrain System using RCP has more runoff capacity and its cross
sectional dimensions are more suitable and advantageous. Also, when it comes to the
applicability depending on the geography and land use, it seems that Underdrain Systems
using RCP are more beneficial especially for urban area.

125
On construction and installation procedures, generally, Rectangular Lined Ditches have
simpler construction methodology. However, it must be noted that despite the ease in
procedure, the dimension still matters when it comes to the time needed to complete the
construction. As for the manpower required, it can be concluded that construction needs
20-60 people depending on the scale of project. Finally, when it comes to maintaining
these drainage networks, it appears that the Rectangular Lined Ditches are much easier to
preserve.

2. On to the results from the correlation of various parameters and the usage of different
empirical formulas, it can be ascertained that for the cross-sectional area of 0.125 to 2.010
shows that Rectangular Lined Ditch is the effective system to use. On the other hand, the
rest of the cross-sectional area shows that Underdrain system using RCP is the effective
system to use. The results are the same for all the comparisons and correlations made.

3. Finally, The equivalent area starting from 0.125 to 3.463 shows that Rectangular Lined
Ditch has the lesser cost between the two systems, thus Rectangular Lined Ditch is the
best system to be used. On the other hand, the rest of data shows that the Underdrain
System using RCP has the lesser cost, thus, that system is best to use for that range.

References

Abdellatif, Atherton, Alkhaddar & Osman (2013). Linking Climate Change to Water Sector: A
Case Study of Urban Drainage System. Retrieved from http://www.climate-impacts-
2013.org/files/cwi_abdellatif.pdf

A. König, J. J. Linde, O. Mark, & G. Svensson, (2008). Analyses and Adaptation of Climate
Change Impacts on Urban Drainage Systems. 11th International Conference on Urban Drainage,
Edinburgh, Scotland, UK, 2008

B. Clarke, D. M. Hultstrand & T.W. Parzybok, (2011). Average Recurrence Interval of Extreme
Rainfall in Real-time. Retrieved from http://www.earthzine.org/2011/04/19/average-recurrence-
interval-of-extreme-rainfall-in-real-time/

126
Blendermann (1979). Controlled Storm Water Drainage. 200 Madison Avenue New York:
Industrial Press Inc.

T. Daniell & G. Tabios III (2008). Asian Pacific FRIEND Rainfall Intensity Duration Frequency
(IDF) Analysis for the Asia Pacific Region. Retrieved from
http://unesdoc.unesco.org/images/0018/001802/180223E.pdf

Cimorelli et al (2013). Optimal Design of Rural Drainage Networks. J. Irrig. Drain Eng., 139(2),
137–144. Retrieved from http://ascelibrary.org/doi/abs/10.1061/(ASCE)IR.1943-4774.0000526

Environment Solutions (2014). Complete Confidence in One Solution Unmatched Protection


Unparalleled Technology. Retrieved from
http://www.solterraph.com/Environment%20Solutions%20Brochure.pdf

Grigg, Hiller & Riordan (1978). Development of a Drainage and Flood Control Management
Program for Urbanizing Communities-Part II. Retrieved from
http://www.cwi.colostate.edu/publications/cr/86.pdf

J. Marsalek & W. E. Watt (1984). Design storms for urban drainage design. Canadian Journal of
Civil Engineering, 1984, 11(3): 574-584, 10.1139/l84-075. Retrieved from
http://www.nrcresearchpress.com/doi/abs/10.1139/l84-075

K. Berggren (2008). Indicators for urban drainage system-assessment of climate change impacts.
11th International Conference on Urban Drainage, Edinburgh, Scotland, UK, 2008

R.S.V Teegavarapu (2012). Floods in a Changing Climate: Extreme Precipitation. Retrieved from
http://books.google.com.ph/books?id=KJa6tEGMzwQC&pg=PA3&dq=floods+rainfall&hl=en&s
a=X&ei=AtkOU4jHAoqjigedsYDwAw&ved=0CDUQ6AEwAw#v=onepage&q=floods%20rainf
all&f=false

S. Duchesne & A. Mailhot, (2010). Design Criteria of Urban Drainage Infrastructures under
Climate Change. J. Water Resour. Plann. Manage. 136(2), 201–208.

United States Environmental Protection Agency (2007) Condition Assessment of Collection


Systems. Science BRIEF. Retrieved from http://nepis.epa.gov/Adobe/PDF/60000GYY.pdf

United States Environmental Protection Agency (2007). Condition Assessment of Collection


Systems. Science BRIEF. Retrieved from http://nepis.epa.gov/Adobe/PDF/60000GYY.pdf

127
APPENDIX C

PANEL MEMBER ASSESMENT

128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
APPENDIX D

ENGLISH EDITOR ASSESSMENT

153
154
155
156
157
158
159
160
161
162
163
164
APPENDIX E

RECEIPTS

165
166
167
APPENDIX F

POSTER

168
169
APPENDIX G

OTHER FORMS

170
171
172
APPENDIX H

STUDENT REFLECTION

RESUME

173
BISNAR, Jefferson Bill G.,

CE-5/2010105831

Reflection

Our Thesis entitled, Optimization of Roadside Drainage System: A Comparative Analysis

of Rectangular Lined Ditch and Underdrain system using RCP, is one of the most difficult

requirements that I needed to complete in order to finish my student life here in this Institute. I

have experienced a lot of things in order to finish the whole thesis ranging from the interactions

with professionals to the creation of various media involved for the thesis. There is so much

brainstorming of various fields in order to find a good topic in order to study. There are various

ups and downs during the creation of the thesis. I can say that it is a mixed of internal factors such

as lack of vigor, lack of time and external factors such as difficulty in data gathering. But despite

all of that, I and my thesis mates finally reached the end. I learned that you can finish something

even though you are doing it in a slow rate as long as it is effective. I also learned that the key for

completing these kinds of works is to have a good working relationship with your thesis mates.

You must remember that all of you must be on the same page in order to come up with

something. I think that I and my thesis mates managed to achieve these conditions.

As we reached the end of this thesis, I would like to thank my thesis mates first for helping

in not only in the technical side of this study but as well as the light side of it. I would also like to

thank the people who helped us to complete this study, starting from the faculty, the advisers and

the professionals outside the Mapua Institute of Technology. And lastly, I would like to thank god

for helping us finish this study and giving me this opportunity to work with my current thesis

mates who I have so much fun working with.

174
De Dios, Kierwin S.

CE-5/2010102145

Reflection Paper

After finishing our thesis, I was able to gain new knowledge and understand a lot of things

in applying the theories we learned in Mapua Institute of Technology, especially in the field of

hydraulics, and hydrology. It is very challenging to finish our thesis while we are taking our

correlation subject (mock board). Our Thesis entitled, “Optimization of Roadside Drainage

Systems: A Comparative Analysis of Rectangular Lind Ditch and Underdrain System using

RCP”, is quite different compared to other thesis of our colleagues because the thesis of the

groups is a qualitative research. At first, it very hard to choose which parameters the group will

correlate, so, the group seek the advice of Prof. Nazareno and Prof. Gonzales, for she is one of the

potential panel for our thesis. I have experienced a lot of things in order to finish the whole thesis

ranging from the interactions with professionals to the creation of various media involved for the

thesis. The group gathered different data from different government departments and offices.

With that, the group gained knowledge on how the departments and offices conduct their work

with respect to drainages.

I am grateful to the persons who helped the group in conducting the thesis, especially Prof.

Nazareno, Prof. Gonzales and the engineers in DPWH. I would also like to express my gratitude

to my groupmates for all the things they have done for the thesis. The group had different

problems as the group conduct the thesis but the group managed to finish the thesis.

175
Profitana, Patricia B.

CE-5/ 2010170318

Student Reflection

As a Batch 2010 student, we were the first ones to encounter the research type of thesis,

which is different from the design-based that we were expecting. On our first day of thesis class,

imagine our surprise when we were told that batch 2010 will be working with their own batch and

that our thesis will no longer be comprised of the design-based we were preparing for terms prior.

We had to rethink thesis topics in a matter of one week. Compared to our previous ideas, these

shotgun ideas are nothing. Nevertheless, we had to work from there and be able to come up with a

sound thesis. It was hard work and it cost a lot of money. Most times, our group was lost with

what step we were going to take next. We are usually unsure of our actions and whether the steps

we will be taking are going to be included in the final thesis. I just wish there were more eco-

friendly ways to conduct the defense proper. With the amount of paper that are being turned in,

and being thrown away once the revisions are in order, it just breaks my heart and wallet to see

them all go to waste. Finally, I would like to express my gratitude to all the people who have

helped us achieve this feat, especially to the professors who took the time and actually read our

thesis before asking us to do a revision. I appreciate the effort to make our paper better. I hope

more professors take the time to read the paper and actually point out what is there to improve. I

also hope that the advisers take the time to sit down with us and do a writeshop of sorts, like what

professors and thesis advisers of other universities. If the faculty wants to see better theses, they

have to work with the students somehow and encourage them to think and actually pursue a topic

they are interested in.

176
JEFFERSON BILL G. BISNAR
Blk. 10 Lt. 4 Kamagong St. Narra Homes Subd. Pag-asa I
Imus, Cavite
Cellphone No.: 09274644682
Emial: bisnar_jeff@yahoo.com

OBJECTIVES
To able to work as an intern as a Civil Engineering student in a career oriented and challenging
environment where I can utilize my skills and knowledge on the field.

EDUCATIONAL BACKGROUND
College
Mapua Institute of Technology 2010-present
Muralla St., Intramuros, Manila
BS Civil Engineering

High School
Imus Institute 2006-2010
Imus, Cavite

Elementary
Cachapero Learning School 2000-2006
Imus, Cavite

PERSONAL INFORMATION:
Place of Birth: Makati City
Birthday: July 17, 1993
Age: 21
Gender: Male
Citizenship: Filipino
Civil Status: Single
Religion: Roman Catholic

AFFLIATIONS
 American Concrete Institute of the Philippines – Mapua Institute of Technology Student
Chapter
Business Manager
July 2013 – July 2014
 Philippine Institute of Civil Engineers – Mapua Institute of Technology Student Chapter
Member
May 2013 - Present

177
EXTRA – CURRICULAR ACTIVITIES
 Bridge Building Competition
Mapua Institute of Technology
3rd Place
March 2014

SKILLS
 Proficient in English and Tagalog
 Computer Literacy (AutoCAD, STAAD, Microsoft Office Applications)
 Fast Learner
 Trained to work under pressure
 Highly motivated and works positively towards task

EXPERIENCE
 Avida Towers 34th Street BGC – Makati Development Corporation
On the Job Trainee
August 04, 2014 – September 13, 2014

SEMINARS AND CONFERENCES


 NSCP Orientation and Concrete Technology
October 29, 2012
 Mapua Institute of Technology Buildings for Tomorrow: Designing and Constructing
Sustainable Buildings
July 17, 2013
Mapua Insitute of Technology
 National Civil Engineering Symposium 2013
September 2013
University of the Philippines Diliman, Quezon City
 Building Information Modelling (BIM)
October 23, 2013
Mapua Institute of Technology, Intramuros, Manila
 NSCP Orientation
December 5, 2013 (12:00P.M. – 6:00 P.M.)
Mapua Insititute of Technology, Intramuros, Manila
 SPACE: International Conference on Resilient Structures
April 2014
SMX Convention Center, SM Aura, Taguig City
 SHIMIZU: Discovering New Solutions Towards Disaster Resilient and Sustainabity-
Oriented Philippine Built Infrastructures
July 18, 2914
Mapua Institute of Technology Gymnasium Intramuros, Manila

178
KIERWIN S. DE DIOS
Blk 13 Lot22 Phase4 Soldiers Hills 4 Molino, Bacoor, Cavite
Telephone: +639055828547 (mobile)
Email: dediokierwin_06@yahoo.com

Objective: .

To be able be a Civil Engineer. Seek exposure to commercial development projects, including all phases
of construction, (i.e. planning, cost analysis, construction management, etc.) and take challenging,
creative and diversified projects.

Education: .

2010 – 2014 Mapua Institute of Technology


Muralla St. Intramuros, Manila
Bachelor of Science in Civil Engineering

2006 – 2010 St. Joseph’s Academy


Padre Diego Cera Las Piñas
Secondary Education

Skills: .

 Efficient in using Microsoft Office applications such as Word, Excel, and PowerPoint.
 Fluent in English and Filipino language.
 Skillful in conducting presentations and reports
 Knowledgeable in using design programs such as STAAD, ETABS, and AutoCAD
 Has good interpersonal communication skills and has the ability to work effectively in a
team environment as well as independently.
 Good leadership skills
 Highly motivated and works positively towards task.
 Can manage multi-tasking and usually works ahead of time.
 Mentoring/Teaching Skills

Work Experience: .

August 2014 – September 2014 ON THE JOB TRAINING


Department Of Public Works And Highways - South Manila
Engineering District
Mac Arthur Highway Km. 16+322 to Km. 17+011

179
July 2014 – August 2014 ON THE JOB TRAINING
Ironcon Builders and Development Corporation
Aspen Tower

May 2014 - July 2014 ON THE JOB TRAINING


Alpa Plumbing Works, Inc.
Avida Towers Centera

Affiliations: .

 School of Civil, Environmental and Geological Engineering Student Council


Internal Vice President
2013-2014

 Center for Student Advising


Peer Adviser for Mathematics and Physics
2012-2014

 Honor Society of Mapua


Member
2013 – 2014

 American Concrete Institute -Philippines (Mapua Student Chapter)


Member
2012 – 2014

 Philippine Institute of Civil Engineers- Mapua Student Chapter


Member
2013-2014

 Mapua Judo Club


Member
2012-2014

Attainment: .

 August 2014 Delegate


9th Aboitiz Future Leaders Business Summit
Aboitiz Equity Ventures, Inc.

 March 2014 Champion


Bridge Building Competition 2014
Philippine Institute of Civil Engineers-MIT Student Chapter

References are available upon request .

180
PLACE AND DATE OF BIRTH: Manila | 04 October 1993
ADDRESS: 11 Buliran St., Concepcion, Marikina City
PHONE: 09065444308
EMAIL: patriciaprofitana@yahoo.com

2014 Bachelor of Science in Civil Engineering, Mapua Institute of Technology,


Manila

2010 High School, Philippine School Doha, Qatar


Third Honorable Mention
Third Yr – Fourth Yr

2008 High School, Marikina Science High School, Marikina City


First Yr – Second Yr

2013-2014 President: School of Civil, Environmental and Geological Engineering


Student Council

Member: Philippine Institute Of Civil Engineers – Mapua Institute of


Technology Student Chapter

Member: The Eastern Asia Society for Transportation Studies -


Transportation Science Society of the Philippines - Mapua Student
Chapter

Member: Honor Society of Mapua

181
2012-2013 Internal Vice President: American Concrete Institute Philippines –
Mapua Student Chapter

2011-2012 Business Manager: Speech Communication Organization of the


Philippines

2013 Building Information Modeling, November 27, 2013


(American Concrete Institute – Mapua Student Chapter)

2014 Student Conference on Transportation Research,


January 27-30, 2014
(EASTS-TSSP – Mapua Student Chapter)

IDEA Global Entrepreneurship Symposium, March 14-17, 2014


(PHILDEV INC.)

May-
August 2014 Practicum
Manila Bay Resorts Project
Paranaque
Hilmarc’s Construction Corporation

August-
September 2014 Practicum
Rehabilitation of Roxas Blvd., Manila
Manila
Department of Public Works and Highways - NCR

Engr. Rodolfo Mendoza Civil Engineer / Professor

182
+639175816215

Engr. Juan Paulo Nazareno Civil Engineer/ Professor


+639172594805

183

Das könnte Ihnen auch gefallen