Beruflich Dokumente
Kultur Dokumente
ON BUILDING
By
NIAZ ALI
August, 2017
CERTIFICATE
This is to certify that, this report of the industrial training is a benefited report of the work
done by NIAZ ALI, in partial fulfillment of requirement for award of degree in Bachelor of
Technology in Civil Engineering from CECOS University Peshawar.
________________________ __________________________
ENGR. SHAMS UL ISLAM ENGR. SULAIMAN
Assistant Professor Lecturer
Department of Civil Engineering Department of Civil Engineering
CECOS University Peshawar CECOS University Peshawar
2
Experience Certificate
3
Author's Declaration
I hereby declare that I am the sole author of this thesis. This is a true copy of the thesis,
including any required final revisions, as accepted by my examiners.
4
Abstract
The aim of my research work is to know the practical site work which involves local method. My
internship work is based on building site1.
For that particular purpose I performed almost different site work and tests that related to site.
The inspection of steel work and how to find the estimate of form work. The form work is measure
in ft2 and m2.
5
Acknowledgement
First of all, thanks to Almighty Allah who enabled me to complete my research work.
The author would like to express his utmost gratitude to Chief Executive of Muslim Enterprises
for providing opportunity to author to pursue the engineering training as a partial fulfilment of
the requirement for the degree of Bachelor of Engineering. I am thankful to Engr. Suliaman
Khan and Engr Shams Ul Islam, who guided me and helped me in each and every aspect to
compile my internship work successfully. I am obliged of Masood Ahmad (Director of Muslim
Enterprisses) for his support throughout my research. I am appreciative to Muhammad Rahim
(fianance Director of Muslim Eterprisses) and Qazi Abdul Munib (Construction Incharge of
Muslim Enterprisses) who assisted me in accomplishing my research
6
Dedication
family members
And
To all my teachers
7
Table of Contents
CERTIFICATE ......................................................................................................................... 2
Abstract ..................................................................................................................................... 5
Acknowledgement .................................................................................................................... 6
Dedication ................................................................................................................................. 7
Chapter 1 ................................................................................................................................. 14
Chapter 2 ................................................................................................................................. 16
Introduction ............................................................................................................................. 20
9
Figure3.3 Coarse Aggregates .......................................................................................... 27
3.3.5 Steel (60,000 psi Grades steel bars used in our project) ...................................... 28
10
3.10 Concrete Test............................................................................................................... 37
3.13 Following are the Procedure for Compressive Strength Test of Concrete Cubes ....... 40
3.13.8 Precautions............................................................................................................ 42
11
3.13.13 Result .................................................................................................................. 43
Chapter 4 ................................................................................................................................. 46
Chapter 5 ................................................................................................................................. 47
Conclusions ............................................................................................................................. 47
References ............................................................................................................................... 48
12
List of Figures
List of Tables
Table 3.1 Compressive strength of different grades of concrete at 7 and 28 days ................. 44
Table 3.2 Minimum compressive strength.............................................................................. 44
13
Chapter 1
1.1 Introduction
Practical training or Industrial training is a mandatory course for all degree students of CECOS
University Peshawar. It is a requirement to fulfil the course in order to complete the degree as
well as graduate from the university. The training refers to work experience that is relevant to
professional development prior to graduation. For CECOS University students; a 12 Credit
hour’s period is allocated for training at locations chosen by students themselves. No restriction
is imposed on them whether they want to work in government agencies or private
organizations.
For this semester, the trainee, NIAZ ALI (CU-990-2013), has started working in the
MUSLIM ENTERPRISES PVT LTD Peshawar from the Nov 2016 until the 25th of April
2017.
vii. Contact with professional realities that complement, enhance, confirm, and reshape
knowledge
14
viii. Chance for career choice through exposure to different work environments and
technologies
ix. Shortened access to productivity due to practical experience gained during mentored
training
x. Increased chances of finding work short time after graduation: employers are ready to hire
those who have acquired the practical flair during their Industrial internships.
4. Regular / irregular Plots area calculated by using different formula like triangles etc.
7. Boundary line excavation by using contractor labours and the some purpose using excavator.
15
Chapter 2
2.1 Introduction
16
2.2 History
Muslim Enterprises company started their first project in 2005 which is known as Muslim
Town Phase 1 located opposite to city university, dalazak road Peshawar. This town consists
of 95 kanal area and this project is completed fully in one year.
Beside this project this company launch the second project in 2007 with the name of Muslim
City located on tarnab farm main g.t road Peshawar, about 400 kanal area which is completed
within 2 years.
In 2008 this company lauch the huge project which is known as Muslim Education City
Azakhel Nowshera.
This area consists of 2500 kanals area. This project also lauch the Muslim university and this
project is still in running.
After a big achievement they launch the Officer Housing Society Phase I located in durran
pur norther bypass,which consists of 500 kanal area and this project completed in two years.
After that this company take another step for Muslim Town Phase II located opposite to
Peshawar institute of technology dalazak road Peshawar.
This project cover the area of 70 kanal area. This project completed in 18 months.
After a great success they launch the Officer Housing Society Phase II located in Mulazai
warsak road Peshawar. This project cover the area of 400 kanals. This project is still in running.
And similarly they lauch the other project with the name of Muslim Villas located on Rehman
Abad, Dalazak road Peshawar. This area consists of 80 kanal area.
17
2.3 COMPLETED PROJECT
III Muslim Town Phase. II Opposite to Peshawar institute of Technology dalazak road
Peshawar.
IV Officer Housing Society Phase. I Doran Poor Near Narthern bypass Dalazak Road
Peshawar
I Officer Housing Society Phase II Near Police Choki Mulazai Warsak Road Peshawar
2 Muslim Villas Near Shah Poor Police Choki Rehman Abad Dalazak Road Peshawar
18
2.5 Muslim Enterprises Head Office ,
19
Chapter 3
Tasks Assigned
Introduction
This consist s of panels fabricated out of thin steel plates stiffened along the edges by small
steel angles. The panel units can be held together through the use of suitable clamps or bolts
and nuts. The panels can be fabricated in large number in any desired modular shape or size.
Steel forms are largely used in large projects or in situation where large number reuses of the
shuttering is possible. This type of shuttering is considered most suitable for circular curved
structures.
3.1 Structure
The complete structure is of RCC frame structure in M-15 concrete.
Other Specifications
(a) Expansion &Contraction joint are provided.
(b) Bitumen treatment are provided at the roof.
(c) Water proofing is done by using chemical water proofing materials e.g. Penybar etc.
The factor to be considered while selecting the building site are as follows:-
Reconnaissance survey: the following has been observed during reconnaissance survey of the
site.
Site is located nearly
The site is very clear planned without ably dry grass and other throne plats over the entire
area.
No leveling is require since the land is must uniformly level
The ground is soft.
Labor available nearby the site.
Houses are located near by the site.
Detailed survey: the detailed survey has been done to determine the boundaries of the
required areas of the site with the help of Total station and G.P.S
21
3.2 Classification of Buildings Based on Occupancy
These building include any building in which sleeping accommodation provide for normal
residential purposes, with or without cooking and dining facilities. It includes single or multi-
family dwellings, apartment houses, lodgings or rooming houses, restaurants, hostels,
dormitories and residential hostels
22
3.2.3 Institutional Buildings
These buildings are used for different purposes, such as medical or other treatment or care of
persons suffering from physical or mental illness, diseases or infirmity, care of infants,
convalescents or aged persons and for penal detention in which the liberty of the inmates is
restricted. Institutional buildings ordinarily provide sleeping accommodation for the
occupants.
23
3.2.9 Hazardous Buildings
These buildings are used for the storage, handling, manufacture or processing of highly
combustible or explosive materials or products which are liable to burn with extreme rapidly
and/or which may produce poisonous elements for storage handling, acids or other liquids or
chemicals producing flames, fumes and ex plosive, poisonous, irritant or corrosive gases
processing of any material producing explosive mixtures of dust which result in the division
of matter into fine particles subjected to spontaneous ignition.
Cement
Aggregates
Water
Steel
Bricks
Tiles
Admixtures
24
Several types of Portland cement are available with the most common being called ordinary
Portland cement (OPC) which is grey in color, but a white Portland cement is also available.
We also used Portland cement in our project because of many good quality and also
availability everywhere. Also cheaply.
3.3.2 Aggregates
Fine Aggregates :- “ Fine aggregates is defined as material that will passed sieve No 4
And will most part retained on sieve no 200.
Types of fine Aggregates
Sand :- The first types of fine aggregate is sand . sand is little particle of silica.
25
Surkhi
Dust Stone
Cinder
Stone Ballast
Clinker
26
Brick Ballast
Gravel
27
Figure 3.4
3.3.4 Water
Portable water used in mixing of concrete. And also used for curing, but free from alkaline,
acidity, fat, and other injurious substances
The PH value shall not be less than 6.
3.3.5 Steel (60,000 psi Grades steel bars used in our project)
Reinforced concrete was designed on the principle that steel and concrete act together in
resisting force. Concrete is strong in compression but weak in tension. The tensile strength is
generally rated about 10 percent of the compression strength. For this reason, concrete works
well for columns and posts that are compression members in a structure. But, when it is used
for tension members, such as beams, girders, foundation walls, or floors, concrete must be
reinforced to attain the necessary tension strength.
Steel is the best material for reinforcing concrete because the properties of expansion for both
steel and concrete are considered to be approximate] y the same; that is, under
normal conditions, they will expand and contract at an almost equal rate.
NOTE: At very high temperatures, steel expands more rapidly than concrete and the two
materials will separate.
28
Figure 3.5 Steel
3.3.6 Bricks
A brick is a block or a single unit of a kneaded clay-bearing soil, sand and lime, or concrete
material, fire-hardened or air-dried, used in masonry construction. Light weight bricks (also
called "lightweight blocks") are made from expanded clay aggregate.
29
Figure 3.6 Bricks
30
3.3.7 Reinforcement Cement Concrete (RCC1:2:4)
Reinforced concrete is one of the most widely used modern building materials. Concrete is an
“artificial stone” obtained by mixing cement, sand, and aggregates with water. Fresh concrete
can be molded into almost any shape, giving it an inherent advantage over other materials. It
became very popular after the invention of Portland cement in the 19th century; however, its
limited tension resistance initially prevented its wide use in building construction. To
overcome poor tensile strength, steel bars are embedded in concrete to form a composite
material called reinforced concrete (RCC).
32
the specified 28 day cube strength of mix in N/mm2. The mixes of grades M10, M15, M20 and
M25 correspond approximately to the mix proportions (1:3:6), (1:2:4), (1:1.5:3) and (1:1:2)
respectively.
3.6.2 Workability
The degree of workability required depends on three factors. These are the size of the section
to be concreted, the amount of reinforcement, and the method of compaction to be used. For
33
the narrow and complicated section with numerous corners or inaccessible parts, the concrete
must have a high workability so that full compaction can be achieved with a reasonable amount
of effort. This also applies to the embedded steel sections. The desired workability depends on
the compacting equipment available at the site.
3.6.3 Durability
The durability of concrete is its resistance to the aggressive environmental conditions. High
strength concrete is generally more durable than low strength concrete. In the situations when
the high strength is not necessary but the conditions of exposure are such that high durability
is vital, the durability requirement will determine the water-cement ratio to be used.
3.7 Formwork
Formwork is the term given to either temporary or permanent molds into which concrete or
similar materials are poured. In the context of concrete construction, the falsework supports
the shuttering moulds.
Types of Formwork
Timber Formwork
Plywood Formwork
Steel Formwork
It should be
well seasoned
light in weight
Timber used for shuttering for exposed concrete work should have smooth and even surface
on all faces which come in contact with concrete.
35
3.7.2 Plywood Formwork
Resin bonded plywood sheets are attached to timber frames to make up panels of required
sizes. The cost of plywood formwork compares favourably with that of timber shuttering and
it may even prove cheaper in certain cases in view of the following considerations:
It is possible to have smooth finish in which case on cost in surface finishing is there.
By use of large size panels it is possible to effect saving in the labour cost of fixing and
dismantling.
Number of re-uses are more as compared with timber shuttering. For estimation purpose,
number of reuses can be taken as 20 to 25.
Shuttering
Provision of camber
36
3.9 Order and method of removing formwork
The sequence of orders and method of removal of formwork are as follows:
Shuttering forming the vertical faces of walls, beams and column sides should be removed
first as they bear no load but only retain the concrete.
Shuttering forming soffit of beams, girders or other heavily loaded shuttering should be
removed in the end.
Rapid hardening cement, warm weather and light loading conditions allow early removal of
formwork. The formwork should under no circumstances be allowed to be removed until all
the concrete reaches strength of at least twice the stresses to which the concrete may be
subjected at the time of removal of formwork. All formworks should be eased gradually and
carefully in order to prevent the load being suddenly transferred to concrete.
Compression Test
37
Figure 3.9 Slump Test
38
5. The mould is then removed from the concrete immediately by raising it slowly and
carefully in a vertical direction.
3.10.3 Calculation
The slump is measured immediately by determining the difference between the height of the
mould and that of the highest point of specimen.
3.10.4 Report
Report the slump in terms of millimeters to the nearest 5 mm of subsidence of the specimen
during the test.
After completion of the slump test, to get an idea on cohesiveness of concrete, tap
slightly the outer perimeter of the slumped concrete. If it subsides further, then it is an
indication of good quality concrete having required cohesiveness. But if it gets collapsed
or shears away then the concrete lacks cohesiveness and this is an indication of poor
quality concrete.
39
3.11 Compressive Strength of Concrete Cubes
This concrete is poured in the mould and tempered properly so as not to have any voids.
After 24 hours these moulds are removed and test specimens are put in water for curing. The
top surface of these specimen should be made even and smooth. This is done by putting
cement paste and spreading smoothly on whole area of specimen.
These specimens are tested by compression testing machine after 7 days curing or 28 days
curing. Load should be applied gradually at the rate of 140 kg/cm2 per minute till the
Specimens fails. Load at the failure divided by area of specimen gives the compressive
strength of concrete.
3.13 Following are the Procedure for Compressive Strength Test of Concrete
Cubes
3.13.1 Apparatus
Compression testing machine
40
3.13.3 Specimen
6 cubes of 15 cm size Mix. M15 or above
3.13.4 Mixing
Mix the concrete either by hand or in a laboratory batch mixer
(ii)Add the coarse aggregate and mix with cement and fine aggregate until the coarse
aggregate is uniformly distributed throughout the batch
(iii)Add water and mix it until the concrete appears to be homogeneous and of the desired
consistency
3.13.6 Sampling
(i) Clean the mounds and apply oil
(ii) Fill the concrete in the molds in layers approximately 5cm thick
(iii) Compact each layer with not less than 35strokes per layer using a tamping rod (steel bar
16mm diameter and 60cm long, bullet pointed at lower end)
3.13.7 Curing
The test specimens are stored in moist air for 24hours and after this period the specimens are
marked and removed from the molds and kept submerged in clear fresh water until taken out
prior to test.
41
3.13.8 Precautions
The water for curing should be tested every 7days and the temperature of water must be at
27+-2oC.
3.13.9 Procedure
(I) Remove the specimen from water after specified curing time and wipe out excess water
from the surface.
(IV) Place the specimen in the machine in such a manner that the load shall be applied to the
opposite sides of the cube cast.
(V) Align the specimen centrally on the base plate of the machine.
(VI) Rotate the movable portion gently by hand so that it touches the top surface of the
specimen.
(VII) Apply the load gradually without shock and continuously at the rate of
140kg/cm2/minute till the specimen fails
(VIII) Record the maximum load and note any unusual features in the type of failure.
3.13.10 Note
Minimum three specimens should be tested at each selected age. If strength of any specimen
varies by more than 15 per cent of average strength, results of such specimen should be
rejected. Average of there specimens gives the crushing strength of concrete. The strength
requirements of concrete.
42
3.13.11 Calculations
Size of the cube =15cm x15cm x15cm
Area of the specimen (calculated from the mean size of the specimen )=225cm2
=……………………….Kg/cm2
3.13.12 Report
a) Identification mark
b) Date of test
c) Age of specimen
f) Appearance of fractured faces of concrete and the type of fracture if they are unusual
3.13.13 Result
Average compressive strength of the concrete cube = 2100 Psi (at 7 days)
Average compressive strength of the concrete cube = 3000 Psi (at 28 days)
43
3.14 Percentage Strength of Concrete at Various Ages
The strength of concrete increases with age. Table shows the strength of concrete at different
ages in comparison with the strength at 28 days after casting.
3.15 Foundation
The Lowest artificially build part of structure which transmits load to the underneath ground
is called foundation.
There are many Types of Foundation.
Raft Foundation
44
Caisson foundation
Grillage Foundation
Pile Foundation
Footing.
Raft foundation:- Here is Raft Foundation is used in Al-Falah Tower, Kohat road Peshawar.
Depth up to : 38 inch.
Steel Bar No# 7 is used for Distribution & Main Bar and also top & Bottom Layer.
45
Chapter 4
4.1 Introduction
Alhamdulillah I don’t faced any kind of issues during my internship but only one thing I noted
that all the equipments are old in site and some of them are useless therefore, I recommend that
the university should be upgrade the internship programs and make a link with government
department just like COMUNICATION AND WORKS DEPARTMENT, P.W.D, WAPDA,
PDA, MES etc.
That the student achieve there main goal in field work.
Concrete is not according to ACI stander.
Contractor always try to earn more profit which affect the quality of work.
Some reinforcement details and other architecture details are missing in drawing.
46
Chapter 5
Conclusions
5.1 Conclusions
My internship conclusion is that, that the field site work is easy than theoretical. But theory
helps us to correct the practical work by easy way. Theory is the way that I know about
practical. I achieve coordination with people. I familiar with marketing strategy. How to buy
products?
My internship report is totally based on construction buildings especially on practical side.
These guidelines provide practical skill to know about site work
47
References
http://www.pnas.org/content/111/52/18484.full
48